9._Site_Visit_Memo_for_Interested_Parties.pdf

PDF 211 KB Posted

Attached to
Command Post Console Furniture Federal contract opportunity
Solicitation number
W912LC-18-Q-5001
Issued by
Department of the Army Colorado Army National Guard

About this file

Site visit memo / Q&As

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

“Building America’s First Team Together”

COLORADO AIR NATIONAL GUARD

140TH WING

BUCKLEY AIR FORCE BASE COLORADO

15 June 2018

MEMORANDUM FOR ALL INTERESTED PARTIES

FROM: 140 MSG/MSC

18860 E. Breckenridge Ave, Bldg 801, Room N-210

Buckley AFB CO 80011-9562

SUBJECT: W912LC-18-Q-5001 Command Post Console Site Visit Summary

1. A site visit for the subject solicitation was held on 14 June 2018 at the 140th Wing Command

Post for all interested parties. As a result of the site visit, several changes to the statement of need were made. Please see revised Statement of Need dated 14 June 2018 for most current information. Additionally, some questions were asked by participating vendors that are not incorporated in to the revised statement of need and are listed below along with the corresponding answer.

Q1. Does the proposed rear storage area have to remain the same depth as existing storage area

(~31” for countertop), or can proposed solution be more shallow?

A1. A more shallow solution would be acceptable (no less than 24”)

Q2. Existing rear storage area is ~44” tall. Should the height of proposed storage solution for rear storage area be the same?

A2. Yes, the proposed solution should remain as close to existing height as possible

LUCAS C. MARTINEAU, MSgt, COANG

Contract Specialist

2018-06-15T13:11:03-0600
MARTINEAU.LUCAS.COLTER.1187386671