Ellington_JRB_Design_Standard_20160615.pdf

PDF 1 MB Posted

Attached to
Renovate Building 1056 Federal contract opportunity
Solicitation number
W912L1-17-B-0002
Issued by
Department of the Army Texas Army National Guard

About this file

Design Standards

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Building 1056, newest first.
File Type Posted
W912L1-17-B-0002-0001.pdf PDF
09310A-Ceramic_Tile.pdf PDF
15440-Plumbing_Fixtures.pdf PDF
09900_-_Painting.pdf PDF
Questions_and_Answers.docx DOCX document
06402-Interior_Architectural_Woodwork.pdf PDF
08710-Door_Hardware.pdf PDF
10801-Toilet_Room_Accessories.pdf PDF
08211-Flush_Wood_Doors.pdf PDF
09651_-_Resilient_Tile_Flooring_and_Accesories.pdf PDF
09680_-_Carpet.pdf PDF
09310B-Pocelain_Tile.pdf PDF
1056_Site_Plans_20160722.pdf PDF
SOW_-_1056_-_Renovate_for_SG_DSI_HG_20170324_Rev1.pdf PDF
1056_Dimensions.pdf PDF
Standard_Finish_Schedule_&_Colors.jpg JPG image
Solicitation_W912L1-17-B-0002.pdf PDF
FWJH152260_SOW-_1056_-_Renovate_for_SG_DSI_HG_20170324.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

147th RECONNAISSANCE WING BASE DESIGN STANDARDS

Ellington Field JRB, Houston, TX as of 15 Jun 16

15 June 2016 Page 1 of 30

AIR NATIONAL GUARD DESIGN OBJECTIVES AND PROCEDULES (Tab C) (ANG/ETL 10-3, Apr 2010)

Air National Guard facilities shall be similar in quality to those facilities found in the private and corporate sector of their local communities. Air National Guard (ANG) projects shall provide clean, architecturally compatible, yet non-monumental solutions to facility requirements. Facility designs shall avoid the appearance of waste or excessive cost. Architectural style and detail shall be based on sound facility architectural principles and shall be developed to maximize facility flexibility. Building and site design shall present a unified campus setting, reflecting the existing or developing master architectural standards of the base. Facility and site design shall also comply with the approved base master plan. Designs between facilities (administrative, industrial, aircraft) that differ in use shall be coordinated so that a unified architectural theme is provided between the various base facilities. All aspects of facility construction shall be carefully considered for their architectural impact. Construction materials shall be specifically selected by the designer for durability, aesthetics and low maintenance/maintainability features. Building and site designs shall thoughtfully provide for the large monthly drill weekend unit training assembly (UTA) occupancy, while economically accommodating the much smaller daily population.

GENERAL CONSIDERATIONS

SITE CONSIDERATIONS: Provide site improvements and building forms appropriate to any new, future or existing buildings. Facilities having similar functions should be located in the same vicinity. The flight line should be reserved for buildings that are related to aircraft operations and maintenance. Parking should not dominate. Encourage pedestrian access. Cluster related buildings in stead of spreading out.

ENVIRONMENTAL CONSIDERATIONS: Design facilities in a ways to enhance environmental quality and minimize consumption of natural resources. Tightly cluster buildings that are related to each other creating walkable campuses. These clusters should reduce the amount of land use, utility costs and vehicle costs to move from building to building.

SUSTAINABLE DESIGN AND DEVELOPMENT: Project will comply with Executive Order 13423, 24 Jan 07 and Energy Policy Act of 2005 and is required to meet the provisions if ANG Sustainable Design and Development policy for United States Green Building Council’s Leadership in Energy and Environmental Design (LEED) Green Building Rating Systems metric and will be capable of achieving LEED Silver certification. Refer to:

1. Air Force Sustainable Design and Development (SDD) Policy, 31 July 2007

2. Air National Guard Sustainable Design Policy

LAYOUTS: Provide functional layouts that are logical and satisfy user’s needs both inside and outside as well as layouts that have the ability to accommodate other future users. Maximize the use of interior open space by using work stations and increasing the flexibility to accommodate changes.

LOW MAINTENANCE: Provide permanent low-maintenance exteriors that are compatible with Ellington ANG Joint Reserve Base Architectural Standards. Use materials that do not require painting during their lifetime. Landscaping shall be indigenous to the area with little or no irrigation or maintenance.

AETHETICS: Follow the Ellington ANG Joint Reserve Base Architectural Standards. Buildings are to blend into the current architectural scheme of the base. Buildings that are to be held out as “Object” buildings will be determined by the Base Civil Engineer and are usually considered public buildings such as headquarters, dinning etc.

15 June 2016 Page 2 of 30

TECHNOLOGY: Provide technically sound buildings at low costs. Take advantage of emerging technologies, but not at the expense of aesthetics or standards.

COSTS: Reduce life-cycle costs. Concentrate on low life-cycle costs as opposed to low initial costs.

Facilities are to be permanent incomputable construction designed to last decades with a minimum of maintenance. Reduce labor-intensive maintenance procedures.

SITE DESIGN

Site selection and location is to be in conformance to the Base Master Plan. Outside spaces need to create friendly, inviting walkable communities. Comply with the applicable site standard including anti-terrorism force protection.

SITING: New facilities are to be sited within compatible functional groups in accordance with base master plan.

COMPLEXES: Locate buildings supporting common functions such as civil engineering, administrative, flying functions in complexes in order to share common infrastructure such as roads, parking, utilities and security. These clusters should read as a single entity with similar details and materials to link them aesthetically as well as functionally. Provide sufficient enough space around building/complex for expansion.

TRAFFIC: When existing traffic patterns are change by new construction proposals, provide adequate traffic alternatives to coincide with the construction of the new project. Locate buildings so that walking between buildings is encouraged. Design parking lots so traffic can move between adjacent parking lots.

Insure Antiterrorism force protection standoffs are maintained.

NOISE: Consider noise levels and attenuation requirements when locating facilities. Refrain from locating facilities in incompatible noise zones.

SITE CONSIDERATIONS:

GENERAL: Address all aspects of the site including relationship of interior spaces to the site, pavement, landscaping, pedestrian access, signage, service equipment, infrastructure, barriers, etc. Design the entire site. Include all applicable standards including antiterrorism force protection.

SITE INFLUENCE: Refrain from using site locations that force uneconomical facilities, complicated building shapes such as curves, diagonals and long rectangles.

OPEN AREA: Site to permit open landscaping around buildings to separate the building from required paving and maintain antiterrorism force protection standoffs. Prevent an overcrowded appearance.

EXISTING SITE CONTOURS: Provide positive drainage away from buildings of at least 2% slope.

Consider existing or natural grades as much as possible to eliminate excessive cut and fill operations.

ENVIRONMENTAL: Building site is to take into account appropriate laws and directives regarding wetlands, flood plains, protected species habitats and archeological sites. None of these are present on Ellington Field.

15 June 2016 Page 3 of 30

SCREENING: Screen utility equipment, dumpsters, recycling bins and storage areas. Consider walls, mature landscaping and/or berms. Insure compliance with antiterrorism force protection requirements Minimize use of chain-link fencing where practical.

SUBSTAINABLE DESIGN:

1. All projects shall comply with the Energy Policy Act of 2005 (EPAct 05) and Executive Order 13423.

2. If directed by the Design Instruction (DI) from NGB/A7, project will be registered with the U.S.

Green Building Council (USGBC) and will obtain an USGBC Leadership in Energy and Environmental Design (LEED®) recognition at the classification and level given in the DI.

DESIGN CRITERIA: The following is a partial list of Department of Defense (Unified Facilities Criteria (UFC)), Air Force (AF), Air National Guard (ANG) and major design codes and standards that are applicable to Air National Guard design and construction. Should these requirements be updated, refer to the most current publication in the design and construction process.

AFI 32-1021 Planning and Programming Military Construction (MILCON) Projects AFI 32-1032 Planning and Programming Appropriated Funded Maintenance, Repair and

Construction Projects ANGH 32-1084 ANG Standard Facility Requirements, 24 April 2006 (Current Working Draft) ANGETL 07-6 Air National Guard Facilities Requirements, 1 May 2007 (Verify it’s use) ANGETL 01-1-1 Air National Guard Design Policy (Tab D) Revised 1 Mar 2004

UFC 4-010-01 Minimum Antiterrorism Standards for Buildings 8 Oct 2003 including change 1, 22

January 2007

UFC 1-200-1 General Building Requirements, 20 June 2005. UFC 1-200-1 adopts the 2003

International Building Code (IBC-2003) as amended by the UFC and as amended by the City of Houston. See Section 1 Design Codes and References ANGETL 01-1.

JAFAN 6/9 Physical Security Standards for Special Access Program Buildings 23 March 2004

National Fire Code, NFPA Fire Protection See ANGETL 01-1-1 (Tab D)

ASHRAE HVAC Design ASHRAE Std 62-89 (R) ASHRAE Std 90.1 Ventilation AFOSH Std 161-2

ANGETL 93-4 Roof Design Guidance, March 1993 NRCA 5th Edition Roofing and Waterproofing Manual

ASCE 7-98 Vertical and Horizontal Design Loads (Latest edition)

EPAct 05 Energy Policy Act of 2005

Utilities Standards established by the Public utility having jurisdiction such as water, sewer, electrical and storm drainage.

15 June 2016 Page 4 of 30

State Regulations Where State has jurisdiction over Safety, Environmental Protection

OSHA, AFOSH Safety Regulations

NEC National Electric Code for Electrical Design

Specification Ellington Master Specifications Master Guide Uniform Facilities Guide Specification (UFGS)

ARCHITECTUAL EXTERIOR DESIGN

The exterior architectural standard scheme for the base is based on buildings 1256, Base Civil Engineering Complex, and building 1258, Base Supply. See attached photographs.

ROOFS:

1. Sloped Roofs (Base Standard): Provide Manufacturers pre-finished metal roof system with 3 to 12 to 4 to 12 roof slope based on building size, width and configuration. Manufacturer standard to follow is AEP Span Span-Lok HP system.

a. Minimum steel gage is 24 GA minimum.

b. Finish: Kynar 500

c. Loading: Roof system required to meet 2003 International building code (IBC) with

Houston amendments for hurricane force winds of 115 MPH

d. Metal fascia gutter will match the roof material, be continuous with a minimum of joints.

1). Construction shall be in accordance with the Sheet Metal and Air Conditioning Manufacturer’s Association (SMACNA) Architectural Sheet Metal Manual.

2). Any lapped joints shall be installed so the edge of the top lap is in the direction of the gutter’s slope.

e. Roofs will be installed with clips that allow roof expansion and contraction in the seamed rib. (This is very important with large roof surfaces.)

f. Color Selection: Keep the established base roof color motif. Consider reflective characteristics, particularly in regards to LEED considerations. Colors will be selected by the Contracting Officer or Representative (COR) from the manufacturer’s full range of standard colors. Medium Bronze is the color used on several building for the roof panel color.

2. Flat Roofs (Only where absolutely necessary and with approval from the Base Civil

Engineer):

a. Standard is a Polyvinyl Chloride Roof such as Tremco Tri-polymer Alloy (TPA) single ply roof membrane that is an elastomeric Tri-polymer alloy based on DuPont’s ELVALOY® and blended CPE and PVC mechanically fastened, 80 mils.

b. Gravel ballast systems are not allowed.

15 June 2016 Page 5 of 30

c. Minimum roof slope is ¼” per 1’-0” (3/8” to ½” is preferred)

d. White is acceptable on roofs that cannot be seen. Otherwise the roof is to be colored with a selection from manufacturer’s stand full range of colors by the CO or COR.

e. Code and flashing shall meet the same standard as Sloped roofs above.

EXTERIOR WALLS:

1. Exterior wall construction shall be brick masonry cavity wall construction to follow the motif of building 1256 Base Civil Engineering and building 1258 Base Supply.

a. Provide a cavity of 1 ½ to 2 inches.

b. Provide weep holes at the base of wall and above lintels at least every 24 inches on center.

c. Provide expansion joints in masonry at every 20 feet. Arrange so they occur at window and door openings where practical.

2. End Walls: Sloped parapet walls with pre-cast concrete caps.

3. Brick Recess Accent Strip: Provide a recessed accent strip at the head of windows.

4. Pre-cast Architectural Concrete Wainscot Panels and Trim: Provide a 3 foot high pre-cast architectural concrete wainscot capped by a 6 inch high semicircular pre-cast architectural concrete wainscot top.

a. At outside and inside corners, provide solid corner returns. No cutting a 45° angle to make corner.

5. Pre-cast Architectural Concrete Window Header Trim: Provide 4” high semi-circular continuous pre-cast architectural concrete head trim at window head as a continuous accent strip.

6. Pre-cast Architectural “Star” Accents: Provide precast architectural concrete accent stars at the center of end parapet walls and above windows and doors as appropriate. Refer to the photographs.

7. EXTERIOR COLOR - Where existing CMU exterior walls are to be painted the base standard color is Sherwin-Williams, Comp (I001), Acrylic, Semi Gloss, 421 Onionskin Tan

WINDOWS and EXTERIOR DOORS:

15 June 2016 Page 6 of 30

1. Windows: Provide anodized aluminum with dark bronze manufacturers applied polymer 20 yr coated finish with thermo-break construction, double glazing. Window is to comply with UFC 4-010-01, Anti-terrorism Force Protection (ATFP) standards. Window sill sits on the top of the semi-circular concrete top to the wainscot.

a. Provide plastic solid corin interior window sills.

b. Provide metal flashing at exterior window sill matching the window color.

c. Double pane glass window section shall be 1 inch thick, dual panel thermal units, bronze-tinted with Low-E coating.

d. Interior glass panel shall be laminated glass meeting UFC 4-010-01 ATFP standards.

2. Exterior Storefronts: Provide at entrances to buildings and courtyard where a lot of light is desirable.

a. Provide anodized aluminum with dark bronze manufacturers applied polymer 20 yr coated finish. Style to be match windows.

b. Double glazing. Same as windows.

c. Assembly and glazing shall meet UFC 4-010-01 ATFP standards.

3. Exterior Storefront Doors: Provide anodized aluminum doors with dark bronze manufacturers applied polymer 20 yr coated finish. Color matching adjacent aluminum frames.

a. Glazing same as windows

b. Assembly and glazing shall meet UFC 4-010-01 ATFP standards.

c. Door Bottom: 10 inches high meeting ADA requirements.

d. Hardware:

1). Hinges: Either continuous integral continuous hinge or 1 ½ pair Stainless steel ball bearing NRP hinges

2). Door Pulls: ¾” round stainless steel.

3). Panic Hardware: Von Duprin straight single strike with “best” 7 pin key core cylinder dogging. Provide electric strike access with Advantor card reader / key pad operation.

4). Closer: Inside arm heavy duty closer with hold open.

4. Exterior entrance doors: Exterior entrance doors are to be furnished with electronic strike access with Advantor card reader / key pad operation. See Detail below. Mechanical, electrical, communication and exterior fire exit doors shall have standard hardware.

15 June 2016 Page 7 of 30

EXTERIOR PHOTOGRAPHS OF BASE CIVIL ENGINEERING AND SUPPLY BUILDINGS

15 June 2016 Page 8 of 30

ARCHITECTUAL INTERIORS

The architectural interior finishes are based on buildings 1256 Base Civil Engineering Complex and 1258 Base Supply.

Administrative Space Name

Floors Mat/Fin

Base Walls Mat/Fin

Ceilings Mat/Fin

Doors Mat/Fin

Remarks

Corridors POR/F POR/F GB/VWC APC/F WD/Stn Notes 1, 2 Entry/Vestibule POR/F POR/F GB/VWC APC/F SF Note 5 Commander CPT/F CPT/F GB/P APC/F WD/Stn Offices CPT/F CPT GB/P APC/F WD/Stn Break Rooms POR/F POR/F GB/VWC APC/F WD/Stn Note 1 Briefing/Conference CPT/F CPT GB/P APC/GB/P WD/Stn Note 1 Classrooms CPT/F CPT GB/P APC/F WD/Stn Note 1 Bathrooms/Lockers POR/F POR/F GB/E

6’CT(W)

GB/P WD/Stn Notes 3, 4

Janitor VCT/W R GB/E

6’ CT(W)

GB/P WD/Stn Notes 3, 4

Storage VCT/W R GB/P APC/F WD/Stn Vaults/ Secure Rms. VCT/W R CON/P CON/P MT/P Dinning Areas POR/F POR/F GB/P APC/F WD/Stn Kitchen Area POR/F POR/F CT/GB/P GB/P WD/Stn Telecomm Closets VCT/W R PLY/GB/P APC/F WD/Stn Mechanical/Electrical CON/S R CMU/P ES/P MT/P Industrial Space Name

Floors Mat/Fin

Base Walls Mat/Fin

Ceilings Mat/Fin

Doors Mat/Fin

Remarks

Bathrooms/Lockers POR/F POR/F GB/E

6’CT(W)

GB/P WD/Stn Notes 3, 4

Break Rooms VCT/W R GB/P GB/P WD/Stn Note 1 Briefing/Conference CPT/F CPT GB/VWC APC/GB/P WD/Stn Note 1 Circulation VCT/W R GB/VWC APC/F WD/Stn Note 1 Classroom VCT/W R GB/VWC APC/F WD/Stn Note 1 Hangar Bay Maintenance Docks

CON/E N/A ES/P ES/P MT/P

Janitor VCT/W R GB/E

6’ CT(W)

GB/P WD/Stn Notes 3, 4

Labs & Clean Rooms VCT/W R GB/P APC/GB/P MT/P Shops CON/E R CMU/P APC/F MT/P Shop Offices VCT/W R GB/P APC/F MT/P Storage CON/S N/A CMU/P ES/P MT/P Shop A/C VCT/W R GB/P APC/F MT/P Warehouse CON/E N/A CMU/P

ES/P

ES/P MT/P

Covered Parking / Docks & Storage

CON N/A N/A ES/P N/A

15 June 2016 Page 9 of 30

Telecomm Closets VCT/W R GB/P PLY GB/P MT/P WD/Stn

Mechanical/Electrical CON/S R CMU/P ES/P MT/P

NOTES:

Note 1: 1x4 WD Chair rail / Stain Note 2: Floor Tile nominal 12 x 12 size.

Note 3: Ceramic Tile shower nominal 8 x 8 size.

Note 4: Ceramic Tile wainscot nominal 6 x 6 size.

Note 5: Walls at exterior will not have VWC Note 6: Provide Terrazzo Floor Symbol at main building entry.

ABBREVIATION KEY:

FLOORS CEILINGS

Abbrev. Material Abbrev Material CON Concrete APC Acoustic Panel Ceiling CPT Carpet CON Concrete CT Ceramic Tile GB Gypsum Board POR Porcelain Tile ES Exposed Structure VCT Vinyl Composition Tile APC/GB Combination of APC & GB

WALLS DOORS

Abbrev. Material Abbrev Material CMU Concrete Masonry Unit SF Store Front CON Concrete MT Metal CT Ceramic Tile WD Wood, Solid Core GB Gypsum Board BASE PLY ¾” Plywood B-Sanded CTP Carpet CP Cement Plaster R Rubber, 4” W Wainscot CT Ceramic Tile, 6” CP Cement Plaster POR Porcelain Tile, 6”

FINISHES: GENERAL NOTES:

Abbrev. Material Notes Remark P Paint Gen 1 Acoustic Panel Ceiling (APC), 2’ x 2’ grid S Seal Gen 2 Wood and Metal Doors to have metal frames Stn Stain Gen 3 Store front doors to have store front frames W Wax VWC Vinyl Wall Covering E Epoxy Coating, 2-part IC Integral Color

15 June 2016 Page 10 of 30

FINISH MATERIALS SPECIFICATIONS and COLORS: (Based on 272 EIS Facility Complex B1259 and Base Vehicle Maintenance B 1142)

The following material color selections are for general guidance only. Color selection should occur based on overall base theme and compatibility, individual project requirements and needs. The A/E is still required to make material and color selections and to submit color boards which are to be reviewed and approved by the Design Working Group (DWG) Refer to attachment A Interior Finish Material and Color Schedule for finish and color information.

1. CEILING:

A. Acoustic Panel Ceiling:

1). Premium Locations

a. Acoustic Tiles: Armstrong Ceiling Systems # 1821 Beveled Tegular 24” x 24” x 3/4”, Class A Color: White

b. Metal Ceiling Grid (Humid Weather Rated) : Chicago Metallic 4000 Tempra 9/16” (Stab or Hook) 2’-0” x 2’-0” grid Color: White

2). Standard Locations

a. Acoustic Tiles: Armstrong Ceiling Systems # 1810 Fine Fissured Square Lay-In

24” x 24” x 3/4”, Class A Color: White

b. Metal Ceiling Grid (Humid Weather Rated) : Chicago Metallic 200 Snap-Grid

15/16” (Hook) 2’-0” x 2’-0” grid Color: White B. Gypsum Wall Board:

1). Gypsum Board Finish: Paint (Color Designations are Benjamin Moore Paints, Typical)

a. Finish: Smooth Texture

b. Color: Ceiling White

c. Gloss: Eggshell (Bathrooms Semi-gloss enamel)

C. Exposed Metal Structure: Paint

a. Finish: Clean

b. Color: Ceiling White

c. Gloss: Eggshell

2. WALLS:

A. INTERIOR WALL COLOR - Gypsum Wall Board: Paint (Color Designations are Benjamin Moore Paints, Typical) 1). Finish: Smooth Texture 2). Color:

a. General Color: #HC-172 Revere Pewter

b. Gloss: Eggshell

B. Interior Concrete Masonry Units (CMU): Paint 1). Finish: Clean 2). Color: General Color: #HC-172 Revere Pewter

15 June 2016 Page 11 of 30

3). Gloss: Eggshell

C. Vinyl Wall Covering (VWC): Omnova Tower Wall Covering 1). Pattern: Judder 2). Color: T2-JU-08 Buttered Bread

3. WAINCOTS and SHOWER WALLS

A. Porcelain Tile (POR) Field: Daltile Corporation Matte

1). Size: Nominal 6” x 6” x 5/16” 2). Finish: Matte 3). Gout Joint 1/16” 4). Color: #X735 Matte Almond

B. Ceramic Tile (CT) Accents: Daltile Corporation Matte

1). Size: Nominal 6” x6” x 5/16” 2). Finish: Matte 3). Grout Joint 1/16” 4). Color: #0766 Matte Elemental Tan

4. BASE:

A. Carpet Base (CB):

1). Location: Offices, Administrative, Classrooms, ETC.

2). Height 4” with Vinyl coved cap 3). Color: Match existing floor carpet.

B. Vinyl Base (VB) Color

1). Location: Where vinyl Composition Tile provided.

2). Height: 4” 3). Color: Roppe P147 Light Brown

C. Porcelain Tile Base (Colors Crossville Ceramic Tile)

1). Location: Vestibules, Corridors, halls with porcelain tile floors.

2). Size 6” H x 12” W x 5/15” thick integral cove bottom and bullnose top 3). Color: # A790 UPS Burgundy Stone 4). Grout: ¼” Color: Laticrete #42 Platinum

D. Porcelain Tile Base (Colors Crossville Ceramic Tile)

1). Location: Toilet Rooms Showers with porcelain tile floors.

2). Size 6” H x 8” W x 5/16” thick integral cove bottom and bullnose top 3). Color: # A790 UPS Burgundy Stone 4). Grout: ¼” Color: Laticrete #42 Platinum

5. FLOOR:

15 June 2016 Page 12 of 30

A. Carpet Tile (CPT):

1) Location: Offices, Administrative, Classrooms, ETC.

2) Carpet: Patcraft

3) Style: #10126 Socrates II – Tile

4) Color: #00509 – Gellner

5) Material: 100% Eco Solution Q Nylon

6) 100% Solution Dyed

7) Gauge: 1/8

8) Stitches per Inch: 8.0

9) Tufted Pipe Height: 5/32”-5/32”

10) Tufted Yarn Weight: 28 oz

11) Tile size: 24” x 24”

12) Finish Pile Thickness: 0.159”

13) Density: 5887

14) Weight Density: 153.062

15) Protective Treatments: SSP Shaw Soil Protection

16) Primary Backing: Non-Woven Synthetic

17) Secondary Backing: EcoWork Tile

18) Pattern Repeat: ¼ Turn

19) Post Consumer Recycled Content: 11.5

20) Post Industrial Recycled Content: 27.8

21) Performance Specifications

a. Methenamine Pill Test (DOC FF-1-70) Passes

b. Flooring Radiant Panel (ASTM E-648) Class I

c. Smoke Density (ASTM E-662) Less Than 450

d. Static Control(AATCC-134) Less Than 3.5 KV

e. CRI Green Label Plus GLP 9968

B. Porcelain Stone Tile (POR) (Colors Crossville Porcelain Stone Tile) 1). Location: Corridors, Vestibules, Hallways 2). Field:

a. Size: 12” x 12” x 5/16”

b. Color: #A675 UPS Stonehenge

c. Grout: ¼” Laticrete #42 Platinum

3). Accent and Edge Pattern:

a. Size: 6” and 12” x 12” x 5/16”

b. Color: #A790 UPS Burgundy Stone

C. Porcelain Stone Tile (POR) (Colors Crossville Porcelain Stone Tile)

1). Location: Showers 2). Field

a. Size 8”x8”x 5/16”

b. Color: #A675 UPS Stonehenge

15 June 2016 Page 13 of 30

D. Vinyl Composition Tile (VCT) Colors Armstrong Commercial Flooring

1). Location: Storage, Janitor, Laundry, Copy Room, Equipment Room, Shops, Shop Offices

2). Field

a. Size: 12” x 12”

b. Texture: Imperial

c. Type: Standard EXCELON

d. Color: #51830 Cottage Tan

3). Accent and Edges:

a. Size 12”x12”

b. Texture Imperial

c. Type Standard EXCELON

d. Color #51869 Humus

E. Terrazzo Floor Detail for 147th RW Facilities

6. SOLID SURFACE LAVATORY COUNTER TOPS:

A. Corian B. Style:

C. Color: Sandstone

7. DOOR FRAMES:

A. Location: Where Oak Wood Doors

1). Manufacturer: Porter Paints 2). Color: #7176-2 Antique Iron 3). Finish: Gloss

B. Location: Where Metal Doors

1). Manufacturer: Sherwin-Williams 2). Color: SW 7041 Van Dyke Brown

15 June 2016 Page 14 of 30

8. WINDOW SILLS:

A. Corian B. Color: Neptune (Solid Black)

9. INTERIOR DOORS:

A. Level of standard for typical door and frame: 3’-0”W x 7’-0”H x 1 ¾”T solid core wood door with 16 gage hollow metal frame.

1). Wood Door Grade: Premium (Grade A faces) 2). Wood Door Faces: Red Oak, quarter sewn.

3). Match between Veneer Leaves: Slip match 4). Match between Door Faces: Balance match 5). Finish:

a. Grade: Premium

b. Finish AWI System TR-4 conversion varnish

c. Stain: Match Contracting Officer’s sample

d. Sheen: Satin.

6). Door hardware shall be complete: A typical example for an office is: (Hardware to be determined based on each specific function for the particular room/area involved)

a. 1 ½ Pair ball bearing butt hinges with non removable pins

b. Set rubber jamb and head seals

c. Best Heavy Duty Commercial Lever Lockset, 7 pin removable “Best” core, master keyed to Base’s keying system. Keyed one side thumb turn other.

d. Wall Bumper

INTERIOR PHOTOGRAPHS:

Conference Room

Conference Room

15 June 2016 Page 15 of 30

DISPLAY CASES & BULLETIN BOARDS:

1. Display Cases AND Bulletin Boards shall be similar to those provided in building 1256, Base Civil Engineering and building 1258, Base Supply:

A. Dark bronze anodized aluminum frame B. Tempered Glass C. Swinging or sliding lockable glass doors depending on function.

D. Tackable back surface.

E. Tempered glass shelves.

2. Display Case Photographs:

Corridor w/ Symbol

Men’s Restroom

Display Case

Bulletin Board

Bulletin Board

15 June 2016 Page 16 of 30

STANDARD MOUNTING HEIGHTS:

1. Standard heights for all equipment, switches and receptacles:

INTERIOR FLORESCENT LIGHTS:

1. Standard Recessed suspended ceiling fluorescent lighting fixture are the high efficiency parabolic coffered open fixtures with T-5 low energy bulbs.

2x4 foot Fluorescent Fixture 2x2 foot Fluorescent Fixture (No U Tubes)

15 June 2016 Page 17 of 30

2. Standard lighting for warehouse and shop spaces similar to Highmax Highbay High Wattage CFL Acrylic Fixtures150 or 200 watts. Provide acrylic lens where flammable materials might be used.

ANTENNAS:

1. SINGLE ANTENNAS:

A. Single antennas may be mounted on the side of buildings similar to buildings 1256, Base Civil Engineering.

B. Antennas shall not be attached or penetrate roofing.

C. Location must be approved the Base Civil Engineer prior to any installation.

2. MULTIPLE ANTENNAS:

A. Multiple antennas are to be mounted on a free standing antenna mast. Antenna will be furnished by the user. Foundations and concrete slabs maybe part of the project scope.

B. Antenna masts must meet hurricane force winds.

C. Antenna masts must be free standing without the use of guide wires.

D. Location must be approved the Base Civil Engineer prior to any installation.

3. COORDINATION: Insure the user does the proper coordination so support and electrical rough-in can be provided as part of the project scope.

4. ANTENNA PHOTOGRAPHS:

Multiple Antenna Mounting

Single Antenna Mounting

15 June 2016 Page 18 of 30

Note: Provide concealed rough-in. No exposed conduits.

SECURITY CAMERAS:

1. If security cameras are part of the project, insure locations are properly coordinated.

Electrical and communication rough-ins (with wires) is provided as part of the project scope.

Terminate electrical in an outlet box above the ceiling and communication cable coiled above the ceiling

2. Camera and their mounting parts are to be provided by the user.

3. Example of typical mounting is shown in the following photograph.

SIGNAGE:

Security Camera

15 June 2016 Page 19 of 30

1. Exterior Signs: All exterior signage on buildings will have to be approved by the Base Civil Engineer

2. Examples of exterior signs are: See Exterior Building Photos

3. Cast aluminum letters shall be:

a. Finish: Medium Bronze

b. Letter Style: Helvetica Bold 531

c. Mounts: Hot-dipped galvanized anchors PM-1 or PM-1A

d. Size: Determined for each individual project.

4. Interior Signage: Provide room identification signs similar to the following photographs.

ROADS, SIDEWALKS and PARKING LOTS

1. Primary Roadways: Primary roadways are to be reinforced concrete pavement with a minimum width of 23 foot inside curb to inside curb and integral 6 inch high concrete curbs both sides. Primary sidewalk circulation systems provide five (5) foot minimum wide sidewalk on one side where necessary to maintain the base’s pedestrian system. Consider using recycled concrete for base materials on roads and parking.

15 June 2016 Page 20 of 30

2. Secondary Roadways: Secondary roadways are to be reinforced concrete pavement with a minimum width of 20 feet wide inside curb to inside curb and integral 6 inch high concrete curbs both sides. Secondary sidewalk systems provide four (4) foot minimum sidewalk on one side where necessary to maintain the base’s pedestrian system.

3. Parking Lots: Parking Lots maybe hot mix asphalt except where parking of heavy military vehicles or access by heavy trucks or equipment such as service, loading and unloading areas where reinforced concrete will be used. Pay particular attention to the Antiterrorism force protection standards.

a. Provide standard reinforced concrete curb and gutter. Gutter only required for hot mix asphalt surfaced driveways.

b. Standard parking stall be 18 feet deep by 9 foot wide at 90° perpendicular parking bay

26 feet driveway.

c. Provide a minimum 10 foot of landscaped area from any roadway or edge of sidewalk and the parking lot.

d. End Island: Provide a minimum of 6 foot wide landscaped island at the end of a parking row and the circulation drive.

e. Parking lots shall have a minimum of 2% slope for asphalt and 1% for concrete with a maximum slope of 5%.

4. Drives: Maybe asphalt except where heavy vehicle access is required. For heavy vehicle driveways, use reinforced concrete.

a. Provide standard reinforced concrete curb and gutter. Gutter only required for AC surfaced driveways.

b. Provide swinging galvanized steel pipe barrier with a positive latched hold open and hold closed at each driveway that goes to the building to deliver supplies. Locate per Antiterrorism force protection standards.

5. Sidewalks: Sidewalks shall be 6’ wide

6. Sidewalk Lighting: Provide Ballard type sidewalk lights at main entries to buildings.

15 June 2016 Page 21 of 30

7. Street and Parking Lot Lighting: Where the project budget permits, street and parking lot lighting should be solar.

a. Style: Anodized aluminum head with lens.

b. Color: Medium Bronze Finish.

SCREENS and FENCING

1. Screens: Provide screen walls to screen mechanical equipment, service yards and other such areas that would distract from the general good appearance of the base. Pay particular attention to the Antiterrorism force protection standards.

a. Finished exposed exterior surface should be brick match the building with precast concrete cap.

b. Provide 16 inch mow strip in front of screen if adjacent to lawn. Mow strip not necessary if adjacent planting bed.

2. Fencing: Security chain link fencing will be per the Air Force standard, 6 foot high with 1 foot of three equally spaced strands of barbed wire mounted on a 45° outrigger. Total Height 7 foot.

a. Provide 32 inch wide (16” each side of fence) concrete mowing strip.

b. Gates can be sliding, but arranged is such a way as to slide along the fence.

ANTI -TERRIORISM FORCE PROTECTION BARRIERS:

1. Provide a swing gate barrier at all service driveways to buildings at the standoff distance for occupied and primary occupied building in accordance with UFC 4-010-01 change 1 22 January 2007 DOD Minimum Antiterrorism Standards for Buildings as shown in the following sketch.

15 June 2016 Page 22 of 30

SECTION 10 MECHANICAL - HEATING, VENTILATING AND AIR CONDITIONING

AND PLUMBING

ANGETL01-1 shall be the governing reference for this section. Included herein are specific requirements established for Ellington Field JRB, Houston TX.

EQUIPMENT AND ROLLUP DOOR PROTECTION:

1. Protect all door jambs, equipment pads and other areas that are subject to damage by motor vehicles with bollards.

2. Bollards are 6” Steel concrete filled pipe set in 2 foot diameter by 4 feet deep concrete footing. Slope top of footing.

3. Bollards are to be covered with heave duty PVC shrouds. These are available at Grainger and manufactured by Eagle Manufacturing Co. 2400 Charles Street, Wellsburg, WV 26070.

See picture below

HVAC SYSTEMS:

15 June 2016 Page 23 of 30

1. GENERAL: The type of HVAC system will be based on the type, functions, use, and other criteria necessary to arrive at the best system by comparative analysis in accordance to ANG/ETL 10-3 (Tab C). Typical systems provided are:

a. Multiple DX units both combined unit and split with electric and hot water heating

b. Hot and chilled water systems with boilers and chillers.

c. Variable volume (VAV) systems.

HVAC INPUT/OUTPUT SCHEDULE EXAMPLE:

INPUT OUTPUT for Misc Controls shall have “HVAC Emergency Shutdown Switch” added.

DDC shall monitor the Pulse Output of gas, water and natural gas utility meters. DDC shall translate pulse into usage rates and provide totalization.

15 June 2016 Page 24 of 30

HVAC System Emergency Shutdown:

Emergency HVAC shutdown switches shall be double action switches. Label switches with a plastic laminate placard stating the following: “Emergency HVAC Shutdown Switch”.

DDC shall monitor the status of the emergency HVAC shutdown switches.

Upon activation of emergency HVAC shutdown switch, equipment shall shutdown per the prescribed sequence of operation. All equipment with DDC controls shall be shutdown through the DDC. Equipment without DDC controls shall be hard wired for shutdown.

2. BOILERS: New and replacement boilers shall be Fulton impulse type hydronic boilers and shall have the following options included:

a. BACnet translator card.

b. Pumps: Bell & Gosset or approved equal pumps shall be specified.

3. UNIT HEATERS:

a. May be provided in shop areas.

b. Because of mild winters in the Houston area, heating are not required in entryways vestibules, restrooms (unless a shower area) and mechanical and electrical rooms.

4. INFRARED HEATING: Where appropriate, open shop bays maybe designed using infrared heating.

5. CHILLERS: All new or replacement chillers shall be Carrier and shall have the following options included:

a. Protective coated fins for salt water spray.

b. Hail guards

c. Extended 5 year warranty.

d. Phase and under voltage protection.

e. BACnet translator card

f. Remote display module for chiller controller.

g. High Short Circuit Current Rating (SCCR)

h. Remote enhanced display.

i. Unit mounted non fused disconnect.

j. Condenser coil trim panels and security grilles

k. Non removable core filter drier

l. Compressor suction service valve

m. Suction line insulation

n. Remote cooler kit

o. Navigator hand held display and remote service port with 115 Volt outlet.

15 June 2016 Page 25 of 30

6. CONDENSING UNITS: Concrete shall be placed around the condensing unit to the work clearances of the unit. For multiple condensing units, provide one single pad for all the units sized to required work clearances. Where unit or units are next to a building provide required work clearance from building. Pad is to extend to the building.

7. CHILLER and CONDENSOR FINS: Provide salt water protective coating for fins.

8. VARIABLE FREQUENCY DRIVES: Provide ABB variable frequency drives as a standard.

SUPPLY REGISTERS:

1. With the extreme humidity present in the Houston area, supply register have a tendency to produce condensate which drips out of the registers. Therefore, supply registers need to be fully insulated.

MECHANICAL IDENTIFICATION:

1. All exposed mechanical and utility piping systems will be identified in accordance with

AFOSHD 91-501 Air Force Consolidated Occupational Safety Standard, Chapter 20 Safety Color Coding, Labeling and Marking for Piping Systems.

BUILDING AUTOMATION SYSTEM (BAS)

1. Direct Digital Control (DDC): Most of the older base control’s DDC system is Delta ORCA View Version 3.33. New facilities shall upgrade the entire system to the operating system, Niagara AX.

2. Verify IP addresses and insure there are not conflicts with existing.

3. Any time versions require upgrading, the entire system shall be upgraded including hardware or software key locks.

4. Points to be controlled and sequence of operations shall be depicted on the drawings.

15 June 2016 Page 26 of 30

METERS:

1. Meters: All new facilities shall meter the electric, gas and water as applicable to the facility.

a. Electric meters shall be Square D PM870 in a factory assembled enclosure with a RS485 port and front panel LCD for local data display and basic setup. Contact Square D for the appropriate part number of the meter.

b. New meters shall communicate with the existing SMS software.

c. New gas and water meters shall send data to the Square D PM870 electric meter and shall be identified on drawing and specifications.

PLUMBING:

1. Backflow preventers: Backflow preventers are not required on the base except for foam suppression systems, sprinkler systems with anti-freeze and boilers.

2. Flush Valves: All flush valves should be the manual type. Battery operated can be installed on urinals. Verify current systems in use with the BCE.

15 June 2016 Page 27 of 30

3. Fixtures:

a. Urinals, water closets, counters and toilet partitions in bathrooms should all be ceiling hung. Water closets flush valves should have energy saving low water/ high water valves.

b. Toilet Partitions shall be matt finish stainless steel.

c. One set of urinals, water closets, lavatories and drinking fountains will meet the requirements for the handicap in each restroom. Where there are multiple sets of toilet rooms (more than one set of men’s and women’s toilet room) only the set nearest the administration portion of the building needs to be designed for the handicapped. This will required Base Civil Engineer approval.

d. Towel dispensers. T1300 blue by San Jamar is the basis of design as long as the towel is standard and will work in any model.

1) Provide electrical operated units in new construction

2) Provide battery operated units in existing facilities where electrical hookup wouldn’t be justified by cost.

4. Eye wash stations: All eyewash/showers shall have a drain in the floor and be connected to electricity and the fire alarm system (sends a safety signal).

SECTION 11 ELECTRICAL

ELECTRICAL:

1. Outlets and Switches: All outlets and switches shall have and embossed tape depicting the panel it is fed from, the voltage and circuit number. Sample in the Civil Engineering Building B1256.

BUILDING GENERATORS:

1. Generator Make: The base preference is Onan, Kohler, Kato Light, in order, for installed generators.

2. Generator wiring hook up mobile generators: A cannon plug should be provided for those facilities not having an installed generator less than 200Amps or less. All others should have the capability to hard wire into the manual transfer switch. Refer to ETL 09-9 for clarification.

TRANSFORMERS:

1. Transformers and switches: New transformers and switches will comply with the most recent regulations. All new transformers and switches will be marked consistent with the base markings.

SECTION 12 UTILITIES

15 June 2016 Page 28 of 30

UTILITIES:

1. Underground utilities: All underground utilities shall have detectable marking tape. Acid and alkali-resistant polyethylene film warning tape manufactured for marking and identifying underground utilities, minimum of 6 inches wide and 4 mils thick, continuously inscribed with a description of utility, with metallic core encased in a protective jacket for corrosion protection, detectable by metal detector when tape is buried up to 12 inches deep:

colored as follows:

a. Red; Electric

b. Yellow; Gas, oil, steam, and dangerous materials

c. Orange; Telephone and other communications

d. Blue; Water systems

e. Green; Sewer systems

2. All detectable marking tape shall be terminated in a termination box so as to avoid damage.

3. Site Water System: Existing base water system High Density Polyethylene (HDPE) pipe.

This type of pipe will be used for all site water to within 5 feet of the building.

4. Underground primary electric should be concrete encased with red concrete. A spare conduit should be provided.

5. Underground secondary electric can be direct buried, in conduit, non concrete encased.

FIRE HYDRANTS: The following provides fire hydrant specifications meeting UFC 3-600-01, ANG ETL 01-1-1, NFPA Standards and base standard:

1. Fire hydrants must be UL listed, FM approved, or listed or classified by an NRTL and must have two 2-1/2-inch hose outlets and one 4-1/2-inch hose connection with national standard fire hose threads in accordance with NFPA 1963. Installation shall be in accordance with NFPA 24 and ANG ETL 01- 1-1. Wet-barrel hydrants are preferable due to little or no danger of freezing. Hydrants must be aboveground type. Manufacturer and model should match those already installed on base for maintenance purposes.

2. Hydrant bonnets and caps are to be painted in IAW ETL 01-1-1 and NFPA 291. All barrels shall be painted red to match the color and specifications adopted as Base standard. The bonnets (tops) and nozzle caps shall be painted with the following capacity-indicating color scheme. GPM rating and color scheme shall be based on actual, individual hydrant flow tests (not area flows), performed by the contractor. For rapid identification at night, it is recommended that the capacity colors be of reflective type paint.

a. Class AA: Light blue >1500 GPM

b. Class A: Green 1000 - 1499 GPM

c. Class B: Orange 500-999 GPM

d. Class C: Red < 500 GPM

SECTION 13 AS BUILTS

15 June 2016 Page 29 of 30

GEOSPATIAL DATA STANDARDS:

1. As part of the as built submittal, all utilities and buildings are to be located using a geospatial positioning system (GPS) meeting the following standards:

a. Geospatial Data Standard:

1). Prepare and furnish geographical Information System (GIS) electronic map of the site and site utilities that integrates into the 147 CES Common Installation Picture (CIP) using Geographical Positioning System (GPS) Geospatial Electronic data per ANG ETL 32-1018 Dated 12 August 2005. Highlights from the ETL are:

a). All GIS data shall be delivered in ArcGIS compliant format (either geodatabase or Shapefile) b). All CAD data shall be delivered in AutoDesk Drawing (dwg) file format.

c). All data will be registered to the following real world map coordinate system parameters:

Texas State Plane South Central FIPS Zone 4204 North American Datum 1983 Horizontal units: Survey feet d). All data layers, whether in GIS or CAD format, shall comply with the Spatial

Data Standards for installation and Environment (SDSFIE) version 2.6 format.

ATTACHMENT A: Interior Finish Material and Color Schedule