About this file

This is Amendment 0002 to Solicitation W912JD26QA025, issued by the W7TC USFPO Activity at Waterville, Maine, with an effective date of 08 SEP 2026. The amendment was issued by the Military Engineering and Research Office at Fort Detrick, Maryland, with contracting officer Thomas Ryan (thomas.j.ryan36.civ@army.mil, 207-430-5297).

The amendment addresses Government responses to contractor questions regarding the installation of emergency lighting and shore-power equipment on a Ford F-550 vehicle located at 1 Armory Road, Waterville, ME 04901. Key clarifications include: the contractor may perform installation at either the Government facility or their own facility within Maine, Vermont, New Hampshire, or Massachusetts; components are not pre-assembled and the contractor may make necessary modifications; demonstrated automotive electrical/upfitting experience is acceptable (no manufacturer certification required); the Whelen CORE system will be provided with a file by the Government, but the contractor is expected to install and program it, including adding a steady burn function; specific part numbers are provided for all Whelen lighting components, Kussmaul charger/Auto Eject components, and accessories; indoor shop/garage space will be provided at the Government location if needed; and the evaluation of past performance will focus on the prime contractor/quoter's ability to manage subcontractors and execute the work. The Supplier Performance Risk System (SPRS) evaluation applies only to the prime contractor. The due date and closing date for the solicitation remain unchanged from Amendment 0001.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Solicitation/Contract Form

The following changes have been made:

Miscellaneous text in this section has been modified to:

Amendment 0002

The due date for questions has not changed.

The closing date for the solicitation has not changed.

12. May the prospective prime contractor rely on its proposed subcontractor's technicians, relevant experience, past performance, and installation facility to satisfy the Technical (Subfactor 1.1-1.3) and Past Performance evaluation factors described in Section M, where the subcontractor - not the prime - would perform the actual installation work?

For the technical submission the proposed subcontractor's information may be the focus as it directly applies to how the quoted solution would fulfill the requirement.

The Government's past performance evaluation is focused on the prime/quoter. Past Performance shows the Government how well the prime contractor performed the work, in other words, how well they executed what was promised in the quote. "The past performance assessment will assess the prime's (hereafter referred to as quoter's) ability to successfully accomplish the proposed effort based on the quoter's demonstrated present and past work record." (Addendum to FAR 52.212-2 Evaluation, b. Past Performance Rating). If the prime contractor has had previous experience with their proposed subcontractor then that effort could be viewed as relevant. In the instance that the proposed subcontractor is an entity that the prime contractor has had no dealings with previously, the prime contractor could focus their past performance submission on efforts where they managed a subcontractor successfully as that is essentially what the prime is proposing to do for this effort.

13. Does the Supplier Performance Risk System (SPRS) evaluation described in Section M(c) apply only to the prospective prime contractor (the quoter), or does it also apply to any subcontractor performing the work?

W912JD26QA0250002

1.

2.

3.

SPRS evaluation applies only to the prime contractor (quoter). See response to question 12 for expanded past performance response.

Amendment 0001

The due date for questions has not changed.

The closing date for the solicitation has not changed.

Could you please confirm the exact physical address/place of performance where the Ford F- 550 will be available for the installation work?

1 Armory Road, Waterville, ME 04901; however we can drive the vehicle to necessary place of installation.

Can you provide the exact part numbers/models for the Whelen CORE/Controller, Inner Edge, and associated Whelen lighting components being supplied?

See answer 3.

Can you provide the exact model/part numbers for the Kussmaul battery charger/tender and Auto Eject components being supplied?

All parts listed below:

SMARTLED 600 Series (Red) x4 P/N: 01-06841264R0 SMARTLED 600 Series (Blue) x4 P/N: 01-06841264B0 Inner Edge Light w/PROCLEAR (left & right) P/N: 01-0688274L33V WHELEN Remote Siren HHS4200 P/N: 01-026H609-01C Super Auto Eject 20 (No P/N, 2 items this is the parts for the shore power) Model #: 091-55-20-120 S/N: S20227468 S/N: S2025371480 Charge Guard 12VDC (No P/N) S/N: 106-041 Siren Remote P/N: 01-0688277-00A KCT-23 Set (Multi Item) Cable set (w/Fuse holder): No P/N // Crimp terminal P/N:

E23-0692-X5 // Socket terminal P/N: E23-0686-X5 (x2) // Fuse 15A P/N: F05- 1537-X5 Door Lights x2 (Whelen three diode inner window mount, no P/N) 4" lights x4 (Whelen slim light surface mount, no P/NNo info) The whelen core system will need to be programmed, it may have a file on it but we would like to add a steady burn option as well and any other updates that core may need.

The truck and body are one unit already put together, there are no pre set mounting surfaces, all lights will need custom drilling for wire routing and mounting purposes

4.

5.

6.

7.

8.

9.

10.

11.

Will a Whelen CORE configuration/programming file be provided, or is the contractor expected to develop and program the system configuration as part of the installation?

Contractor will be expected to install. Unit can/will provide necessary file.

Does this requirement require any specific Whelen or Kussmaul manufacturer certification or authorized-installer status, or is demonstrated automotive electrical/upfitting experience acceptable?

Demonstrated automotive electrical/upfitting experience is exceptable.

Will the F-550 and VMRDS equipment body arrive fully assembled, and are necessary mounting penetrations through the equipment enclosure/body permitted for installation of the specified lighting and shore-power components?

Components are not assembled; contractor/installer is permitted to make modifications as necessary.

Is there a predetermined lighting/function specification for the Whelen CORE system, including required flash patterns, controller functions, ignition behavior, scene/warning functions, or other operating logic?

"Nothing is pre determined on the Whelen Core at this time, we would again like to add a steady burn function on the light system and all other sirens/lights can just be standard patterns/sounds.

What is the physical address/location of the Government-owned F-550?

See response to question 1.

Is the contractor expected to perform the installation at a Government facility, or may the vehicle be transported to the contractor's commercial installation facility?

Either If work is required at the Government location, will indoor shop/garage space be provided for the installation?

Yes If performance at a contractor facility is permitted, is there a maximum allowable distance or geographic restriction for transporting the Government vehicle?

Geographic restriction to Maine, Vermont, New Hampshire, or Massachusetts. We can drive the vehicle for installation anywhere within those four states.

IDCode: J
Page: 1
Pages: 4
AmendNo: 0002
EffDate: 08 SEP 2026
ReqNo:
ProjNo:
IssCode: W912JD
AdmCode:
IssuedBy: W7NC USPFO ACTIVITY ME ARNG

KO FOR MEARNG DO NOT DELETE, WITHROP STREET BLDG 39

AUGUSTA, ME 04333-0032

UNITED STATES

THOMAS RYAN, EMAIL: THOMAS.J.RYAN36.CIV@ARMY.MIL TELEPHONE: (207) 430-5297

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912JD26QA025
SolDate: 21 AUG 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is for the Government to provide responses to questions asked by interested parties.
ContNameTitle:
CoNameTitle: DARLENE HOWES
ContDate: