Addendum_01_Description.pdf

PDF 109 KB Posted

Attached to
134th ARW Repair Building 406
Solicitation number
W912L7-16-B-0002
Issued by

About this file

Addendum Description

View the file

Other files

File Type Posted
Addendum_02_Description.pdf PDF
W912L7-16-B-0002-0004.pdf PDF
Pre-Bid_Questions_40-41.pdf PDF
W912L7-16-B-0002-0003.pdf PDF
Addendum_1_-_08800_BSD-Glazing.pdf PDF
Pre-Bid_Questions_11-31_Existing_roof_trusses_to_remain.pdf PDF
24 S2.1 Foundation floor Plans - Lower Level Bldg A B.pdf PDF
48 E1 Electrical Site Plan.pdf PDF
49 E2 Electrical Plans bldg A.pdf PDF
7 A2.2 Floor Plans Main Level Bldg A B.pdf PDF
33 P3 Plumbing Plans Upper Level.pdf PDF
19 A6.2 Miscellaneous.Details.pdf PDF
13 A3.1 Bldg Elevations.pdf PDF
Pre-Bid_Questions_11-31.pdf PDF
46 MP3 HVAC Piping Upper Level.pdf PDF
29 S4.2 Sections Bldg A B.pdf PDF
44 MP1 HVAC Piping Lower Level.pdf PDF
10 -A2.5 Reflected Ceiling Plans Lower Level Bldg A B.pdf PDF
2 - A0.2 Sheet Index Miscellaneous.pdf PDF
40 M4 Enlarged Plans.pdf PDF
31 P1 Plumbing Plans Lower Level.pdf PDF
4 A1.2 Rough Grading Plan.pdf PDF
5 A1.3 Landscape Plan.pdf PDF
27 S2.4 Roof Plans Bldg A B.pdf PDF
45 MP2 HVAC Piping Main Level.pdf PDF
11 A2.6 Reflected Ceiling Plans Main Level Bldg A B.pdf PDF
1 - SU1 Site Utilities Plans Details.pdf PDF
3 A1.1 Site Plan.pdf PDF
26 S2.3 Floor Plans - Upper Level Bldg A B.pdf PDF
8 A2.3 Floor Plans Upper Level Bldg A B.pdf PDF
21 A7.2 Door Schedules.pdf PDF
22 A7.3 Room Finish Schedules.pdf PDF
Pre-Bid_Questions_32-39.pdf PDF
35 P5 Enlarged Plans Diagrams.pdf PDF
9 A2.4 Roof Plans.pdf PDF
32 P2 Plumbing Plans Main Level.pdf PDF
43 M7 HVAC Details Schedules.pdf PDF
12 A2.7 Reflected Ceiling Plans Upper Level Bldg A B.pdf PDF
39 M3 HVAC Plans Upper Level.pdf PDF
15 A4.1 Wall Sections Details.pdf PDF
38 M2 HVAC Plans Main Level.pdf PDF
34 P4 Enlarged Plans Riser Diagrams.pdf PDF
20 A7.1 Door Schedules.pdf PDF
25 S2.2 Foundation Floor Plans - Main Level Bldg A B.pdf PDF
50 E3 Electrical Plans bldg B.pdf PDF
30 S4.3 Sections Bldg A B.pdf PDF
41 M5 HVAC Schedules.pdf PDF
18 A6.1 Miscellaneous.Details.pdf PDF
6 A2.1 Floor Plans Lower Level Bldg A B.pdf PDF
37 M1 HVAC Plans Lower Level.pdf PDF
Show 40 more

Latest 50 of 70 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

240 W. Bessemer Street Alcoa, Tennessee 37701

ADDENDUM NO. 1

September 2, 2016

TO

SPECIFICATIONS AND DRAWINGS FOR

REPAIR BUILDING 406

MCGHEE TYSON AIR NATIONAL GUARD BASE

PSXE102033

Addendum Descriptions:

1. All FCUs shall include factory supplied supply and return air grilles.

2. Refer to Drawing M1.2: All concentric vent termination kits for the boilers and water heaters shall be stainless steel.

3. All Open Storage compartments in the dormitory room millwork shall have a stainless steel corner guard on the bottom edge of the millwork. Corner guard shall be ¾”x¾”, 90 degree, 16 gage, Type 304 SS, Satin #4 brushed finish.

4. FP3.1 fire protection pipe bracing details show wire rope/cable bracing. Rigid bracing may be required depending on the available overhead space and for coordination with the other building utilities, structural members, etc. No additional payment shall be made for rigid pipe bracing where required.

5. Provide a tether stop on all cabinet doors in the dormitory rooms. Product shall be

HAFELE Item #366.74.900, or approved equal.

6. Bid Question #25: Automatic Door Opener associated with the ABA push button shall be Door Motion Technologies commercial door operator DuraSwing 5 full time door operator, or approved equal.

7. All of the exterior hand railing shall receive factory powder coat finish in lieu of the clear anodized finish called out on the plans and specs. Color shall be Dove Gray.

Powder coat finish shall conform to AAMA 2605 High Performance requirements.

8. Door stops shall be installed for all of the Accessible Bedrooms. Door stop shall be floor mounted type No. 241F as manufactured by Hager Company with US26D finish, or approved equal.

9. Revised Glazing Specification 08800 provided with changes to Section 2.1 for

Insulating Glass Units.