W912LR-17-B-0002 Q&A

June 27, 2017

Q0002-0004: What format does the digital bid needs to be submitted?

A: See Solicitation block 13. Additional Solicitation Requirements. Also a digital copy in Portable Document Format (PDF)

Q0002-0005: What procedure will be used to account for rain days that cause work to stop? (weathers delays) A: See Solicitation Section 01000 Item 34. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

Q0002-0006: Are payrolls required to be submitted weekly?

A: Yes, payrolls shall be submitted every week.

Q0002-0007: What are the customary working hours for the contractor at the construction site?

A: Monday to Friday from 0700 hour to 1600 hours. However, if the contractor would like to work outside the above hours, they need to meet with FMS Supervisor and Project COR two weeks in advance for coordination.

Q0002-0008: Is the Puerto Rico Construction General Permit (Permiso General Consolidado) required to start works?

A: Yes. Before to begin any work the contractor shall have the Puerto Rico Construction General Permit.

Q0002-0009: Is a contractor office required at the construction site?

A: Yes

Q0002-0010: We want to know if the pre bid conference made on June 20 was mandatory or we have the opportunity to participate in the bid?

A: Attendance to the Pre-bid conference was not mandatory.