Site Visit summary.docx
DOCX document 11 KB Posted
- Solicitation number
- W912K612R0003
About this file
Summary of items that should be noted for proposal
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Electrical Drawing.pdf | ||
| map.pdf | ||
| W912K6-12-R-0003-0001.pdf | ||
| Exhibit C.docx | DOCX document | |
| W912K6-12-R-0003.pdf | ||
| UFGS 02 41 00 Demolition.pdf | ||
| UFGS 31 00 00 Earthwork.pdf | ||
| Exhibit F.docx | DOCX document | |
| EAL.xlsx | XLSX spreadsheet | |
| SOW PJMS112354 Demo Pump House 1152 and Water Stor 1151.doc | DOC document | |
| evaluation factors.docx | DOCX document | |
| Exhibit A.docx | DOCX document |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
These items were talked about during the site visit and should be noted when providing a quote:
| 1) | New water service to Facility 1150 (as well as the eye wash) needs to be provided as the existing water service runs through the Pump House to be demolished. |
| 2) | The water in Fire Protection Water Storage needs to be TCLIP tested to determine how the water can be removed and meet all MDE requirements. |
| 3) | A water spout will be added when building 1152 is removed to allow for proper drainage. |
| 4) | Electrical drawings added. |