1.
Q; Is the bid bond penalty 20%?
A; Yes.
2.
Q; Is the bid bond form your Standard Form 24?
A; Yes.
3.
Q; Will you be requiring Performance & Payment Bonds from the low bidder? If so, are they the
Standard Form 25 and Form 25A?
A; See solicitation document.
4.
Q; What is the completion date?
A; CLINs 0001 and 0002 are 120 from the Contract Date. CLIN 0003 will be in the Spring due to the time of year and CLIN 0004 is as stated.
5.
Q; Are there any liquidated damages, if the project is not completed by the completion date? If so, what are the LD’s per calendar day?
A; No.
6.
Q; Are we allowed to email the bid?
A; No.
7.
The following clarifications are in response to the Aug. 29th site visit bid questions.
CLARIFICATION 1: The existing sewer line running from bldg. B494 ties directly into the sewer main with a "T" connection. Contractor shall excavate to remove the existing sewer line from the building foundation out to the point shown on the revised drawing C201 and cap /plug off the sewer line with mortar or concrete. Key note 4 has been revised to reflect the sewer line change. See attached revised drawings C201.
CLARIFICATION 2: Delete both key notes 7 on drawing C201. The overhead communication line has been removed and the camera also has been removed. See attached revised drawing C201.