W912LA-17-B-0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 01 00 00 - GENERAL REQUIREMENTS
The following have been added by full text:
RFI
| Project No. |
| Replace Vehicle Maintenance Facilities Complex (VMF), at the Moffett Federal Airfield, 129th Rescue Wing, California Air National Guard. |
| Date: 09/5/2017 |
| #QMSN 099104, at the Moffett Federal Airfield, 129th Rescue Wing, California Air National Guard. |
| RFI NO. |
| DATE RECEIVED |
| DESCRIPTION |
| DATE TO ENG./OWNER |
| DATE FROM ENG./OWNER |
| DATE TO CONTRACTOR |
| COMMENTS |
| 1 |
| 7/26/2016 |
| Please provide Table 1 for the LEED requirements. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Table 1 included in Volume I, 01 33 29. |
| 2 |
| 8/15/2016 |
| Please provide project requirements for the cranes. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference Specification Sections 41 22 13.14 and 41 22 23.19 included in Volume III. |
| 3 |
| 8/15/2016 |
| 5/ From the ABI’s identified on the revised proposal schedule and the drawings:ABI 0001 – Covered parking structures. Can you please clarify what is to be included within this ABI in addition to the covered parking structures? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 4 |
| 8/15/2016 |
| 5/ From the ABI’s identified on the revised proposal schedule and the drawings:Is the concrete pavement a part of the alternate? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 5 |
| 8/15/2016 |
| 5/ From the ABI’s identified on the revised proposal schedule and the drawings:If the concrete is a part of the ABI, what is to be installed there under the base bid in lieu of the concrete? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 6 |
| 8/15/2016 |
| With reference to the RFI No. 27 of the RFI Log, asking to clarify the question we sent, this is what my electrical sub was trying to ask. “ Please clarify required primary voltage: 12470 delta (sheet E-701) vs. 13800 delta (spec part 2.1.1.5.c)”. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - The primary site distribution is 12470 V Delta. |
| 7 |
| 7/14/2017 |
| Are drawings available for this project? I could not locate them on Fed Biz Ops. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 8 |
| 8/5/2017 |
| Good AM. How can we gain access to project bid documents for project below? |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 9 |
| 8/7/2017 |
| Can you please let me know how to unlock the project files for the subject mentioned project ? I have tried logging in to the account and try downloading them but it didn’t work, they saying I need to fill up a form in order to unlock those files, |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 10 |
| 8/10/2017 |
| The above solicitation was released on 8/5/17 and if the Registration Access to the secure access does take in fact 15 days it would only leave us with approximately 15 calendar days to review contract Specifications and Drawings. |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 11 |
| 8/10/2017 |
| Would the superintendent be allowed to act as the SSHO and QC manager? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There is no requirement for a SSHO on this project. |
| 12 |
| 8/10/2017 |
| Would email bid proposals be acceptable? |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| EMAIL PROPOSALS ARE NOT ACCEPTABLE THEY CAN BE MAILED IN FEDEX OR HAND DELIVERED. THEY MUST BE DELIVERED PRIOR TO THE BID OPENING TIME. NO LATE BIDS WILL BE ACCEPTED |
| 13 |
| 8/11/2017 |
| Do you have an approximate idea of when the complete plans & specs files will be posted to fbo.gov? |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| ALL PLANS AND SPECS ARE UPLOADED |
| 14 |
| 8/11/2017 |
| We want to bid as a general contractor but for some reason we are not granted access to all the files that are currently uploaded to fbo.gov. Do you know what we still need to do to access the locked files for the “Replacement of Vehicle Maintenance Facilities (VMF) Complex, PN# QMSN099104, 129th Rescue Wing, Moffett, CA.” project? Or perhaps you know who can help me with this? |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 15 |
| 8/22/2017 |
| I am an estimator with Abide International interesting in bidding the new vehicle maintenance facility. On August 8th I sent in the necessary paperwork to JCP and unfortunately the plans and specs are still locked on FBO. It is getting closer to the deadline and I have not even been able to review the project documents. Is there some way you can assist |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 16 |
| 8/22/2017 |
| We are interested in reviewing the above listed solicitation. However, 2/3 of the documents on the FBO web posting are locked. Is there any way you can help me gain access to them? |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 17 |
| 8/22/2017 |
| I don’t see the sign in sheet from the pre-bid meeting. Could you email it over? |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Uploaded to FBO 08/22 |
| 18 |
| 8/22/2017 |
| The Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage references the bid repository as “CE's Conference Room, 683 Macon Road, at the Moffett Federal Airfield, 129th Rescue Wing, Moffett, CA”, but the SF1442 and solicitation package references “USPFO,CA P&C, Camp Roberts, 903 Industrial Way, San Miguel, CA 93451.”Please provide clarification of this as the two locations are roughly 155 miles away from each other. |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Bid repository has CHANGED TO THE “CE's Conference Room, 683 Macon Road, at the Moffett Federal Airfield, 129th Rescue Wing, Moffett, CA”, SEE THE UPDATED sf 1442 |
| 19 |
| 8/22/2017 |
| We would like to bid to all General Contractors and what will help us is a list of attendees at job walk conducted on August 18, 2017. |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Uploaded to FBO 08/22 |
| 20 |
| 8/23/2017 |
| I attended last week's pre-proposal conference, on Friday August 18 at 1:00PM at Moffett Federal Airfield. Could you please direct me to register as Vendor and obtain the plans and specifications. |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| Please follow the Pre-Proposal Conference PowerPoint presentation provided on the FBO webpage. This will explain the steps to gain access. |
| 21 |
| 8/29/2017 |
| Specification section 230900 calls out an open BACnet architecture with no reference to a specified product. We would like use Reliable Controls as the product for installation. Reliable Controls meets all of the performance specs in 230900. Reliable Controls can be integrated into any campus system using BACnet. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Per section 23 09 23.02 under Part I, 1.1 Summary, the DDC specifications indicates that ALC shall be installed on Base shall be the standard manufacturer installed throughout all facilities. This is also indicated in Sections 23 09 13 and 23 09 00 under Part I, 1.1-Summary. |
| 22 |
| 8/29/2017 |
| The specifications do not reference safety requirements. Is the contractor to have on site a full time, qualified site safety and health officer (SSHO) during construction activities? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There is no requirement for a SSHO on this project. |
| 23 |
| 8/29/2017 |
| Section 01 45 00.10, Article 1.5.1.1 states that the site superintendent can also perform the duties of the QCM if so qualified. If a SSHO is required, can the combined site superintendent/QCM also perform the duties of the SSHO if so qualified? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There is no requirement for a SSHO on this project. |
| 24 |
| 8/29/2017 |
| Please provide copy of the geotechnical report for the subject site |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Geotechnical Report is included as Appendix G of Moffett VMF B3 SUBMITTAL BOOK_20160630. |
| 25 |
| 8/29/2017 |
| The job calls for 8x8x16 trenwyth block do they want them ground face or regular smooth face? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Per A-602 Basis of Design Finishes Schedule, CMU-2 is Smooth Face. |
| 26 |
| 8/29/2017 |
| Section 01 45 35 requires a special inspector of record (SIOR) to oversee the special inspections and inspectors. Can this SIOR work for the same company as the individual special inspectors? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Yes. |
| 27 |
| 8/29/2017 |
| The drawings indicate hollow 4” CMU veneer units, will solid 4” CMU veneer units be acceptable? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Solid 4" CMU is acceptable in lieu of hollow 4" CMU for veneer units. |
| 28 |
| 8/29/2017 |
| The drawing sheet S-551, detail 9, appears to show an underhung bridge crane. Specification 41 22 13.14 calls for a top running crane. Please clarify if the bridge crane is to be underhung or top running. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Top running bridge crane as specified in section 41 22 13.14 |
| 29 |
| 8/29/2017 |
| Clarify edging details at base bid and any option items. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Question is vague. Please clarify |
| 30 |
| 8/29/2017 |
| Sheet C-501, detail 3 indicates #4 rebar at 2” each way. Please clarify rebar spacing. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Rebar spacing should be 12" on center each way. |
| 31 |
| 8/29/2017 |
| Drawing P100 and P903 shows two (2) 4” trench drain lines connected to four (4) catch |
basins “CB”. Detail 8, Drawing P502 show one (1) trench drain to each catch basin.
Drawing P602 Equipment Schedule Trench Drain (TD-1) refers to structural drawings.
Structural Drawing S101 makes no reference to trench drains or catch basins. Architectural Drawing A101 shows four (4) catch basins with approximately 17’ long trench drain on both sides of catch basin. Please specify type, size and locations of trench drains; and conflict between what is shown on A101 and P101 drawings.
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference sheet S-111, Keyed Note 3.204 for Trench Drain reference. Details for trench drain are located on sheet S-511. |
| 32 |
| 8/29/2017 |
| Specification section 230900 calls out an open BACnet architecture with no reference to a specified product. We would like use Reliable Controls as the product for installation. Reliable Controls meets all of the performance specs in 230900. Reliable Controls can be integrated into any campus system using BACnet. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 21 |
| 33 |
| 8/29/2017 |
| The specifications do not reference safety requirements. Is the contractor to have on site a full time, qualified site safety and health officer (SSHO) during construction activities? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 22 |
| 34 |
| 8/29/2017 |
| Section 01 45 00.10, Article 1.5.1.1 states that the site superintendent can also perform the duties of the QCM if so qualified. If a SSHO is required, can the combined site superintendent/QCM also perform the duties of the SSHO if so qualified? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 23 |
| 35 |
| 8/29/2017 |
| Please provide copy of the geotechnical report for the subject site |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 24 |
| 36 |
| 8/29/2017 |
| The job calls for 8x8x16 trenwyth block do they want them ground face or regular smooth face? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 25 |
| 37 |
| 8/29/2017 |
| Section 01 45 35 requires a special inspector of record (SIOR) to oversee the special inspections and inspectors. Can this SIOR work for the same company as the individual special inspectors? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 26 |
| 38 |
| 8/29/2017 |
| The drawings indicate hollow 4” CMU veneer units, will solid 4” CMU veneer units be acceptable? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 27 |
| 39 |
| 8/29/2017 |
| The drawing sheet S-551, detail 9, appears to show an underhung bridge crane. Specification 41 22 13.14 calls for a top running crane. Please clarify if the bridge crane is to be underhung or top running. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 28 |
| 40 |
| 8/29/2017 |
| Clarify edging details at base bid and any option items. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 29 |
| 41 |
| 8/29/2017 |
| Sheet C-501, detail 3 indicates #4 rebar at 2” each way. Please clarify rebar spacing. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Repeat question. Reference response to question 30 |
| 42 |
| 8/29/2017 |
| Sheet C-041, indicates site demolition. Will there be a specification section to use for this work poriton? Please clarify. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Division 31 specifications apply to earthwork. |
| 43 |
| 8/29/2017 |
| Section 00010 of the solicitation lists the requirements of a complete bid package. Please confirm that items “(b) Section 00010 Line Items-” and “(c) Section 00010 Bid Schedule breakown” are in fact the same document listing the 11 bid items and that only one rendition of this document is necessary. |
| 8/31/2017 |
| 9/5/2017 |
| 9/5/2017 |
| PLEASE COMPLETE BOTH HOWEVER ONLY (B) WILL BE EVALUATED FOR AWARD. |
| 44 |
| 8/30/2017 |
| The Finish Schedule (page A-602) calls out for entry mats at 101 Corridor. Please provide a size and location. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Provide entrance mats full width of corridor by 4'-0" long located at doors 101A and 101B |
| 45 |
| 8/30/2017 |
| Page A-602 also notes CPT-1 through CPT-3. On the Room Finish Schedule, there is only a “CPT” designation. Please clarify which type of carpet will be required in each room with the “CPT” call out. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - CPT-1 through CPT-3 are base standard carpet. Owner will make final color selection from options indicated for spaces indicated to receive CPT. |
| 46 |
| 8/30/2017 |
| Per page C-031, hydroseed will be required to be installed. Will this hydroseed need to be removed at the conclusion of this project? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - No. |
| 47 |
| 8/30/2017 |
| Note 3/C-031 and section A-A/C-031 call out for wick drains. |
* What is the depth of these drains?
* Will a specification for the wick drains be provided?
* Will a geotechnical report be provided to provide further soils information (soil types) to the wick drain installers?
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Wick Drain installer is required to review soil conditions and geotechnical report to determine depth of wick drains. Reference Soil Surcharge Plan Notes on sheet C-031 for requirements of wick drain system. Geotechnical Report is included as Appendix G of Moffett VMF B3 SUBMITTAL BOOK_20160630. |
| 48 |
| 8/30/2017 |
| Page C-101 notes to “see architectural” for the trash enclosures. However, there is not anything shown on the architectural plans for these enclosures. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Trash Enclosures, located at the east end of the building, are indicated on Sheet A-101 (Keynote 4.117) and S-101. |
| 49 |
| 8/30/2017 |
| Will aggregate base be required per detail 5/C-501 under all building footings, or will this detail only apply to the perimeter footings of the building. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Referenced detail (5/C-501) is incorrect. Detail 5/S-501 indicates typical foundation earthwork requirements per geotechnical report. |
| 50 |
| 8/30/2017 |
| Please provide a detail for the truncated domes and the ADA ramps shown on page C-101. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - As indicated on sheet C-101, Sloped ramps are required to meet all ADA and State of California Requirements for accessibility. |
| 51 |
| 8/30/2017 |
| On page C-101, ABI 0008 and ABI 009 are called out to be the addition of concrete paving in lieu of gravel surfacing. However, the specifications list ABI 0008 as related to the storm infiltration basin. The ABI 0009 description discusses the upgrade of landscape areas. Please clarify. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 52 |
| 8/30/2017 |
| Will the addition of this concrete be included in the base bid, or should the addition of this concrete be included in the covered parking RFI’s (ABI 0010 and ABI 0011)? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 53 |
| 8/30/2017 |
| Page C-101 calls out for ABI 0006 to be the addition of asphalt paving in lieu of gravel surfacing. However, in the specifications, ABI 0006 is described as the change of manual gates to automated gates. Please clarify. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 54 |
| 8/30/2017 |
| Will the carport structures being added in ABI 0010 and ABI 0011 require painting? Will these carport structures require fire sprinklers? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Metal wall panels and standing seam metal roofing for carport structures are prefinished. Steel framing is finished per section 13 34 19. |
| 55 |
| 8/30/2017 |
| Will an enlarged plan for the trash enclosures be provided? Will there be any curbs, construction joints, etc. at these locations? |
* Please confirm that no lime treatment of the soils will be required under any of the site sidewalks noted in detail 1/C-501.
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference S-101 and A-101 for information regarding trash enclosures. Lime treatment is not required at sidewalks noted in detail 1/C-501. |
| 56 |
| 8/30/2017 |
| Will dowels and caulking be required at all construction joints per details on C-503? Page C-101 simply identifies the jointing as “typical.” |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Reference details 6/C-503 and 7/C-503 for all construction and contraction joint conditions. |
| 57 |
| 8/30/2017 |
| Specification sections 07 42 63 and 13 34 19 do not call out a description for MP-2 or MP-3. Will these panels be required on this project? If so, please provide a description. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Basis of Design for metal wall panels (MP-1, MP-2, and MP-3) are indicated on sheet A-602. Reference specification sections 07 42 13 and 07 42 63 for metal wall panels. |
| 58 |
| 8/30/2017 |
| Page S-151 calls out for metal deck over the administrative areas from grid lines 12-8. However, there is not metal deck called out to go on top of the PEMB purlins per pages S-151 or S-152. Are there insulated metal panels above the PEMB purlins? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - No insulated metal panels on PEMB roof. Roof material per 13 49 19 |
| 59 |
| 8/30/2017 |
| If so, detail 3/A-512 seems to call out for metal deck with rigid insulation at these locations. Please clarify. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - PEMB roofing and insulation should be as indicated in specification section 13 49 19. |
| 60 |
| 8/30/2017 |
| Would it be acceptable to provide 4” insulated metal panels in lieu of metal deck and rigid insulation? The insulated metal panel would provide a higher R value and have a thinner profile. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - PEMB roofing and insulation should be as indicated in specification section 13 49 19. |
| 61 |
| 8/30/2017 |
| With regard to specification section 41 22 13.14 – Bridge Cranes: |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - No response required |
| 62 |
| 8/30/2017 |
| Paragraph 2.1 – top running crane section references CMAA #70 which applies to double girder cranes. Since the crane on this project is a single girder crane, should CMAA #70 be changed to CMAA #74 everywhere in the specifications? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Per paragraph 2.1, CMAA 70 Class C per specifications |
| 63 |
| 8/30/2017 |
| Paragraph 2.3.1.3 (Micro-Drives) notes adjustable frequency controls which are required per paragraph 2.4.2. Micro speed control can be achieved with adjustable frequency controls. It is not required to have a separate micro-drive consisting of a motor, gear, and clutch for hoist, trolley, and bridge. It seems redundant to have the micro-drive and the adjustable frequency controls. It would be more cost effective to remove the micro-drives. Is this acceptable? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - As long as design intent per specification is met, it is acceptable. |
| 64 |
| 8/30/2017 |
| Page S-5551, view 9 (section at crane rail support) does not provide an elevation dimension of the lowest obstruction shown by the dotted lines. The minimum clearance between the highest point on the crane and the lowest obstruction should be 3” as required by the CMAA specification. Please provide a dimension. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Detail 9, Sheet S-551 indicates 4" clear from top of bridge crane beam. Maintain minimum required clearances to any obstruction. |
| 65 |
| 8/30/2017 |
| Paragraph 2.3.11 specifies that the stop and hold is to be 131.25%. However, OSHA does not permit overloading the hoist beyond 125%. Drawing 05-Q101, ID#PV7 UE-04 specified a 5 ton capacity crane. Should a 7.5 ton hoist de-rated to a 5 ton be furnished to satisfy paragraph 2.3.11? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There is no drawing 05-Q101 in project set |
| 66 |
| 8/30/2017 |
| Would it be acceptable to change the wording in paragraph 2.3.11 to limit the stop and hold to 125% while controlling the decent of 131.25% load? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Acceptable |
| 67 |
| 8/30/2017 |
| Paragraph 2.1.2 notes a speed of 120 FPM. This seems like it is too fast for a 25’ span crane. Is it acceptable to reduce the speed to a safer 80 FPM? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Span is indicated as approximately 44' in paragraph 2.1 |
| 68 |
| 8/30/2017 |
| Drawing 05-Q101, ID#PV7 UE-02 notes a 7 ton bridge crane. There is no specification provided for this underhung crane. Specification section 41 22 13.14 is for a top riding crane and does not apply to the underhung crane. Will there be another specification issued for the 7 ton underhung crane? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There is no drawing 05-Q101 in project set |
| 69 |
| 8/30/2017 |
| With regard to specification section 41 22 23.19 – Monorail Hoists,: |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - No response required |
| 70 |
| 8/30/2017 |
| Page S-242, views 2 and 3 does not detail how the monorail beam (3.403) must be attached to the roof structures. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Monorail support beam and connections per PEMB manufacturer. Coordinate with crane supplier. |
| 71 |
| 8/30/2017 |
| In addition, keynote 3.403 on page S-242 states, “Bottom of steel elevation is 125’6”.” Is this elevation the bottom of the monorail beam or the bottom of the roof support steel? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Bottom of steel for monorail beam |
| 72 |
| 8/30/2017 |
| The drawings indicate hook limits for the 7 ton crane. However, the drawings do not illustrate the location of the 7 ton crane nor do they show the location of its runways. Will a drawing be issued showing the location of the 7 ton crane and runways? In addition, will a hook height be provided? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There is no 7 ton crane indicated on drawings. Cranes include 2 1/2 ton Bridge Crane (41 22 13.14) and 2 1/2 ton Monorail Hoist (41 22 23.19) |
| 73 |
| 8/30/2017 |
| In order to deliver bridge crane materials, a 60’ stretch trailer will be needed for delivery. Please confirm that there will not be an access barricades that will obstruct a delivery truck from accessing the project site. |
| 8/31/2017 |
| 9/5/2017 |
| 9/5/2017 |
| THERE WILL BE A SEPARATE ENTRANCE FOR CONSTRUCTION |
| 74 |
| 8/30/2017 |
| This is to suggest you push the bid back a week for the Moffett project. We are calling subcontractors trying to get some interest in the project, but since it is bidding the day after Labor Day no one is willing to look at it. This is going to lead to less competition which leads to higher pricing. |
It would be in the best interest of the project to push it back a week to allow the interested parties adequate time to finalize their proposals.
| 8/31/2017 |
| 9/5/2017 |
| 9/5/2017 |
| BID OPENING HAS BEEN EXTENDED AND CHANGED TO CHANGED TO September 11, 2017, 1:00 PST, SEE AMENDED SF1442 |
| 75 |
| 8/30/2017 |
| Can the AISC shop and Field certification requirement noted in the structural steel specs be waived? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - No. All code requirements must be met |
| 76 |
| 8/31/2017 |
| We are really interested in the Moffett project that ANG has out right now. It looks like there are some pre bid RFI questions that need to be answered and it bids on Tuesday after the holiday weekend. This is not to your advantage in getting good pricing bidding the day after a holiday. Can you inquire as to whether the bid is going to be pushed? |
| 8/31/2017 |
| 8/31/2017 |
| 8/31/2017 |
| BID OPENING HAS BEEN EXTENDED AND CHANGED TO CHANGED TO September 11, 2017, 1:00 PST, SEE AMENDED SF1442 |
| 77 |
| 8/31/2017 |
| Please provide the bridge crane monorail support centers. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - Bridge crane support is part of PEMB design as indicated on Sheets S-002 and S-151 |
| 78 |
| 8/31/2017 |
| On sheet PV2 03-A100, it shows (2) 5 ton cranes. Should this read 3 ton cranes (capacity)? Keynote 3 on sheet PV2 03 S-105 and PV203-S106 both note a 3 ton capacity crane. |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There are no drawing PV2 03-A100, PV2 03 S-105, or PC203-S106 in project set |
| 79 |
| 8/31/2017 |
| Sheet PV2 03-Q101 states, “Four (4) total crane assemblies rated at three (3) ton. Two (2) cranes per bridge assembly.” Should this read, “Four (4) total hoist assemblies rated at thee (3) ton. Two (2) hoists per bridge assembly”? |
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - There is no drawing PV2 03-Q101 in project set |
| 80 |
| 8/31/2017 |
| For Units 1, 2, 3, and 4(PV#2), the (4) 3 ton TRSG cranes (with two 3 ton hoists per 3 ton crane), will the (4) 3 ton bridge cranes run back-to-back on the same runway? *Will the cranes have hook separation? * What is the runway capacity? |
* Is the runway rated for all the cranes to operate back-to-back or with (one) crane bay separation?
| 8/31/2017 |
| 9/4/2017 |
| 9/5/2017 |
| M&H - This question refers to multiple cranes that are not a part of this project. |
| 81 |
| 8/31/2017 |
| I saw your information on the Builder’s Exchange. I may be interested in bidding hauling services for construction debris hauling. I could not determine if this is part of the bid? Do you need boxes? |
What size? Frequency per month?
How many months is the job?
Types of material going in the box?
When does job start?
| 8/31/2017 |
| 9/5/2017 |
| 9/5/2017 |
| This question would be answered by the awardee |
| 82 |
| 8/31/2017 |
| We are a plumbing wholesaler in the San Francisco Bay area and would like to know who the qualified bidders are for the plumbing side of this project. |
| 8/31/2017 |
| 9/5/2017 |
| 9/5/2017 |
| please see the job walk and interested bidders list both on FBO |
| 83 |
| 8/31/2017 |
| Process for obtaining access to the bid documents via the JCP System delayed our access to the final Bid documents. We appreciate the further clarification provided with the published pre-proposal slides. However, we respectfully request an extension to the bid due time to allow for more adequate bid document review. |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| Owner Response Required |
| 84 |
| 8/31/2017 |
| Sheet C-031 Soil Surcharge Plans calls for the installation of a wick drainage system. Please provide Specifications and Soils Report detailing requirements for this system such (a) as spacing of wicks, (b) duration of surcharge, (c ) depth, (d) existing soils profile to show presence of rock, etc. |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Wick Drain installer is required to review soil conditions and geotechnical report to determine depth of wick drains. Reference Soil Surcharge Plan Notes on sheet C-031 for requirements of wick drain system. Geotechnical Report is included as Appendix G of Moffett VMF B3 SUBMITTAL BOOK_20160630. |
| 85 |
| 8/31/2017 |
| Sheet C-031 Soil Surcharge Plans shows an area to be used as borrow area for the surcharge. Is this soil acceptable to be used as structural fill? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - No. Per Soil Surcharge Plan Note 1, "Following surcharge, the soil borrowed for the surcharge shall be relocated to the borrow site, to restore the borrow site to its original condition." All structural fill shall meet the requirements of the geotechnical report. |
| 86 |
| 8/31/2017 |
| Reference sheet L-101, L-102, C-101. These sheets show scope of work for the landscaping, but there are no project specifications for landscaping. Please provide Landscape specifications |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Reference Notes and details on sheets L-101 and L-102 for landscaping requirements. |
| 87 |
| 8/31/2017 |
| Sheet S-001, Note 10 States: "Office space requires ATFP design per UFC 4-010-01. All exterior windows and doors must comply with the requirements of this standard, including doors and windows between the office space and vehicle maintenance space". Please provide project specifications for ATFP windows. |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Reference specification sections 08 11 16, 08 41 13, and 08 51 13 for ATFP door and window systems |
| 88 |
| 8/31/2017 |
| Sheet S-001, Note 10 makes reference to Doors and Windows meeting the ATFP design. Sheets 601 and 602 provide reference to ATFP windows, but there are no other reference to ATFP doors. Please confirm doros are to meet the ATFP design requirements. |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Reference specification sections 08 11 16, 08 41 13, and 08 51 13 for ATFP door and window systems |
| 89 |
| 8/31/2017 |
| Per Sheet S-001 Doors and Windows are to comply with ATFP design. Is the building required to meet the ATFP Standoff Distance? Clarify. |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Reference Appendix F - AT/FP Summary for standoff distances |
| 90 |
| 8/31/2017 |
| Sheet S-002, PEMB System notes, MBS-3, indicates to “allow for review and revision of foundation design after anchor bolt drawings and reactions are fully coordinated with approved metal building design from manufacturer”. - Will the government’s engineer be performing the review and revision of the foundation design, or is the intent for the contractor to retain an engineer for this effort? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Government's Engineer will Review during submittal process to confirm that assumed design loads for building foundations meet or exceed actual design loads from PEMB design. |
| 91 |
| 8/31/2017 |
| Sheet S-002, PEMB System notes, MBS-3, indicates to “allow for review and revision of foundation design after anchor bolt drawings and reactions are fully coordinated with approved metal building design from manufacturer”. - Once the PEMB anchor bolt drawings and reactions submittal package is reviewed and approved by the government, is the intent for the contractor to perform a structural adequacy verification for the concrete foundation system? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Repeat question. Reference response to question 90 |
| 92 |
| 8/31/2017 |
| Sheet S-002, PEMB System notes, MBS-3, indicates to “allow for review and revision of foundation design after anchor bolt drawings and reactions are fully coordinated with approved metal building design from manufacturer”. - Will the government require a shop drawing for the concrete foundation system at the conclusion of the foundation adequacy verification? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Repeat question. Reference response to question 90 |
| 93 |
| 9/1/2017 |
| We have been unable to locate a window schedule. Will a window schedule be provided? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Window types are on sheet A-601. |
| 94 |
| 9/1/2017 |
| Will the overhead steel doors and vision panels per A-601 be required to comply with ATFP requirements? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - No |
| 95 |
| 9/1/2017 |
| 1) Please advise if the electrical and access control work for two motorized gates as shown on plan sheet E-011 is part of base bid or ABI#5? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - As indicated on sheet G-101, ABI# 005, "Route conduit for power and controls underground to structure location for future installation" are included in base bid. |
| 96 |
| 9/1/2017 |
| 2) Please advise if the lighting work show on E-401 is part of base bid or ABI#8 & #9? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - As indicated on sheet G-101, ABI# 009 and 010, "Route conduit for power underground to structure location for future installation" are included in base bid. |
| 97 |
| 9/1/2017 |
| 3) Please advise if the electrical work for the bridge cranes & ceiling fan shown on E-131 is part of base bid or ABI#1? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - As indicated on sheet G-101, ABI# 001, "Structure and utilities to support equipment installation (destratification fan, bridge crane, and monorail crane)" are included in base bid. |
| 98 |
| 9/1/2017 |
| On Solicitation CLIN 0008 states “ADDITIVE BID ITEM #7 -This is priority #7. Install Stormwater Infiltration Basin. Description: Add concrete mow edge, underdrain piping, and clear stone cover to L-shaped drainage swale in NE corner of site. Add site landscaping and irrigation per sheets L-101 and L-102.This is shown as ABI 007 in the specification”. Also CLIN 0009 states “ADDITIVE BID ITEM #8- This is priority #8. Upgrade Landscaping. This is shown as ABI 008 in the specifications.” |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 99 |
| 9/1/2017 |
| However, plans sheet G101 depicts alternatives schedule with different description from the solicitation for ABI #7 & #8. Also, the same plans sheet G101 depicts a site drawing with ABI# 8 for concrete paved area! |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Reference Sheet G-101 for list of ABI's and what is included. |
| 100 |
| 9/1/2017 |
| Is there a soils report? |
| 9/5/2017 |
| 9/5/2017 |
| 9/8/2017 |
| M&H - Geotechnical Report is included as Appendix G of Moffett VMF B3 SUBMITTAL BOOK_20160630. |