Sample Task Order
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 09_Jan_Draft_RFP_Site_Visit_Sign_In_List.pdf | ||
| W912P4-13-R-0001.pdf | ||
| Haz_Waste_and_Disposal_SCA_Wage_Determination.pdf | ||
| APP_SSHP_Checklist_word_doc_tnr_w_Be_SLDA_PWS_20Sep2012_RHW.doc | DOC document | |
| DBA_Wage_Determination.pdf | ||
| Eng_Form_93.pdf | ||
| SLDA_GFP_Inventory.xlsx | XLSX spreadsheet | |
| LRB-Crane-CertificateOfCompliance.doc | DOC document | |
| Basic_SCA_Wage_Determination.pdf | ||
| Att_2_-_Labor_Rate_Form.xlsx | XLSX spreadsheet | |
| AT_OPSEC_Cover_sheet.pdf | ||
| LRB-ContractorMonthlyManhourExposureForm.xls | XLS spreadsheet | |
| e33941_w_Instructions.pdf | ||
| NAVFAC_USACE_PPQ.docx | DOCX document | |
| W912P4-13-R-0001.pdf | ||
| Site_Layout.pdf | ||
| UFGS_01_35_26_Feb_12_Gov'l_Safety_Req_SLDA_SOW_PWS_upd_20Sep2012.doc | DOC document | |
| UFGS_01_35_29.13_Jan_2008_SLDA_SOW_PWS_upd_20Sep2012.rtf | RTF text file |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION J
SLDA Sample Project Performance Work Statement (PWS)
| 1.0 | INTRODUCTION |
| 1.1 | General |
This sample project is intended to illustrate work anticipated to be performed at the Shallow Land Disposal Area (SLDA) to enable the Government to evaluate the CONTRACTOR’s proposed costs.
1.2 Contract Type
For this sample project, assume a cost reimbursement task order to perform the activities described in this Performance Work Statement (PWS). It should be noted that development of project work plans will be a fixed price activity under this task order.
2.0 LOCATION
The SLDA is located in Armstrong County, Pennsylvania, about 23 miles (38 km) east-northeast of Pittsburgh, Pennsylvania.
3.0 SITE HISTORY
In 1957, the Apollo Nuclear Fabrication Facility began operations in Apollo, Pennsylvania, under U.S. Atomic Energy Commission (AEC) license No. SNM-145. From 1957 to 1962, the Apollo facility was used for small-scale production of high-enriched uranium (HEU)[footnoteRef:1] and low-enriched uranium (LEU) and thorium fuel. By 1963, most of the Apollo facility was dedicated to continuous production of uranium fuel and, throughout its operation, the facility converted LEU hexafluoride to uranium dioxide, which was used as fuel for commercial nuclear power plants. In 1963, a second product line was added to produce HEU fuel for U.S. Navy propulsion reactors; other operations included analytical laboratories, scrap recovery, uranium storage, and research and development. [1: NRC defines HEU as uranium enriched to at least 20% U-235; LEU has enrichment less than 20% U-235.]
Between 1961 and 1970, Nuclear Materials and Equipment Corporation (NUMEC), who owned both the Apollo Facility and the SLDA, buried process and other wastes from the Apollo plant and possibly from other facilities at the SLDA. According to historical documents, these wastes were reportedly buried in accordance with AEC regulation 10 CFR 20.304, Disposal by Burial in Soil, which was subsequently rescinded in 1981. In 1967, NUMEC stock was bought by Atlantic Richfield Company (ARCO) and the use of the SLDA for radioactive waste disposal was discontinued after 1970. In 1971, the Babcock & Wilcox Company (B&W) acquired NUMEC. In 1997, BWX Technologies, Inc. (BWXT) assumed ownership of the SLDA. Although Babcock & Wilcox Technical Services Group, Inc. is the current owner, ARCO retains environmental liability for the SLDA.
| 4.0 | SITE CONDITIONS |
| 4.1 | Site Description |
The SLDA is located in Parks Township, Armstrong County, Pennsylvania, about 23 miles (38 km) east-northeast of Pittsburgh, Pennsylvania (Attachment 1). The site is currently owned by Babcock & Wilcox Technical Services Group, Inc. (B&W TSG) of Lynchburg, Virginia (formerly BWX Technologies, Inc. (BWXT)) and is maintained under NRC license Spent Nuclear material (SNM)-2001[footnoteRef:2]. The SLDA occupies approximately 44 acres (17.8 hectares) of vacant land and is bounded by the community of Kiskimere to the southwest and vacant undeveloped land to the southeast and northeast. The former Parks Nuclear Fabrication facility site is located adjacent to and northwest of the SLDA. Approximately seventy percent (70%) of the site is vegetated with grasses and annuals. Wooded areas are also present along the northeastern, southeastern, and southern portions of the site. Land use within the vicinity of the SLDA is mixed, consisting of small residential communities, individual rural residences, small farms with croplands and pastures, idle farmland, forested areas, and light industrial properties. [2: The license was suspended by NRC on August 5, 2011 to allow USACE to commence waste excavation and disposal activities.]
4.2 Physical Setting and Climate
The SLDA occupies approximately 44 acres (17.8 hectares) and is bounded by the community of Kiskimere to the southwest and vacant undeveloped land to the southeast and northeast. The former Parks Nuclear Fabrication facility site is located adjacent to and northwest of the SLDA. Currently, the Parks site is vacant land owned by BWX Technologies, Inc. (BWXT). Land use within the vicinity of the SLDA is mixed, consisting of small residential communities, individual rural residences, small farms with croplands and pastures, idle farmland, forested areas, and light industrial properties.
5.0 SUMMARY OF CONTAMINATION
Results of sampling completed at the SLDA indicated that the uranium-contaminated materials placed in the trenches are present in a wide range of enrichments, from less than 0.2 percent by weight U-235 to greater than 45 percent. Sampling and analysis efforts indicate that the radioactive contaminants at the site are generally confined to the immediate vicinity of the trenches, although isolated pockets of radiological surface and subsurface soil contamination are present at the site outside of the immediate vicinity of trench boundaries.
The primary radionuclides of concern (ROCs), expected to be present at the site at activity levels posing a potential risk concern, at the SLDA are, thorium-232 (Th-232), uranium-234 (U-234), uranium-235 (U-235), uranium-238 (U-238), americium-241 (Am-241), plutonium-239 (Pu-239), plutonium-241 (Pu-241), and radium-228 (Ra-228). Radionuclides that may be present, but not necessarily at activities posing a potential risk concern, at the SLDA include but are not necessarily limited to cobalt-60 (Co-60), cesium-137 (Cs-137), plutonium-238 (Pu-238), plutonium-240 (Pu-240), radium-226 (Ra-226), and thorium-230 (Th-230). In addition to radionuclides, various organic and inorganic contaminants, including beryllium, are present at the SLDA.
6.0 SCOPE OF SERVICES
In general, the effort under this PWS consists of remediation work including development of project work plans, waste characterization, excavation, handling, packaging, sampling, transportation, and off-site disposal of contaminated materials at a Government approved facility. Assume 29,550 tons of radiologically contaminated soil and debris greater than the cleanup criteria. For the purposes of this sample project, assume 75% is composed of low level radioactive waste (LLRW) soil, 15% LLRW debris, and 10% mixed waste (i.e., waste that contains both source, special nuclear, or by-product material subject to the Atomic Energy Act of 1954, as amended, and hazardous waste subject to the Resource Conservation and Recovery Act). Also assume 35,900 bank cubic yards of uncontaminated cover and cutback soils will require excavation at the perimeter of the excavation limits to facilitate a safe excavation. This material should be segregated and stockpiled separate from the contaminated soil, pending sample results, and reused as backfill in the excavation if sample results are below cleanup criteria. After excavation of the contaminated soil, post remedial action sampling will be conducted on the base of the excavation to verify that cleanup goals have been attained. After results confirm clean up levels have been attained, the excavation will be backfilled with the non-contaminated excavated material and borrow from an off-site source up to pre-existing grade and seeded and mulched.
7.0 COST ESTIMATE PREPARATION
The CONTRACTOR shall prepare a cost estimate for all tasks described in this sample project PWS. No work plan or write-up is required, however, the bid schedule shall be completed and detailed backup supporting the cost estimate shall be provided. Below is a compilation of assumptions and technical requirements for the CONTRACTOR to consider in development of their cost estimate:
· Development of project work plans as detailed in § 3.8 of Section C of this solicitation.
· Perimeter and worker real time dust monitoring and radiation monitoring is required during all remediation activities.
· Transportation of radiologically contaminated soil above regulatory cleanup goals to a Government approved waste disposal facility.
· Soil intended to be reused as backfill will be segregated into 250 cubic yard piles with composite sampling performed to verify radiation levels are below cleanup criteria. All analytical work will be performed by onsite lab.
· Post remedial action sampling (Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM) Final Status Survey gamma walkover survey) required at the base of excavation. Confirmatory samples shall be analyzed at the onsite laboratory for radiological constituents only.
· Perform post remedial action scanning, as required per MARSSIM.
· Backfill shall be obtained from an off-site borrow source. The top 6-inches shall be topsoil. All backfill and topsoil, from an off-site source, shall be tested for VOC’s, SVOC’s, TAL Metals, Pesticides and PCBs at a rate of one sample per 2,000 BCY or fraction thereof, prior to being delivered to the site. In-place density shall be verified using either ASTM D 1556 or ASTM D 2922.
· Site restoration shall consist of seeding the excavated area with a turf-type tall fescue.
· A closeout report consisting of a Project Completion Report and Lessons Learned Report shall be developed at the completion of the project.
8.0 TASKS
Below is a summary of tasks required under this PWS. The Contractor shall furnish all services, materials, supplies, labor, and travel as required to perform the required work herein. All equipment and miscellaneous items deemed necessary for the performance of this PWS including, but not limited to, computers, projectors, telephones, software, field equipment, etc. shall be provided by the Contractor.
Measurement and payment shall be made as described under each Task description. Tasks 1 through 12 shall use fully loaded rates, excluding fee. CONTRACTOR’s fee for Tasks 1 through 12 shall be included in Task 13. In developing their bid, offerors should assume Government owned equipment is free for use, with the exception of fuel and maintenance costs. In addition, Government owned facilities may be used rent free and only cleaning and maintenance costs should be included in bid. Government provided equipment and facilities are provided as Attachment 4 in Section J of this solicitation.
8.1 Task No. 1 – Preparation of Work Plans
Work shall include preparation of work plans, review and comment by USACE and others as specified by USACE, responses to comments, work plan revisions, reproductions and submittals. All work plans must be approved prior to commencing any site work. For the purposes of this sample project, assume the entire work plan process may take approximately 12 months. Preparation of work plans will be a fixed price activity under this task order regardless of time and amount of revisions for acceptance by USACE.
8.2 Task No. 2 – General Conditions
Work shall include all of the items required in this sample project and base contract that are not explicitly covered under other Tasks. Examples of this are the CONTRACTOR’s cost for insurance, fees, permits, and other similar expenses directly related to the work; project-dedicated supervisory staff and equipment; compliance with specified regulatory requirements; pre-construction and construction period planning, project schedule updates, periodic submittals, reporting, administration; Contractor quality control; field preparation and tasks not included under the other Tasks; environmental protection and spill control; perimeter and worker dust monitoring; project photographs; weather monitoring; weekly inspection during shutdown periods; utility costs; cleaning and maintenance of Government owned property and facilities, office trailer rental, and routine site maintenance. Site physical security is the responsibility of USACE and their security contractor and is not required for this sample project.
8.3 Task No. 3 – Mobilization
Work shall include labor, materials and equipment necessary to transport to the site all personnel and any additional equipment not provided by the Government the CONTRACTOR believes is necessary to complete the work; establish work areas and boundaries; and initial setup, including any temporary facilities not provided by the Government the CONTRACTOR believes are necessary to complete the work.
Work shall also include all preparatory activities necessary for the execution of work following Annual Demobilization as specified in Task No. 11, if necessary. This includes re-mobilization of equipment, materials, and personnel, personnel training, and preparation of work areas and temporary facilities for use. Work includes the set up and calibration of scales and laboratories.
8.4 Task No. 4 – Characterization, Excavation and Stockpiling of Uncontaminated Cover and Cutback Soils Work shall include all labor, materials and equipment associated with characterization, excavation, segregation, and handling of non-contaminated soil. In addition, work shall include composite sampling to confirm it is clean prior to use as backfill.
8.5 Task No. 5 – Characterization, Excavation, Sorting and Storage of Radiologically Contaminated Soil and Debris Work shall include all labor, materials and equipment associated with characterization, excavation, sorting and storage of the radiologically contaminated soil and debris prior to shipment for disposal. In addition, work shall include post remedial action sampling.
8.6 Task No. 6 – Transportation and Disposal of Radiologically Contaminated Soil and Debris Work shall include all labor, materials and equipment associated with loading and transportation of the radiologically contaminated soil and debris to the Government approved disposal facility.
8.7 Task No. 7 – On-Site Laboratory
Work shall include analysis of radionuclides and chemical contaminants (including beryllium, lead, and other metals), utilizing an on-site Department of Defense (DOD) Environmental Laboratory Accreditation Program (ELAP) accredited laboratory.
8.8 Task No. 8 – Backfill and Compaction
Work shall include all labor, materials, and equipment associate with reusing clean excavated on-site material, purchasing backfill from an off-site source, analyzing backfill from an off-site source to verify it is clean, placing and compacting backfill to within 6-inches of the existing grade.
8.9 Task No. 9 – Topsoil Placement
Work shall include all labor, materials, and equipment associated with purchasing topsoil from an off-site source, analyzing topsoil to verify it is clean, placing and rolling topsoil to a thickness of 6-inches to bring the site to final grade.
8.10 Task No. 10 – Seeding and Mulching
Work shall include all labor, materials, and equipment associated with restoring the disturbed area with seed appropriate for local conditions, fertilizer, and straw mulch.
8.11 Task No. 11 – Annual Demobilization
Work shall include all activities necessary to prepare the site for periods of inactivity in which no excavation, processing, and waste transport and disposal will take place. Additionally, all project construction equipment, laboratory equipment, radiological instrumentation, and supplies shall be decontaminated as necessary, radiologically surveyed, and removed from the site or secured within an existing temporary structure at the site. Accumulated waste water stored in tanks shall be treated and discharged, as necessary.
8.12 Task No. 12 – Demobilization
Work shall include performing radiological surveys of the main access road, FSS pad, parking and staging pads, and material processing building, decontaminating equipment, tools, and supplies (including Government owned facilities and equipment) for unrestricted use or else controlled as radioactive material for reuse or disposal, performing verification radiological surveys on the decontaminated equipment and supplies prior to their release from the site (USACE may perform Quality Assurance confirmatory surveys), sampling and analyzing waste generated during the decontamination activities; and removing all site security, access restriction and project signage; restoring project area to near pre-project conditions (CONTRACTOR shall assume areas that have been graded and or improved during remediation shall not be re-graded to pre-project conditions), turning over the project records to USACE; completing all post-work submittals and submit to USACE, and demobilizing all personnel, equipment, tools, and supplies.
8.13 Task No. 13 – Closeout Report
Work shall include preparation of the Project Completion Report. Assume the Project Completion Report will include, at a minimum:
· Table of contents.
· Narrative description of the sequence of work and activities that were accomplished.
· Project lifecycle transportation and disposal cost tracking summary.
· Separate electronic files for each submittal and supporting documentation (i.e., work plans, survey/monitoring/sampling results and analytical records, transportation and disposal records, reports, drawings, etc.).
· Index of file names and file contents, with the file naming convention corresponding to file contents.
· All quality control documentation (i.e., QC reports, meeting minutes, correspondence, etc.).
· Photo documentation of remediation activities.
8.14 Task No. 14 – Fee
Provide proposed total fee for Tasks 1 – 13.
BID SCHEDULE: SLDA Sample Project
| Task |
| Description |
| Unit |
| Quantity |
| Unit Cost |
| Total Cost |
| 1 |
| Preparation of Work Plans |
| LS |
| 1 |
| 2 |
| General Conditions |
| month |
| 36 |
| 3 |
| Mobilization |
| LS |
| 1 |
| 4 |
| Characterization, Excavation and Stockpiling of Uncontaminated Cover and Cutback Soils |
| CY |
| 35,900 |
| 5 |
| Characterization, Sorting, Excavation and Storage of Radiologically Contaminated Soil and Debris |
| month |
| 16 |
| 6 |
| Transport and Disposal of Radiologically Contaminated Soil and Debris |
| tons |
| 29,550 |
| 7 |
| Onsite Laboratory |
| month |
| 16 |
| 8 |
| Backfill and Compaction |
| CY |
| 22,530 |
| 9 |
| Topsoil Placement |
| SY |
| 5,050 |
| 10 |
| Seeding and Mulching |
| acre |
| 2 |
| 11 |
| Annual Demobilization |
| LS |
| 1 |
| 12 |
| Demobilization |
| LS |
| 1 |
| 13 |
| Closeout Report |
| LS |
| 1 |
| 14 |
| Fee |
| LS |
| 1 |
Total Project Cost