Performance Work Statement (PWS) for
CONSTRUCTION OF NEW WORKING BAY AT FMS #2 IN GURABO
1.0 General
1.1 Scope. The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished, to perform the construction works of the new Working Bay at FMS #2 in Gurabo, Puerto Rico, as defined in this PWS.
1.2 Background. The Puerto Rico National Guard (PRARNG) have a total of four (4) Field Maintenance Shops (FMS) in Puerto Rico. A typical FMS building is a structure that includes a maintenance shop area to repair combat and tactical vehicles, administration area, organizational vehicle parking, wash rack area (open area to wash military vehicles) and privately owned vehicle (POV). The FMS #2 located in Gurabo has a maintenance shop with nine (9) bays, wash rack area with a recently built metal roof and green area currently used as an organizational vehicle parking.
1.3 Period of Performance (PoP). The Period of Performance shall be 270 calendar days (9 months).
1.4 General Information.
1.4.1 Quality Control (QC). The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non- recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO) acceptance in writing of any proposed changes to its
QCP.
1.4.2 Quality Assurance (QA). The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).
1.4.3 Recognized Holidays: The following are recognized US holidays. The contractor shall not perform services on these days.
1.4.3.1 New Year’s Day
1.4.3.2 Martin Luther King, Jr.’s Birthday
1.4.3.3 President’s Day
1.4.3.4 Memorial Day
1.4.3.5 Independence Day
1.4.3.6 Labor Day
1.4.3.7 Columbus Day
1.4.3.8 Veteran’s Day
1.4.3.9 Thanksgiving Day
1.4.3.10 Christmas Day
1.4.4 Place and Performance of Services. The contractor shall provide services between the hours of 0730-1600 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings.
Performance shall be at the PRARNG FMS #2 in Gurabo, Puerto Rico. The contractor, shall at all times, maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Telecommuting is not authorized.
1.4.5 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.6 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.
1.4.7 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, HQDA and/or local policy.
Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.4.8 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the contractor is advised that any time contractor place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.9 Use of Government Information Systems (IS) and access to Government networks is a revocable privilege, not a right. This contract does not require use of Government Information systems.
1.4.10 Protection of Personally Identifiable Information (PII). The contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoDD 5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.
1.4.11 AT Level 1 Awareness Training (AT). All contractor employees requiring access to Army Installations, facilities, and controlled access areas shall complete Level 1 AT within 10 calendar days after contract start date and within 10 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training. Level 1 AT is available at http://jko.jten.mil/courses/atl1/launch.html.
1.4.12 iWATCH Training. The contractor with an area of performance within an Army-controlled installation, facilities or area shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the KO. This training shall be completed within 10 calendar days of contract award and within 10 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training.
1.4.13 OPSEC Training. In accordance with AR 530-1, Operations Security, new contractor employees shall complete Level I OPSEC training within 10 calendar days of http://jko.jten.mil/courses/atl1/launch.html their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training. Level 1 OPSEC training is available at http://cdsetrain.dtic.mil/opsec/.
1.4.14 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.15 Key Control. This PWS does not require handling of keys.
1.5 Special Qualifications. The contractor shall ensure all employees possess all required licenses for operating heavy equipment, welding licenses, Material Handling Equipment (MHE) ie. Forklift and any others, in the performance of this contract. The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified and qualified to provide services.
1.6 Post Award Conference/Periodic Progress Meetings. The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations Subpart 42.5. The KO, Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contacting Officer will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.7 Contract Manager (CM). The contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO within 3 calendar days after contract award. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.8 Identification of Contractor Employees. All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence http://cdsetrain.dtic.mil/opsec/ types (to include signature blocks on e-mail) and dealings with Government or non- Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicle passes shall be returned to the COR within the 10 days of an employee’s departure) or contract completion.
1.9 Combating Trafficking in Persons. The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in any forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The Contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.Contractor shall complete the following online training within 10 calendar days after contract award: Course number is N-US189-HB; available at: http://jko.jten.mil/.
1.10 Contractor Travel: Not authorized on this PWS.
1.11 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership /copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. Provide a copy 10 calendar days after contract completion. This right does not abrogate any other Government rights.
1.12 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.)
or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
http://jko.jten.mil/
1.13 Safety Plan as per specification 01 35 26 Governmental Safety Requirements.
Provide a copy to the COR within 10 calendar days after contract award.
1.14 Environmental Plan as per specification 01 57 19 Temporary Environmental Controls. Provide a copy to the COR within 10 calendar days after contract award.
2.0 Definitions and Acronyms
2.1 Definitions.
2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or services to the government. The term used in this contract refers to the prime.
2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.
2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S.
Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications.
This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.
2.2 Acronyms
AAR After Action Report AC Area Commander AEI Army Enterprise Info Structure AFARS Army Federal Acquisition Regulation Supplement ANG Army National Guard AR Army Regulation ATCTS Army Training Certification Tracking System AUP Acceptable Use Policy BBP Better Business Practice CDM Concept Development Meeting CCIRs Commander’s Critical Information Requirements CCE Contracting Center of Excellence CFR Code of Federal Regulations CM Contract Manager CNGB Chief National Guard Bureau COMSEC Communications Security CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer Representative COTR Contracting Officer's Technical Representative COTS Commercial-Off-the-Shelf CUI Controlled Unclassified Information DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DMDC Defense Manpower Data Center DOD Department of Defense FAR Federal Acquisition Regulation FEMA Federal Emergency Management Agency FPCON Force Protection Condition FPM Final Planning Meeting FTE Full Time Equivalent HIPAA Health Insurance Portability and Accountability Act of 1996 HQDA Headquarter Department of Army IA Information Assurance IPM Initial Planning Meeting IT Information Technology
JFHQ Joint Forces Headquarters JOC Joint Operations Center JTR Joint Travel Regulation JTF Joint Task Force KO Contracting Officer LNO Liaison Officer MHE Material Handling Equipment MOA Memorandum of Agreement MPM Mid-Planning Meeting MSR Monthly Status Report NACI National Agency Check Inquires NGB National Guard Bureau NLT Not Later Than OCI Organizational Conflict of Interest OCONUS Outside Continental United States ODC Other Direct Costs OPSEC Operations Security PCO Procuring Contracting Officer PII Protection of Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SME Subject Matter Experts TAR Travel Authorization Request TE Technical Exhibit WWAF-RA Wide Area Workflow-Receipt and Acceptance
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S).
The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract.
3.1 Property: None.
3.2 Materials: None.
3.3 Equipment: None.
3.4 Services: None.
3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4.0 Contractor Furnished Property, Materials, Equipment and Services (GFP/M/E).
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.
4.2 Bathrooms: The contractor shall provide portable bathrooms for their employees during the period of performance accompanied by its periodical maintenance.
5.0 Requirements.
5.1 The contractor shall make reference to Technical Exhibit # 3 for Construction of New Working Bay at FMS #2 in Gurabo.
5.2 Contractor Manpower Reporting Application (CMRA).
5.2.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Puerto Rico National Guard, via a secure data collection site.
5.2.2 The contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/. Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013.
Contractors may direct questions to the help desk at http://www.ecmra.mil.
6.0 Applicable Publications: Publications applicable to this PWS are listed below:
6.1 References
6.1.1 29 CFR 1926 OSHA Construction Industry Regulations:
6.1.2 Subpart A: General Requirements
6.1.3 Subpart C: General Safety and Health Provisions
6.1.4 Subpart E: Personal Protective and Life Saving Equipment
6.1.5 Subpart G: Signs, Signals and Barricades
6.1.6 Subpart H: Materials Handling, Storage, Use and Disposal
6.1.7 Subpart I: Tools Hand and Power
6.1.8 Subpart K: Electrical
6.1.9 Subpart L: Scaffolds
6.1.10 Subpart M: Fall Protection
6.1.11 Subpart P: Excavations
6.1.12 Subpart Q: Concrete and Masonry Construction
6.1.13 Subpart X: Ladders
6.1.14 ER 415-1-17 Construction Contractor Performance Evaluations http://www.ecmra.mil/ http://www.ecmra.mil/
Technical Exhibit 1 Performance Requirements Summary
This Performance Requirements Summary includes performance standards applicable to Technical Exhibit #3. The Government will use these standards to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
Discipline/ PWS
Paragraph
Task Performance
Standard
Acceptable Quality Level
(AQL)
Surveillance Method/By
Whom
Quality Control/ 6.1.14
a. Quality of Workmanship
b. Adequacy of the CQC Plan
c. Implementation of the CQC Plan
d. Quality of QC Documentation
e. Storage of Materials
f. Adequacy of Materials
g. Adequacy of Submittals
h. Adequacy of Testing
i. Adequacy of As-Built
j. Use of Specified Materials
k. Identification/Correction of deficiency works in a timely manner
100%
98%
Periodic Inspection COR will review monthly work order logs.
Effectiveness of Management/ 6.1.14
a. Cooperation and Responsiveness
b. Management Resources & Personnel
c. Coordination and Control of Subcontractors
d. Adequacy of Site Clean-up
e. Effectiveness of Job Site Supervision
f. Compliance with Laws and Regulations
g. Professional Conduct
h. Review/Resolution of Subcontractors Issues
Inspection COR will review
Timely Performance/
a. Adequacy of Initial Progress Schedule
b. Adherence of Approved Schedule
c. Resolution of Delays
d. Submission of Required Documentation
e. Completion of Punch List Items
f. Submission of Updated and Revised Progress Schedules
g. Warranty Response
Inspection COR will review
Compliance with Safety
Standards/
a. Adequacy of Safety Plan
b. Implementation of Safety Plan
c. Correction of Noted Deficiencies
Inspection COR will review
Technical Exhibit 2 Deliverables Schedule
PWS Reference / Deliverable Title Frequency Number of
Copies Medium/Format Submit To
1.4.1 Quality Control
Plan
Provide within 10 calendar days after
Contract Award 1 Electronic
Submission KO
1.4.11 AT Level 1
Awareness Training Certificates
Provide within 10 calendar days after
Completion of Training
1 Electronic Submission COR
1.4.12 iWATCH Training
Provide within 10 calendar days after
Completion of Training
1 Electronic Submission COR
1.4.13 OPSEC Training
Certificates and Plan
Provide within 10 calendar days after
Completion of Training
1 Electronic Submission COR
1.5 Special Qualifications Prior to Notice to
Proceed
1 Electronic Submission COR
1.7 Contract Manager
Provide within 3 calendar days after Contract Award
1 Electronic Submission COR
1.8 Identification of
Contractor Personnel
Provide 10 days after contract completion or employee’s departure
1 Hard Copy COR
1.9 Combatting of
trafficking of persons
Provide within 10 calendar days after
Contract Award 1 Electronic
Submission COR
1.11 Data Rights
Provide 10 days after contract completion
1 Hard and Digital Copies COR
1.13 Safety Plan
Provide within 10 calendar days after Contract Award
1 Electronic Submission COR
1.14 Environmental
Plan
Provide within 10 calendar days after
Contract Award 1 Electronic
Submission COR
TECHNICAL EXHIBIT #3
CONSTRUCTION OF NEW WORKING BAY AT FMS#2
GURABO, PUERTO RICO
1. PROJECT DESCRIPTION
1.1 Construction of a New Working Bay with 25-TONS capacity Top-Running Double Girder Overhead Crane. The Maintenance Bay will be composed of a mat foundation of 33’-0” width and 62’-8” long (2,068 SF), metal roof of 30’-0” height with metal siding around the entire steel structure and two (2) rolling up doors of 14’-0” height and 16’-0’’ width. At the exterior two (2) concrete sidewalks of 4’-0” width and 62’-8” long. In addition, the mechanical shop will be connected to potable and sanitary systems. In order to bring the adequate voltage to the New Maintenance Bay and continue the operations in the existing mechanical shop at FMS #2, the acquisition of a new transformer of 13.2 KVA and a New Step-Up Transformer of 120/208V to 480V will be necessary. The project also includes to install an air compressor of 15-hp (480V/3/60Hz) and pouring an asphalt road of 1,692 m2.
2. GENERAL CONDITIONS
2.1 The Contractor is responsible for visiting site to determine the location of pipes, drainage and all necessary material or equipment required to complete the project.
2.2 The proposal must include the Workmen Compensation (CFSE), Municipal taxes, insurance and bonds, Comprehensive General Liability and Comprehensive Automobile Liability.
2.3 The Contractor is responsible to repair any pipe or exiting utility damage during the construction period.
3. SUBMITALS
3.1 The Contractor must submit the proposed system prior to procurement to the USPFO Contracting Officer or his representative for proper evaluation and approval. See Submittal Log for a minimum submittal to be provide.
4. LIST OF DRAWINGS (17 PAGES)
4.1 T-1 Cover Sheet, Index of Drawings
4.2 G-0 General Notes, Abbreviations & Legend
4.3 C-1 Site Plan
4.4 C-2 Geometric Site Plan
4.5 C-3 Proposed Utility Plan
4.6 C-4 Utilities & Site Details
4.7 A-1 Proposed Floor Plan, Elevations & Notes
4.8 S-1 Foundation Plan
4.9 S-2 Foundation Sections & Details
4.10 S-3 Roof Framing Plan & Elevations
4.11 S-4 Structural Details
4.12 S-5 Structural Notes
4.13 Q-1 Overhead Crane Installation Details
4.14 P-1 Utility Plan & Details
4.15 E-1 Electrical Floor Plans
4.16 E-2 Electrical Schedules, Notes & Details
4.17 E-3 Panel Schedule, Diagrams & Details
5. APPLICABLE SPECIFICATIONS, Unified Facilities Guide Specification (UFGS)
5.1 Section 01 11 00 SUMMARY OF WORK
5.2 Section 01 32 01.00 10 PROJECT SCHEDULE
5.3 Section 01 33 00 SUBMITTAL PROCEDURES
5.4 Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
5.5 Section 01 45 00 QUALITY CONTROL
5.6 Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES
AND CONTROLS
5.7 Section 01 57 20 TEMPORARY ENVIRONMENTAL CONTROLS
5.8 Section 01 57 20 ENVIRONMENTAL PROTECTION
5.9 Section 01 78 23 OM DATA
5.10 Section 03 20 00.00 10 CONCRETE REINFORCING
5.11 Section 03 30 00 CAST IN PLACE CONCRETE
5.12 Section 04 20 00 UNIT MASONRY
5.13 Section 05 05 23.16 STRUCTURAL WELDING
5.14 Section 05 12 00 STRUCTURAL STEEL
5.15 Section 05 50 14 STRUCTURAL METAL FABRICATION
5.16 Section 08 33 23 OVERHEAD COILING DOORS
5.17 Section 09 90 00 PAINT AND COATINGS
5.18 Section 10 44 16 FIRE EXTINGUISHER
5.19 Section 22 00 00 PLUMBING, GENERAL PURPOSE
5.20 Section 22 15 13 GENERAL SERVICE COMPRESSED AIR
PIPING
5.21 Section 22 15 19 GENERAL SERVICE PACKAGED AIR
COMPRESSORS AND RECEIVERS
5.22 Section 23 30 00 HVAC
5.23 Section 23 35 00.00 10 VEHICLE EXHAUST REMOVAL SYSTEM
5.24 Section 26 00 00 ELECTRICAL MATERIALS AND METHODS
5.25 Section 26 05 13 MEDIUM VOLTAGE CABLES
5.26 Section 26 05 19.00 10 INSULATED WIRE AND CABLE
5.27 Section 26 05 71 LOW VOLTAGE OVERCURRENT PROTECTIVE
5.28 Section 26 12 19.10 3 PHASE PSD MOUNTED TRANSFORMERS
5.29 Section 26 18 23 MEDIUM VOLTAGE SURGE ARRESTERS
5.30 Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM
5.31 Section 26 51 00 INTERIOR LIGHTING
5.32 Section 26 56 00 EXTERIOR LIGHTING
5.33 Section 32 12 16 HOT MIX ASPHALT
5.34 Section 33 11 00 WATER DISTRIBUTION
5.35 Section 33 30 00 SANITARY SEWERS
5.36 Section 41 22 13.13 OVERHEAD BRIDGE CRANE-TOP RUNNING
6. SITE VISIT
6.1 Prior to the submission of any offers, the contractor is required to visit the project site location to become familiar with the project requirements. Failure to visit the project site will not disqualify an offer; however, the contractor is required to comply with the terms and conditions of any resultant contract by reason of such failure. In no event will a failure to inspect the site constitute grounds for a claim after award of the contract.
7. WARRANTY
7.1 Unless otherwise noted the contractor shall provide a minimum of one (1) year construction warranty on all materials and workmanship from the date of the Government's acceptance of the work in addition to the manufacturer's standard warranties.
8. POINT OF CONTACT
8.1 All site work must be coordinated thru CPT Alejandro Fonseca, authorized COR contacted by phone at (787) 289-1400 X 1054 or via email at alejandro.fonseca-rodriguez.mil@mail.mil.
9. ENCLOSURES
9.1 Enclosure A – Construction Plans
9.2 Enclosure B – Technical Specifications