015000_Temporary_Controls_B494.pdf

PDF 56 KB Posted

Attached to
Demolition of Buildings 494 and 418
Solicitation number
W912JD-16-B-2002
Issued by

About this file

Temp Controls

View the file

Other files

File Type Posted
Record_of_Attendance.pdf PDF
SF_1409.pdf PDF
Q A.pdf PDF
Rec_of_Att.pdf PDF
Site_Visit_Deconstruction_of_Buildings.pdf PDF
C201_Revised.pdf PDF
329200_Turf_Grasses_B494.pdf PDF
Site_Demolition_Plans_B494.pdf PDF
312000_Earth_Moving_B494.pdf PDF
024100__Deconstruction_B494.pdf PDF
SOW_Deconstruct__B418.pdf PDF
16-B-2002.pdf PDF
SOW_Deconstruct_B494.pdf PDF
Record_Dwg_B494.pdf PDF
021200__Disposal_Haz_Waste_B494.pdf PDF
Site_Demolition_Plans_B418.pdf PDF
Asbuilts_Drawings__1986_B418.pdf PDF
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAINE AIR NATIONAL GUARD

BANGOR, MAINE

TEMPORARY CONTROLS 015000-1

SECTION 015000 - TEMPORARY CONTROLS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Statement of Work, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for support facilities, and security and protection facilities.

B. Related Requirements:

1. Section 31100 “Site Clearing” for temporary erosion and sedimentation control measures.

2. Statement of Work and Contract for work restrictions and limitations on utility interruptions.

PART 2 – PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 SUPPORT FACILITIES INSTALLATION

A. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain including curbs, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

B. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction.

Maintain Project site, excavations, and construction free of water.

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties or endanger permanent Work or temporary facilities.

2. Remove snow and ice as required to minimize accumulations.

3.2 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Protection of Existing Facilities: Protect existing vegetation, equipment, structures, utilities, and other improvements at Project site and on adjacent properties, except those indicated to be removed or altered. Repair damage to existing facilities.

1402474072N Typewritten Text 27 June 2016

1402474072N Typewritten Text Attachment 1

MAINE AIR NATIONAL GUARD

BANGOR, MAINE

TEMPORARY CONTROLS 015000-2

B. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

1. Comply with work restrictions specified in Statement of Work and Contract.

C. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas and to adjacent properties and walkways, comply with environmental regulations.

1. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross tree- or plant- protection zones.

2. Inspect, repair, and maintain erosion- and sedimentation-control measures during construction until permanent vegetation has been established.

3. Clean, repair, and restore adjoining properties and roads affected by erosion and sedimentation from Project site during the course of Project.

4. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.

D. Stormwater Control: Comply with requirements of authorities having jurisdiction. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.

E. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

F. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.

END OF SECTION