Question_15-17_Answers.pdf

PDF 12 KB Posted

Attached to
Repiar Overhead Doors Basewide Federal contract opportunity
Solicitation number
W912L7-18-B-7004
Issued by
Department of the Army Tennessee Army National Guard

About this file

Questions15-17

View the file

Other files for this federal contract opportunity

Other files attached to Repiar Overhead Doors Basewide, newest first.
File Type Posted
Question_1-14_Answer.pdf PDF
Sign_in_sheet_W912L718B7004.pdf PDF
Preproposal_minutes_W912L718B7004.pdf PDF
REV1_Submittal_Repair_Overhead_Doors.pdf PDF
W912L718B7004_Amendment_1.pdf PDF
PWS,_PSXE142004_Repair_Overhead_Doors_Basewide.pdf PDF
Drawings_12_Jan_2018.pdf PDF
W912L718B7004_Final.pdf PDF
Specificaitons_12_Jan_2018.zip ZIP file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15. Question: To be clear is the Architect saying that the outside, only what is visible to the exterior side if the building is powder coated? If the answer is yes than the interior surface will be a standard baked on finish in grey, white or tan finish.

15. Answer: No, the complete door is to be powder coated with a standard RAL color with the exception of those noted as requiring a custom color.

16. Question: Motor Operator 08734 Paragraph 2.2 c. 1), 2), 3), 4) require TENV, TEFC, and NEMA4/ 4X Wash down enclosures, 2.2 D. indicates a NEMA ICS Type 1 Enclosure. This is a contradiction. Existing operators are all NEMA type 1. Which is required? the NEMA 4X is very expensive. I see no need for the NEMA 4X on any location I visited. I have the same question for the Sectional Door operators.

16. Answer: NEMA 4X is not required.

17. Question: Overhead Coiling Doors 08330 Paragraph 2.2 2. D. requires a IECC 2012/2015 C402 4.3 Air leakage < 1.00 cfm. This requires a special package on Rolling steel products and adds to the expense.

To clarify, is this required as none of the products both old and new on base have this option + we have seen this specification widely ignored by door venders when bidding. If it is required I would like this emphasized if possible

17. Answer: No, this is not required.