MATOC EXHIBIT E.doc
DOC document 36 KB Posted
- Attached to
- Multiple Award Task Order Contract (MATOC) Federal contract opportunity
- Solicitation number
- W912LM-10-R-0003
About this file
Exhibit E and E-1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Duluth MATOC Q A - 5-20.doc | DOC document | |
| 090255Addendum_051810 | — | |
| W912LM-10-R-0003-0002 - Duluth MATOC Amendment.doc | DOC document | |
| M102A _Addendum051810.pdf | ||
| Duluth MATOC Q A - 5-18.doc | DOC document | |
| 04 2000 Unit Masonry.pdf | ||
| W912LM-10-R-0003-0001 - Duluth MATOC Amendment.doc | DOC document | |
| Site Visit Roster - Duluth.pdf | ||
| Duluth Pre-Proposal Slides.ppt | PPT presentation | |
| 090255FinalDwgs_032610.pdf | ||
| 2010 - MATOC EXHIBITS A-D F and G Jan 09.doc | DOC document | |
| 090255FinalSpec_032910.pdf | ||
| W912LM-10-R-0003 - Duluth MATOC Solicitation.doc | DOC document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDIQ MATOC
RFP W912LM-10-R-0003
EXHIBIT E PROTOTYPICAL PROJECT
NOTICE OF PROPOSED PROJECT, PROPOSAL FORM
Date: April 26, 2010
PROJECT TITLE AND NO:
Energy: Decentralize Heat Plant, Bldg 230
FMKM932052
PROJECT DESCRIPTION:
The project consists of removing several buildings from central plant steam and providing individual boilers. Small additions will be added at two buildings to accommodate the new boilers. The project also includes the demolition of existing Bldg 230, the Central Heating Plant.
MAGNITUDE OF PROJECT:
$500,000 – 1,000,000 PERFORMANCE PERIOD: 120 Days, after receipt of Notice to Proceed SITE VISIT: A site visit will be conducted in conjunction with the MATOC pre-proposal meeting. See Section 00100 of the solicitation for details.
PERFORMANCE & PAYMENT BONDS: In accordance with FAR 28.102-1 and Contract Clause 52.228-15, Contractors are reminded that any amount awarded over $30,000 shall require Payment Bonds, and awards exceeding $100,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 days after award.
LIQUIDATED DAMAGES: ( ) YES or ( X ) NO- reference Contract Clause 52.211-12.
CONSTRUCTION: (X ) YES or ( ) NO- reference Contract Clause 52.246-21, Warranty of Construction, is applicable to this task order.
WAGE DETERMINATION: Currently, General Decision Number MN20080075, Modification No. 0, dated March 12, 2010 is applicable to this task order. However, the current prevailing Wage Determination will be incorporated at time of award.
PROJECT SAFETY: In accordance with FAR 52.236-13, Accident Prevention, construction contractors are required to use the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. To view this manual click here http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1-1/toc.htm PROPOSAL DUE DATE: All offers are due with proposal for MATOC basic contract. Failure to provide a price will make offer noncompliant, eliminated from the competition and offeror ineligible for a basic contract award. Basis for award is in the RFP.
Item
Number
Description
Lump Sum Amount
Replace Central Heat Plant
IAW Specifications
Option 0001 1500 gpm Pumps
Option 0002 Abandon Steam Pits
Option 0003 Demolish Bldg 230
Option 0004 Emergency Power to
1000 gpm Pumps
Option 0005 Emergency Power to
1500 gpm Pumps
Option 0006 DDC, TAC in Lieu of ALC
SIGNATURE:
COMPANY NAME
Name and title of person authorized to sign Offer Date
EXHIBIT E – 1 - CALCULATION OF SELF-PERFORMED WORK
SUBMITTED IN RESPONSE TO W912LM-10-R-0003
Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
Clearly describe the work to be self-performed:
Show Calculation of Self-Performed work:__________________________________
B.1 Total Offer Price: $_________________
B.2 If applying for consideration as a General Contractor (multi-discipline projects) Subtract specialties, ie: Mechanical, Electrical, Roofing, Horizontal (unless being self-performed) $_____________ B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc. ($)_________________________________________
B.4 Remainder is “Total amount of work to be performed under the Contract” = $__________________
B.5 “Work to be self-performed”: = $ _________________________________ Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”?
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
B.6 % Self-performed Work = Line B.5 / B.4 X 100% = ________________________%
File details come from the government source that posted it. Updated .