UFGS 02 41 00 Demolition.pdf
PDF 46 KB Posted
- Solicitation number
- W912K612R0003
About this file
Supporting Documentation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Electrical Drawing.pdf | ||
| Site Visit summary.docx | DOCX document | |
| map.pdf | ||
| W912K6-12-R-0003-0001.pdf | ||
| Exhibit C.docx | DOCX document | |
| W912K6-12-R-0003.pdf | ||
| UFGS 31 00 00 Earthwork.pdf | ||
| Exhibit F.docx | DOCX document | |
| EAL.xlsx | XLSX spreadsheet | |
| SOW PJMS112354 Demo Pump House 1152 and Water Stor 1151.doc | DOC document | |
| evaluation factors.docx | DOCX document | |
| Exhibit A.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 41 00
DEMOLITION
05/10
PART 1 GENERAL
1.1 REFERENCES
1.2 PROJECT DESCRIPTION
1.2.1 Demolition Plan
1.2.2 General Requirements
1.3 ITEMS TO REMAIN IN PLACE
1.3.1 Existing Construction Limits and Protection
1.3.2 Weather Protection
1.3.3 Trees
1.3.4 Utility Service
1.3.5 Facilities
1.4 BURNING
1.5 QUALITY ASSURANCE
1.6 DUST AND DEBRIS CONTROL
1.7 PROTECTION
1.7.1 Traffic Control Signs
1.7.2 Protection of Personnel
1.8 RELOCATIONS
1.9 EXISTING CONDITIONS
PART 2 PRODUCTS
2.1 FILL MATERIAL
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
3.1.2.2 Disconnecting Existing Utilities
3.1.3 Paving
3.1.4 Roofing
3.1.4.1 Temporary Roofing
3.1.4.2 Reroofing
3.1.5 Concrete
3.1.6 Structural Steel
3.1.7 Miscellaneous Metal
3.1.8 Patching
3.1.9 Electrical Equipment and Fixtures
3.1.9.1 Fixtures
3.1.9.2 Conduit and Miscellaneous Items
3.1.10 Items With Unique/Regulated Disposal Requirements
3.2 DISPOSITION OF MATERIAL
3.2.1 Title to Materials
3.2.2 Reuse of Materials and Equipment
3.2.3 Salvaged Materials and Equipment
3.2.4 Unsalvageable and Non-Recyclable Material
3.3 CLEANUP
3.4 DISPOSAL OF REMOVED MATERIALS
3.4.1 Regulation of Removed Materials
3.4.2 Burning on Government Property
3.4.3 Removal from Government Property
3.5 REUSE OF SALVAGED ITEMS
SECTION 02 41 00
DEMOLITION
05/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2008; Errata 1-2010; Changes 1-3 2010; Changes 4-6
2011) Safety and Health Requirements Manual
1.2 PROJECT DESCRIPTION
1.2.1 Demolition Plan
Prepare a Demolition Plan and submit proposed salvage, demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Identify components and materials to be salvaged for reuse or recycling with reference to paragraph Existing Facilities to be Removed. Append tracking forms for all removed materials indicating type, quantities, condition, destination, and end use. Coordinate with Waste Management Plan. Include statements affirming Contractor inspection of the existing roof deck and its suitability to perform as a safe working platform or if inspection reveals a safety hazard to workers, state provisions for securing the safety of the workers throughout the performance of the work.
Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Plan shall be approved by COR prior to work beginning.
1.2.2 General Requirements
Do not begin demolition until authorization is received from the COR. Remove rubbish and debris from the project site; do not allow accumulations inside or outside the building. The work includes demolition, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the COR. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the COR. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload structural elements or pavements to remain. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the COR prior to performing such work.
1.3.1 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement. Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove snow, dust, dirt, and debris from work areas daily.
1.3.2 Weather Protection
For portions of the building to remain, protect building interior and materials and equipment from the weather at all times. Where removal of existing roofing is necessary to accomplish work, have materials and workmen ready to provide adequate and temporary covering of exposed areas.
1.3.3 Trees
Protect trees within the project site which might be damaged during demolition and which are indicated by the COR to be left in place, by a 6 foot high fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the COR.
1.3.4 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, utilities serving each area of alteration or removal will be shut off by the Government and disconnected and sealed by the Contractor. For the electrical utility shutoff, the Contractor shall have full responsibility of coordinating work and scheduling with BGE, informing the COR of all communications.
1.3.5 Facilities
Protect electrical and domestic water services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and domestic water utilities. Floors, roofs, walls, columns, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished, unless directed otherwise by the COR. Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, or demolition work performed under this contract.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.5 QUALITY ASSURANCE
Comply with federal, state, and local hauling and disposal regulations. In addition, conform to the safety requirements contained in ASSE/SAFE A10.6. Comply with the Environmental Protection Agency requirements. Use of explosives will not be permitted.
1.6 DUST AND DEBRIS CONTROL
Prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
Sweep pavements as often as necessary to control the spread of debris that may result in foreign object damage potential to aircraft.
1.7 PROTECTION
1.7.1 Traffic Control Signs
Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Anchor barricades in a manner to prevent displacement by wind. Notify the COR prior to beginning such work.
1.7.2 Protection of Personnel
Before, during and after the demolition deconstruction work continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or failure while workmen remove debris or perform other work in the immediate area.
1.8 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor with new undamaged items as approved by the Contracting Officer.
1.9 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the COR showing the condition of structures and other facilities adjacent to areas of alteration or removal. Photographs sized 4 inch will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines alarm systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit survey results.
PART 2 PRODUCTS
2.1 FILL MATERIAL
Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition of structures.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
Inspect and evaluate existing structures onsite for reuse. Existing construction scheduled to be removed for reuse shall be disassembled. Dismantled and removed materials are to be separated, set aside, and prepared as specified, and stored or delivered to a collection point for reuse, remanufacture, recycling, or other disposal, as specified. Materials shall be designated for reuse onsite whenever possible.
3.1.1 Structures
a. Remove existing structures indicated to be removed as indicated in the Scope of Work
(SOW).
b. Demolish structures in a systematic manner from the top of the structure to the ground.
Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed. Demolish concrete walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the COR.
c. Locate demolition equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the COR. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing. Do not begin demolition work until all utility disconnections have been made. Shut off and cap utilities for future use, as indicated.
3.1.2.2 Disconnecting Existing Utilities
Remove existing utilities, as indicated in the SOW and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the COR. When utility lines are encountered but are not indicated on the drawings, notify the COR prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the COR.
3.1.3 Paving and Slabs
Remove sawcut asphaltic concrete paving including aggregate base for new electrical service trench. Provide neat sawcuts at limits of pavement removal. Pavement not to be used in this project shall be removed from the Installation at Contractor's expense.
3.1.4 Roofing
Remove existing roof system and associated components in their entirety down to existing roof deck. Remove ballasted single-ply roofing to effect the connections with new flashing or roofing. Remove roofing system without damaging the roof deck. Sequence work to minimize building exposure between demolition or deconstruction and new roof materials installation.
3.1.4.1 Temporary Roofing
Install temporary roofing and flashing as necessary to maintain a watertight condition throughout the course of the work. Remove temporary work prior to installation of permanent roof system materials unless approved otherwise by the COR. Make provisions for worker safety during demolition, deconstruction, and installation of new materials.
3.1.4.2 Reroofing
When removing the existing roofing system from the roof deck, remove only as much roofing as can be recovered by the end of the work day, unless approved otherwise by the COR. Do not attempt to open the roof covering system in threatening weather. Reseal all openings prior to suspension of work the same day.
3.1.5 Concrete
Saw concrete along straight lines to a depth of a minimum 2 inch. Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound.
3.1.6 Structural Steel
Salvage for recycle structural steel, angles, plates and shapes. Flame-cutting torches are permitted when other methods of dismantling are not practical and a Burn Permit has been issued. Transport structural steel shapes to a designated area as directed by the COR.
3.1.7 Miscellaneous Metal
Salvage metal soffit and fascia panels for reuse. Recycle scrap metal as part of demolition and deconstruction operations. Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the SOW.
3.1.8 Patching
Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work.
Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be as specified and indicated, and shall include:
a. Concrete and Masonry: Completely fill holes and depressions, caused by previous physical damage or left as a result of removals in existing masonry walls to remain, with an approved masonry patching material, applied in accordance with the manufacturer's printed instructions.
3.1.9 Electrical Equipment and Fixtures
Recycle motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Recycle wiring systems and components. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.
3.1.9.1 Fixtures
Remove and salvage electrical fixtures. Salvage unprotected glassware from the fixture and salvage separately. Salvage incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured prior to 1978, boxed and tagged for identification, and protected from breakage.
3.1.9.2 Conduit and Miscellaneous Items
Recycle conduit except where embedded in concrete or masonry. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.
3.1.10 Items With Unique/Regulated Disposal Requirements
Remove and dispose of items with unique or regulated disposal requirements in the manner dictated by law or in the most environmentally responsible manner.
3.2 DISPOSITION OF MATERIAL
3.2.1 Title to Materials
Except for salvaged and recycled items specified, and for materials or equipment scheduled for salvage or recycling, all materials and equipment removed and not reused, salvaged or recycled, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the COR of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the COR to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.2.2 Reuse of Materials and Equipment
Remove and store materials and to be reused or relocated to prevent damage, and reinstall as the work progresses.
3.2.3 Salvaged Materials and Equipment
Remove materials and equipment that specified to be removed by the Contractor and that are to remain the property of the Government, and deliver to a storage site as directed by the COR.
a. Salvage items and material to the maximum extent possible.
b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. On site sales of salvaged material is prohibited.
c. Remove salvaged items to remain the property of the Government in a manner to prevent damage while in storage or during shipment. Items damaged during removal or storage must be repaired or replaced to match existing items.
3.2.4 Unsalvageable and Non-Recyclable Material
Dispose of unsalvageable and non-recyclable noncombustible material in the disposal area offsite.
3.3 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.4 DISPOSAL OF REMOVED MATERIALS
3.4.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified offsite. Storage of removed materials on the project site is prohibited.
3.4.2 Burning on Government Property
Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.
3.4.3 Removal from Government Property
Transport waste materials removed from demolished and deconstructed structures, except waste soil, from Government property for legal disposal. Dispose of waste soil as directed.
3.5 REUSE OF SALVAGED ITEMS
Recondition salvaged materials and equipment designated for reuse before installation.
Replace items damaged during removal and salvage operations or restore them as necessary to usable condition.
-- End of Section --