W912JD-16-B-2001-P00002_Conformed.pdf
PDF 500 KB Posted
- Solicitation number
- W912JD-16-B-2001
About this file
W912JD-16-B-2001-0002 Conformed Amendment
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID_OPENING_ATTENDANCE_ROSTER.pdf | ||
| OF_1419-Final.pdf | ||
| W912JD-16-B-2001-0002_Pages_for_Acknowledgment.pdf | ||
| Checklist_for_Bid_Bonds.docx | DOCX document | |
| 2016-07-27_MEANG_Bangor_Fire_Station_-_Comm_Manhole_Site_Inspection_Report.pdf | ||
| Final_Pre-Award_RFI.doc | DOC document | |
| SK-001.pdf | ||
| ANG_AddAlter_Fire_Station_-_Geotechnical_Report.pdf | ||
| Fire_Dept_Communication_Manholes.pdf | ||
| Pre-Award_RFI_1_20160726.doc | DOC document | |
| 465393.pdf | ||
| 1.2.5_-_Existing_Floor_Plans.pdf | ||
| W912JD-16-B-2001-0001.pdf | ||
| Revised_M-603.pdf | ||
| Pre-Award_RFI_1_20160720.doc | DOC document | |
| Pre-Award_RFI_1_20160719.doc | DOC document | |
| Pre-Award_RFI_1_20160715.doc | DOC document | |
| Pre-Award_RFI_1.doc | DOC document | |
| 16-B-2001_SITE_VISIT_PPT.pdf | ||
| SITE_VISIT_ROSTER.pdf | ||
| Division_01_General_Requirements.pdf | ||
| W912JD-16-B-2001_ADAL_Fire_Crash_Rescue_Station.pdf | ||
| Add-Alter_Fire_Crash_Station_Brand_Name_Item_JA_16B2001_V0.1.pdf_Redacted.pdf |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912JD-16-B-2001-0002
F7QJCE6147A001
Add./Alter. Fire Crash Rescue Station PN: FKNN059220
This project consists of construct an addition of 2550sf and renovating the existing Base Fire, Crash, Rescue Station’s 16,850sf at the Maine Air National Guard Base in Bangor, ME (Penobscot County). This project w ill provide the required space for training, personal protective equipment lockers, mobility storage, apparatus storage and equipment maintenance facilities, administrative off ices, enlarged physical f itness training area, laundry and sleep rooms. This project w ill renovate current spaces to better utilize existing square-footage as w ell as provide new square footage that supports daily operations.
This project is being solicited as a Small Business Set Aside. The North American Industry Classification (NAICS) code is 236220, and the Small Business Size Standard is $36.5M in average annual receipts for the previous three years. Construction magnitude is betw een $5M to $10M. Persons w ho intend to bid are strongly encouraged to attend the Pre-Bid Conference. See Section 00100 for location and date. All documents including plans and specif ications w ill be available only from FedBizOps w ebsite: w w w .fbo.gov.
X
JASON M. EDWARDS 207 404 7107
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
16-Jun-2016
(RFP)
(IFB)
CALL:
ADAL FIRE CRASH RESCUE STATION
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________540 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________04 Aug 2016 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
101 MSG/MSC BASE CONTRACTING
JASON M. EDWARDS
101 MAINEIAC AVENUE, SUITE 505
BANGOR ME 04401-8010
W912JD
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
FKNN059220
8. ADDRESS OFFER TO (If Other Than Item 7)
207 404 7177FAX:TEL: 207 404 7107 TEL: FAX:
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912JD-16-B-2001
Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
BASE BID FOR PN: FKNN059220
FFP
Non personal services: Provide all plant, labor, new and current material, transportation, tools, equipment, appliances, supplies, services, permits, insurance and supervision necessary to build a 2,550sf addition and renovate 16,850sf in the Fire, Crash, Rescue Station in accordance with specs dated 28 March 2016 and drawings dated 28 March 2016.
FOB: Destination
SIGNAL CODE: A
NET AMT
0002 1 Job
ADDITIVE BID ITEM #1
FFP
This is priority #1. Replace Overhead Doors
0003 1 Job
ADDITIVE BID ITEM #2
FFP
This is priority #2. Reconstruct Sills and Weatherstripping.
0004 1 Job
ADDITIVE BID ITEM #3
FFP
This is priority #3. Upgrade Interior Finishes.
0005 1 Job
ADDITIVE BID ITEM #4
FFP
This is priority #4. Remove Pavement; Add loam/seed/mulch.
0006 1 Job
ADDITIVE BID ITEM #5
FFP
This is priority #5. Replace unit heaters in renovated spaces.
0007 1 Job
ADDITIVE BID ITEM #6
FFP
This is priority #6. Add etched glass emblem at entry.
0008 1 Job
ELECTRICAL ALLOWANCE
FFP
A $20,000 allowance for the coordination and relocation of two existing utility poles. Allowance is in reference to drawing C-104, Site Utility Plan. This CLIN is informational only.
FOB: Destination
PURCHASE REQUEST NUMBER: F7QJCE6147A001
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government
0003 Destination Government Destination Government 0004 Destination Government Destination Government 0005 Destination Government Destination Government 0006 Destination Government Destination Government 0007 Destination Government Destination Government 0008 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC
0001 540 dys. ADC 1 101 ARW/CE
JOHN CRONIN
CIVIL ENGINEERS - F7QJCE
106 ASHLEY AVENUE
SUITE 486
BANGOR ME 04401-8029
207-404-7112
F7QJCE
0002 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0003 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0004 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0005 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0006 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0007 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
0008 540 dys. ADC 1 (SAME AS PREVIOUS LOCATION)
SECTION 00010 NOTES
SECTION 00010 Solicitation Contract Form
TABLE OF CONTENTS
SOLICITATION, OFFER, AND AWARD SF 1442 and SF 1442 BACK
SECTION 00010 - BID SCHEDULE, NOTES
SECTION 00100 - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
SECTION 00600 – REPRESENTATIONS & CERTIFICATIONS
SECTION 00700 - CONTRACT CLAUSES
SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS
ATTACHMENT 1 – PLANS AND SPECIFICATIONS Project # FKNN059220 Dated 14 June 2016
ATTACHMENT 2 - DIVISION 01 GENERAL REQUIREMENTS
ATTACHMENT 2- BRAND NAME JUSTIFICATION & APPROVAL, Dated 13 June 2016 ATTACHMENT 3- SOLICITATION QUESTIONS AND ANSWERS DOCUMENT 27 July 2016
ATTACHMENT 4- FINAL REPORT, REGIONAL COMPLIANCE RESTORATION PROGRAM
PRELIMINARY ASSESSMENT/SITE INSPECTION BANGOR AIR NATIONAL GUARD BASE, BANGOR,
MAINE, July 2015
ATTACHMENT 5- BID BOND CHECKLIST
ATTACHMENT 6- FIRE DEPT COMMUNICATION MANHOLES
ATTACHMENT 7- 1.2.5 - EXISTING FLOOR PLANS
ATTACHMENT 8- ANG ADDALTER FIRE STATION - GEOTECHNICAL REPORT
ATTACHMENT 9- 2016-07-27_MEANG BANGOR FIRE STATION - COMM MANHOLE SITE INSPECTION REPORT, Dated 27 July 2016 ATTACHMENT 10- SK-00,1MANHOLE RELOCATION SKETCH, Dated 27 July 2016
SECTION 00010 NOTES
NOTES
1. All questions and requests for information regarding this Invitation For Bids (IFB) must be received NOT LATER THAN close of business five days prior to bid date in order to minimize the need to extend the bid opening date. Questions shall be emailed to: dirck.g.storms.mil@mail.mil and jason.m.edwards1.mil@mail.mil.
2. Offeror’s attention is invited to the insurance requirement contained in this solicitation (Contract Clause FAR 52.228-5). Certification of the required coverage for the prime contractor shall be furnished prior to beginning work on this contract, and the Contracting Officer may request evidence of the required insurance at any time during the life the contract.
3. Reference Contract Clause 252.236-7008, CONTRACT PRICES – BIDDING SCHEDULES (DEC 1991).
The prices shown in the Bidding Schedule must reflect ALL costs involved in performing the work, as described in the plans and specifications.
4. The term “Bidding Schedule” shall also be construed to mean “Offer Schedule” or “Schedule”. The terms “bid” and “offer”, and “bidder” and “offeror” shall be construed as having the same meaning in this solicitation and resulting contract.
5. All information relating to this IFB, including pertinent changes/amendments and information will be posted on web site: http://www.fbo.gov.
6. Facsimile transmission of bid is not authorized.
7. Government reserves the right to include additive bid items taken at time of award in the Base CLIN to facilitate and simplify schedule and payment processing.
8. All information relating to this IFB, including pertinent changes/amendments and information will be posted on web site: http://www.fbo.gov. For security reasons, all potential offerors, plan rooms and printing companies are required to be registered in the GSA System for Award Management (SAM) database. Firms can register via the SAM internet site at https://www.sam.gov/portal/public/SAM/. Interested bidders are required to submit their representations and certifications at the same site. You will need your DUNS number and MPIN in order to log in to the Online Representations and Certifications Application (ORCA) website. The solicitation and associated information and the plans and specifications will be made available only from the Federal Business Opportunities (FedBizOpps) website on-line at https://www.fbo.gov/
9. FedBizOpps is a web-based dissemination tool designed to safeguard acquisition-related information for all Federal agencies. Interested bidders/offerors must register with FedBizOpps before accessing the system.
FedBizOpps registration requires the following information: 1) Central Contractor Registration (CCR) Marketing Partner Identification Number (MPIN), 2) DUNS Number and CAGE Code, 3) Telephone Number,
4) Email address. Registration instructions can be found on the FedBizOpps website at https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf. Contractors who do not already have a MPIN are advised that the normal processing is 15-30 business days to obtain a MPIN password that will give them access to the plans and specifications, which are located in the controlled access location on FBO. (PLAN ACCORDINGLY). Reference paragraph 4.4 of the Vendor Guide for instructions to retrieve the specification and drawing documents for this project. DISCLAIMER: The official plans and specifications are located on the official government webpage and the Government is not liable for information furnished by any other source.
Amendments, if/when issued will be posted to https://www.fbo.gov/ for electronic downloading. This will normally be the only method of distributing amendments prior to closing; therefore, it is the offerors responsibility to check the website periodically for any amendments to the solicitation. Websites are occasionally inaccessible due to various reasons. Reference paragraph 4.7 of the Vendor Guide for instructions to obtain a MPIN to retrieve the specification and drawing documents. Bidders/offerors who have registered with FedBizOpps must access the data for this solicitation with their MPIN. Bidders/Offerors cannot log into the FedBizOpps home page and search for data
10. CLINS 0002 through 0007 are additive bid items. The Government will determine apparent low bidder in accordance with the procedure described in DFARS Provision 252.236-7007, Additive or Deductive Items.. After determination of apparent low bidder the Government may award any combination of line items.
See section 00100 Evaluation of Bids for an explanation as how the low bid will be determined for this solicitation.
11. A complete bid package must contain the following:
(a) Offer, Standard Form (SF) 1442 front and back signed
(b) Section 00010 Line Items- all items must be priced
(c) A valid Bid Bond. Standard Form 24.
(d) Section 00600, Representations and Certifications, completed and return only additional certifications found in this section In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications (ORCA), is http://orca.bpn.gov.
(e) When completing the “Offeror” portion of the SF 1442 (Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR 4.102.
One copy of the SF1442 is required to have an original signature.
(f) All amendments to the solicitation must be acknowledged.
(g) Mark the front of the envelope with the following: “BID No. W912JD-16-B-2001”, and the Name and Address of Bidder. See Block 13A of SF 1442 for required number of copies.
End of Section 00010 word document
PRE-AWARD RFI'S
27 July 2016
Point of Contract: MSgt Jason Edwards Contract Specialist jason.m.edwards.mil@mail.mil Tel: (207) 404-7107
Project Title and No: Add./Alter. Fire, Crash, Rescue Station; FKNN059220
The purpose of this amendment is:
1. Address Requests for Information (RFI’s) received as a result of the pre‐bid conference/site visit and contractor reviews of the plans and specifications. This is a running document and the final document will be incorporated by amendment prior to bid opening.
Please remember to acknowledge receipt of this Amendment on the original Invitation for Bid (IFB) Form in the appropriate block.
All other terms and conditions remain unchanged by this amendment.
Q1. There are drawings in the bid set that are stamped “Not for Construction” dated March 28, 2016. Are we to use these drawings for our price proposal?
A1. As mentioned as the pre‐construction conference and site visit the plans and specifications dated 28 March 2016 would be replaced with final plans and specifications. The Final plans and specifications dated 14 June 2016 were uploaded to FBO.gov on 13 July 2016. The plans and specifications dated 14 June 2016 shall be used for price proposal and performance of construction.
Q2. Spec Section 232113 (Hydronic Heating) paragraph 3.1.A.1 and 3.1.B.1 require that copper joints be brazed instead of soldered, is it really necessary to have brazed joints?
A2. Not necessary to have brazed joints. Joints can be soldered.
Q3. Do you know which drawing the "Cutout dimensional characters" are on?
A3. "Cutout dimensional characters" are meant to reflect exterior Bay #'s on the Overhead doors. They are found on A‐201 & A‐202.
Q4. Page 1 of the SF1442 states time of completion is 540 CD, page 40 states it is 365 days.
A4. The period of performance is 540 calendar days. The correction to FAR 52.211‐10 has been incorporated into this amendment.
Q5. Page 13 referenced Davis Bacon Wage Determination website, which when used, the date of the Determination is 7/1/16. Page 59 thru 64 of the SF1442 provides a Davis Bacon Wage Determination that is dated 4/1/16.
A5. The most current Davis Bacon Wage Determination will be used. At the time of the Invitation for Bid, 4/1/16 was the most recent determination. This amendment incorporates the 7/1/16 determination.
Q6. There doesn’t appear to be a requirement for Builder’s Risk Insurance. Please confirm that the General Contractor it is not required to provide BR Insurance for this project.
A6. Builders risk is not required. Contractors shall carry insurance as indicated in FAR 52.228‐5 – Insurance – Work on a Government Installation.
Q7. Metal Lockers 105113: 2.3‐I calls for recessed door handle and latch, but 2.3‐J calls for a projecting turn handle and latch. Please confirm the desired handle and latch.
A7. 2.3‐I calls for recessed door handle and latch is the correct option. 2.3‐J should have been deleted.
Q8. Metal Lockers 105113: 2.3‐P calls for a continuous Z base, but is shown in the elevations and details on a plywood base with a tile face. Please confirm desired base condition.
A8. 2.3‐P, continuous Z base should be removed from specs. Drawings indicating section details with raised/tiled base is the desired detail.
Q9. Drawing A603 Window and Storefront Types: Please provide clarification as to which of the elevations are storefront and which are aluminum windows. For example, elevation E10 is depicted as a window, but detail 1/A322 depicts it as a storefront.
A9. A‐603 is correct, as it shows Window types above the Header title "Window Types". Storefronts are labeled and located to the right of the window Schedule, but with "SF" designations See A94 for clarification on all window and storefront information.
Q10. Reference drawing P‐101. There is a new ¾” domestic HW recirculation line that begins in the ceiling of Conference Room 105 off the 1” domestic HW line. Should a balancing valve be installed there to control the hot water recirculation volume?
A10. A balancing valve is not necessary in the hot water recalculation loop. There is a recirculation pump located in the boiler room that is controlled by an aqua‐stat. The pump turns on/off to maintain the temperature of the aqua‐stat. Nothing is achieved by adding a constriction (balancing valve) in the loop.
Q11. Temporary Facilities & Controls 015000‐3.4‐I‐4: Will temporary standpipes and hoses actually be required for temporary fire protection?
A11. This is not anticipated as part of the proposed work, but they are included in the Specification to clearly establish them as Contractor responsibilities in the event they become necessary.
Q12. Temporary Facilities and Controls 015000 & Closeout Procedures 017700: Both specifications make reference to pest control services, pest control field reports and pest control final inspection reports. Is there a specific expectation for pest control needs on this project?
A12. This is not anticipated as part of the proposed work, but they are included in the Specification to clearly establish them as Contractor responsibilities in the event they become necessary.
Q13. E104, Key Note 4 calls for a surface mount fixture on GWB for the base bid. However AD122 and A112 are showing ACT ceiling. Please confirm existing ceiling type and desired fixture mounting for base bid and alternate.
A13. Disregard note for surface mount fixture. Existing ceiling is ACT; ABI #3 is to replace ACT in‐kind. In either case, a recessed fixture will be required.
Q14. E104, Key Note 1 in room 205 call for a recessed downlight. The L fixture shown does not match the application. Should this be a K fixture which is a recessed can and there are none shown currently?
A14. The fixtures identified by Keyed Note #1 in Room 205 shall be Type K fixtures (recessed downlight) for installation into gypsum soffit.
Q15. E104, Key Note 6 is shown in Bunk Rooms 221‐237 but the 3‐way switches and “In Use” lights are gray as if they are existing. In Bunk rooms 238‐240, the switched and IU’s are black, as if new but there is no note.
Please confirm our scope of work where note 6 is located and in Bunks 238‐240? If we are to provide in “in use” lights, please specify a model?
A15. Keyed Note #6 shall also apply to Bunk/Toilet Rooms 238‐240. Provide In‐Use light new for these rooms.
Fixture shall be similar to existing Bunk Rooms. Use RT Technologies product LEDS‐RIU‐2W as basis‐of‐design product.
Q16. E102, Note 4; does this note refer to the 12 exterior on circuits diamond 4 & 5? ED102 does not indicate to salvage these fixtures.
A16. Exterior building‐mounted fixtures are existing to remain. See Note #3 on Sheet ED‐102. Fixtures are to be temporarily removed ‐ if required ‐ to accommodate building siding replacement. Exterior building fixtures are controlled via photocell through lighting contactor, in conjunction with Note #4 on Sheet E‐102.
Q17. E102, Note 8; should we provide a metering device for 2 circuits – Keynotes 1 and 3? Please specify the desired metering device.
A17. (Assume this should be Note #7 on Sheet E‐102, re: metering exterior lighting) Use AcuAmp current transducer as a basis‐of‐design metering device. Device shall be capable of outputting a signal to building management system for recording.
Q18. E102, Vehicle Bays: Please clarify the switching scheme in this area? There are no zones indicated and each OS is adjacent to fixtures on 2 or 3 circuits. Could we consider getting the D fixture with an integral occupancy sensor?
A18. For bidding, please consider Type D fixture with integral occupancy sensor.
Q19. C104, Key Note 7; should we provide 1” with 3‐#10 for site lighting circuit?
A19. Yes, that is acceptable. Keyed Note #1 on Sheet E‐102 covers this lighting circuit.
Q20. C104, Key Note 8; assuming the 6 new pole lights are the BB fixture on the E502 schedule? Please provide more info on this fixture; wattage, mounting height?
A20. New pole lights are Type BB fixture on Sheet E‐502 schedule. Fixture shall match existing pole‐mount fixtures. As basis‐of‐design, use Cree OSQ Symmetric Type V, 215‐watt, 5700K. Existing pole‐mount fixture shall be confirmed with Contracting Officer upon contract award.
Q21. C104, Key Note 6; please confirm that we should provide 5‐1” conduits to the security turnstile as per Key Note 9 on E101? Please advise if there are PA devices and required cabling at the turnstile; none is shown?
Please advise if we should include any communications or security system cabling to the turnstile?
A21. Provide (5) 1" conduits as indicated by Keyed Note #9 on Sheet E‐101. Security system is by Government in future ‐ provide pull strings for all spare/future use conduits. Provide PA speaker at gate with associated wiring.
Q22. C104, Key Note 5; Please advise what the electrical contractors scope is for this item? What is the existing duct bank; size and quantity of conduits? What is the existing cabling, where does each cable run from/to, and what is the intent to do with the cabling?
A22. Contractor will be required to coordinate and complete the relocation of the existing communications manhole. Existing duct bank, size and quantity of conduits are unknown. It is our understanding the line (s) service the FAA tower. Existing cabling is being researched by Base Communications. Drawings will be posted to FBO.gov.
See attached inspection report dated 7/27/16 for description of existing services. Attached SK‐001 outlines the installation of a new electrical vault and riser and abandonment of the existing vault in place to accommodate the proposed building addition.
Q23. C104, there is a callout in the middle of the sheet “relocate existing utility pole and overhead electric”.
Please advise what the electrical contractor’s scope is regarding this item? What is the hardware or equipment on the pole and what cabling does it support?
A23. Contractor is required to coordinate and complete relocation of two existing utility poles. Poles are owned by Emera Maine and/or Fairpoint Communications. We believe these provide power to the existing Fire, Crash/Rescue Station and adjacent Taxiway lighting. CLIN0008 is incorporated by amendment requiring all bidders to carry a $20,000 allowance for this work. Reference also Q46. and Q99.
Q24. 260553‐2.1 and 3.1‐A mentions MC Cable, but 260519 does not. Will MC Cable be acceptable for all concealed wiring? Or will MC be allowed for drops to devices in existing walls and 6’ whips to fixtures?
A24. MC cable will be allowed for new and existing wall cavities and lighting fixture whips. Above ceiling shall be conduit.
Q25. 262416‐1.4‐A‐1 regarding studies: Do we need to provide studies for the 1 panel that we are adding to the existing distribution system, or provide studies on the complete existing system?
A25. Study is only required for new panel P3.
Q26. The millwork plans indicate plastic laminate tops, as do the specifications, but the detail sections refer to solid surface. Please confirm desired surfaces.
A26. Follow the specifications direction to use plastic laminate surface, not solid surfacing.
Q27. Please confirm that the Maine Air National Guard will not allow substitutions for Sargent 8200 Mortise Lock Campus, Sargent 8800 Exit Device Campus, and Sargent Interchangeable Core Key System.
A27. Correct. Sargent is a brand name requirement as indicated in Section 00100 INSTRUCTIONS of the Invitation for Bid. No substitution or deviation will be authorized.
Q28. Drawing P‐501 – Typical HVAC Condensate Piping detail indicated that condensate piping is PVC. Spec section 232113, para 3.1.D states that the condensate piping is to be copper tube. Please clarify.
A28. Use ASTM D 1785, Schedule 40 PVC pipe and solvent‐welded fittings. See Spec Section 237200 3.2.H.
Q29. Please provide requirements for the FAA Clash Alarm (Klaxon) and FAA Alert Alarms shown on drawings E101 and E03 including specifications, wiring requirements, etc.
A29. Wheelock UTA‐WH series, 120‐volt AC power, CAT 6 cable input.
Q30. Please provide riser diagrams for the Communications and Public Address Systems.
A30. Communications backbone is existing. Contractor shall route horizontal voice/data cabling from jacks back to patch panels in Computer Equipment Room. Public Address System is a prescriptive specification.
Contractor shall provide a new system to meet requirements.
Q31. Reference Note 4 on drawing E‐101. Please elaborate on this note if the requirements are beyond the specific exterior wall mounted speakers shown on drawing E‐101.
A31. Public Address System shall be audible from all areas of the Fire Station property boundary. Provide adequate speaker coverage on exterior poles and structures to meet audible requirement. For purposes of bidding, consider a minimum of ten (10) exterior pole/structure mounted speakers in addition to those shown as mounted to building (Fire Station).
Q32. Reference demolition note #9 on drawing ED‐103. Do these conduits contain existing wiring? If so, please identify the wiring, source, etc.
A32. Existing conduits are assumed to contain wiring but size and quantity are unknown. Conduits traverse from 1st Floor Room 107 (Maint. Repair Storage) to above 2nd Floor Ceiling. For purposes of bidding, assume the following:
(30) CAT 6 cables from 2nd Floor Comp. Equip. Room to 1st Floor
(10) 120‐volt, 1‐phase circuits from Panel EP in Room 107 to 2nd Floor Areas (Lighting, FACP, etc.). Assume each circuit consists of (2) #12 AWG & (1) #12 GND conductors.
Contractor shall verify quantities and loads in the field.
Q33. The new windows on the North Elevation are required to meet AT/FP blast hazard mitigation per UFC‐ 010‐01 as noted in spec 085113. Other than replacement of wood blocking, there are no upgrades to the existing exterior walls. Is the Contractor to assume the existing exterior walls are structurally sufficient to meet the AT/FP window installation?
A33. Due to current standoff distance the existing openings and walls are adequately designed.
Q34. We cannot find a specification for the aluminum diamond wall plate shown on drawings A‐401 and A‐
404. Please provide.
A34. Interior grade Aluminum wall covering is to be used. Basis‐of Design product “Diamond Life, MaxTile F1, Aluminum wall tile” and associated trim details at all corners and top and bottom of wainscot heights, applied in accordance with manufacturers standards.
Q35. We cannot find a specification for the industrial steel shelving that is shown on drawing A‐101, keynote #5.
A35. Basis‐of‐Design Product: Global Industries heavy Duty Industrial Shelving, Model #WG258180
Q36. Corner guards are noted to be installed in the circulation corridors. Please clarify what are circulation corridors.
A36. “Circulation corridors” include: Corridor #102, Corridor #119, Corridor #202 and Corridor 208.
Q37. Roof Spec 075423, para 3.8.B states that the concrete roof pavers are to be installed with 3” space between adjacent pavers. Detail 3 on drawing A‐332 notes that the concrete pavers are to be installed on a pedestal system and drawing A‐114 plan indicates that the pavers are to be installed without a gap between the pavers. Please clarify the roof paver installation and pedestal system.
A37. Roof pavers are to be installed to align with top of finished 2nd floor as noted on Key Note #16, drawing A‐
103. The pavers need to allow for water drainage to roof drain. Since the roofing will be sloped to drain, and a level paver surface is required, providing a 3” max pedestal height that is adjustable is required. This will allow for proper leveling coordination between roofing slope and finished floor elevation. (ie. Pavers near the terrace access door may be ½” raised pedestal, and pavers adjacent to roof drain may be raised 3”+/‐. Field conditions will vary upon existing roofing removal and should be verified prior to installation).
Q38. Detail 6 on A‐405 shows a TV wall mount bracket but we cannot find a specification for it. Please provide.
A38. This item is GFCI (Government Furnished, Contractor Installed). Locations on elevations are for blocking purposes within walls. Coordinate mounting heights with tv mounts in existing bunk rooms.
Q39. Note 5 on drawing A‐601 requires the Contractor to inspect all existing doors, frames and hardware.
Please confirm that the Contractor inspects only and is not required to carry any repair work at this time.
A39. Contractor shall inspect all existing door hardware and notify Government of any damaged hardware, and coordinate replacement in‐kind to be included as a part of “finish upgrade ABI #3.
Q40. E101, Key Notes 4 and 6: What is CFCI Smartboard? Is it “contractor furnished contractor installed”? If we are to provide the Smartboard, please specify?
A40. CFCI = Contractor Furnished; Contractor Installed. Assume SMARTBoard Model SBM685i6.
Q41. E101, Keynote 8 is shown next to a GB2 symbol (2‐gang box)? Please provide more information as to what is required such as part numbers and wiring diagram? Or are we just to provide rough‐in to the box?
A41. GB2 = two‐gang box. Devices are Wheelock UTA‐WH series, 120‐volt AC power, CAT 6 cable input.
Q42. E101, Key Note 10; Please confirm that we are only to provide power to the VES devices and the controller? Is there a switching device for each VES at the control panel (do the conductors need to run thru the CP)? Is the EC responsible for control cabling, or the controls contractor?
A42. Definitive system control will be based upon submitted/approved system and shall be coordinated during installation. For purposes of bidding, assume EC provides power to each VES Fan through the VES control panel.
VES control panel requires separate power source by EC. Control wiring by controls contractor.
Q43. E101, Note 4: Please provide more information as to what is required? Does each lighting pole get 1 speaker; what mounting height? Do we need more the building mounted exterior speakers shown for “exterior building areas”? Is the conduit for PA in Key Note 9 for the pole mount speakers, or does this go to the security turnstile?
A43. Refer to Q/A #31. Conduit in Keyed Note #9 is for both Public Address System and turnstile.
Q44. E01 Note 6: Please confirm if we should delete the DF’s as indicated in E603 Unit Heater Schedule note 1?
A44. Confirmed – if ABI #5 is approved, DFs are deleted from scope.
Q45. Refer to drawing A603, are widows E1, E4, E5 and E9 to receive BOTH shades and verticals?
A45. See A60, A61 & A62 for answers
Q46. From RFI Log, #23, Regarding the Existing Utility Pole and Overhead Electric Relocation: Will the owner cover the Emera/Fairpoint fees? If the contractor is to cover fees, could an allowance be established? Also, is there any underground conduit/cabling turning up at this pole? If so, please describe size, type, from‐to?
A46. Contractor is responsible for Emera/Fairpoint fees. No allowance will be established, however, a cost reimbursement change order will be contemplated with appropriate documentation and in accordance with the Federal Acquisition Regulation and its supplements. See updated response to Q23, Q80 and Q99.
Q47. Drawing A‐601 door schedule shows sectional doors, elevation sheet A‐201 & A‐202 show sectional but under keyed noted call out roll‐up. Spec header is sectional and, R‐value is sectional, thickness is sectional but under Door Assembly Overhead model 627 is coiling (roll‐up) door. Please clarify.
A47. All Doors labeled “OH” on drawing A‐601 should be sectional doors, and should match existing door models. ABI #1 includes replacement of sectional doors, and would be new, but in‐kind. They are not to be “coil‐ up” doors. The R‐Value and thickness are accurate and the “Basis of Design” product listed should be deleted.
Existing doors are to be matched. Verify‐in‐Field.
Q48. Have not located the “Existing Hazardous Material Information” could those be made available through the FBO site?
A48. File is uploaded to FBO.gov as annotated in amendment P00002.
Q49. Drawing A‐113 Note 9 specifies Stainless Steel floor grates, Specification 124816 2.3B calls for aluminum. Please advise which is correct.
A49. Aluminum floor grates
Q50. Drawing A‐503 Det 1 Drawing specifies galvanized embed and Specification 124816 2.4 says to match grating material. Please advise which is correct.
A50. Drawing A‐503 does not exist. Please clarify.
Q51. Specification124816 2.3.B.1.a specifies Aluminum Color: As selected by Architect from full range of industry colors and color densities. This says industry colors as opposed to manufacturers colors, could this include custom colors?
A51. Should be color selected by Architect from manufacturers standard finishes. No custom colors.
Q52. Specification 076200 1.5.E.4 specifies Anodized Aluminum Samples: Samples to show full range to be expected for each color required. This section is under submittals but the specification does not give a color requirement. Please advise if color is from manufacturer standard or custom.
A52. All exposed trim/flashing/coping/etc. finishes should be selected to match colors as noted on A‐201 & A‐
202. This shall require custom colors if manufacturers standard colors cannot be matched.
Q53. Specification 084113 2.10A specifies Baked‐Enamel or Powder‐Coat Finish: AAMA 2603 except with a minimum dry film thickness of 1.5 mils. Comply with coating manufacturer's written instructions for cleaning, conversion coating, and applying and baking finish. The exposed aluminum for storefront appears to be custom coating with no color chosen, is it the intent that all exposed aluminum will match this custom color?
A53. Yes, for storefronts and windows.
Q54. Drawing A‐401 Shows aluminum diamond plate wall covering. It seems there is no spec section or product information regarding this.
A54. Interior grade Aluminum wall covering is to be used. Basis‐of Design product “Diamond Life, MaxTile F1, Aluminum wall tile” and associated trim details at all corners and top and bottom of wainscot heights, applied in accordance with manufacturers standards.
Q55. Drawing S‐502 #5 shows an aluminum handrail welded to a steel beam. Aluminum and steel cannot be welded together.
A55. Hand rail to be galvanized steel
Q56. Drawing C‐502 #4 shows a steel post with aluminum rails. Again aluminum and steel cannot be welded together.
A56. Hand rail to be galvanized steel
Q57. Drawing S‐102 Column line A.75 shows HSS 5x5x3/4 in several locations. Square tubing of this wall thickness is not available. 5/8” thick is the thickest available in that size.
A57. These columns should be HSS5x5x3/8.
Q58. Drawing S‐102 Section 1/501 seems to be mislabeled.
A58. This section cut should be 1/S502.
Q59. Drawing C‐502 Detail 6 shows to use Stainless Steel Nosing’s. Spec section 055000 2.8A. Stair nosing’s are to be cast aluminum. Please specify a make and model and material you would like for the nosing’s. These can greatly vary in cost.
A59. The nosings should be stainless steel.
Q60. Regarding Window Treatments: A102 shows 20 sections for window E10, A201 shows 24 section, which is desired?
A60. A‐102 showing 20 sections is accurate. This allows detail 1/A322 mullion to align with new partition demising Fitness room 213 & Dining/Living/Day room 210
Q61. Regarding Window Treatments: How are the window treatments to be divided for window E10, specifically how to avoid the building columns? Shall each bay be treated separately?
A61. Window treatments shall be of equal lengths to maximum width possible per manufacturer standard, running entire window run. Where a column breaks a window run, the treatments shall fit tight to the wall/column surfaces, leaving minimum required working clearance as per manufacturer’s installation standards.
Q62. Regarding Window Treatments: A102, Room 205 – Window E9 is not sectioned like the window elevations, is this to be treated as a one track unit or will each bay receive its own vertical? Same question for the shades.
A62. Both window treatments are to run continuous of full window width. (Windows E4, E5 & E9 shall have 1 shade/1 treatment each. If window runs are too long for one continuous treatment, then it shall be broken up to 2 equal treatments, or 3 equal treatments, etc. Minimum # takes priority.)
Q63. The final project specifications and drawings were posted to FBO. What changes were made from the pre‐final, B2 plans and specifications?
A63. Modifications from the B2 to the B3 submission for the Fire, Crash/rescue Station project were completed in response to the Government review comments received 5/17/16. One additional plan sheet was added to the set, Sheet P502, Sanitary Vent and Riser Diagrams. Additional Specification sections included 074113.16 ‐ Standing Seam Metal Roof Panels, 236313 ‐ Air Cooled Refrigerant Condensers, and 283500 ‐ Refrigerant Detection and Alarm. Specification section 238126 ‐ Split System Air Conditioners was removed.
Q64. Please advise if widows E1, E4, E5 and E9 are to receive BOTH shades and verticals. Intent is unclear.
A64. As per Key note 10a, on drawing A‐114, Window E4, E5 and E9 receive both. E1 only receives blinds, not roller type sunshade.
Q65. A‐102 ‐‐‐ Rm 205 ‐‐‐‐ do not see that window Type E9 is sectioned off‐‐‐ is this correct? A) Are these to be treated as one track unit? Or each bay to receive its own vertical? B) ALSO if shades are desired for this window, same question?
A65. See response to Q62 above. Window type E9, shows mullion locations on A‐603. This sheet applies for all window/storefront mullions.
Q66. A‐102 ‐‐‐‐ has 20 sections for E10; A‐201 ‐‐‐‐ shows 24 sections. Which is right?
A66. Previously answered in question 60.
Q67. Shelving and clothes rods. Where do the rod and shelf apply?
A67. Shelving and clothes rods were previously designed to be in room 108. They are no longer included.
Q68. Due to the timing of the final specifications and plans, will the bid date be extended?
A68. The bid date will be extended to 28 July 2016 at 1:00 P.M.
Q69. In reference to drawings A‐602, A‐602 & A‐604, the storefront is specified as 451UT which is a double thermally broken system that is blast tested and is only available as center glazed as shown on details 7, 8, 9 on A‐604. However, page A‐603 Window Schedule calls for front glazed on all storefront. At the same time page A‐ 602 shows front set storefront door framing (details 4 and 5). The spec also asks for 451UT front glazed, which is not an available product. Possible solution: SF1, SF1A, SF2 and SF3 should be 451UT or similar brand center glazed storefront. All window types should actually be 451T VG storefront (which is front set) with operable 8225TL windows as drawn.
A69. All Storefront labeled with “SF” designation can be 451UT (or approved similar) center glazed. All windows can be 451T VG (front set) with the operable option to match desired 8225TL windows. All storefronts and windows must maintain ATFP requirements and thermal requirements listed in specifications See A94 for clarification on all window and storefront information.
Q70. In reference to drawings A‐604, A‐332, A‐313 & A‐314, the window specification calls for 8225TL operable project out windows. In RFI #1 the windows are said to all be 8225TL, some fixed and some operable which matches the details on A‐604. However page A‐332 detail 1 shows one of these same windows as front set storefront, not an 8225TL window, pages A‐313 and A‐314 show these windows as either front set storefront or curtainwall. To add to the confusion, window E10 is drawn connected to SF3 at the corner where they meet?
There isn’t a detail for this and I don’t have any idea how this would work other than by building a corner post in the building that the two framing types are butted up to on either side. Possible solution: Just to throw it out there, the 8225TL window can be build many ways. It can be an operable window installed into storefront, or it can be a window in and of itself. 451UT storefront is only available as center glazed. 451T VG (front/back set) is blast tested.
A70. Please see answer to Q69 above. In addition, the Basis of design products (Kawneer) offer typical corner detail solutions that should be followed. Since window E10 and Storefront SF3 are fixed systems, provided by same manufacturer, the corners shall be of one corner detail, with steel reinforced mullions as required, per manufacturer's standard requirements. See A94 for clarification on all window and storefront information.
Q71. Specification Section 283500 has been added to the revised specifications issued on 7/13/16 for refrigerant detection and alarms; however, the drawings do not show any of this system. Please provide corresponding drawings to show device quantities and locations for this system on the electrical drawings.
A71. A room level refrigerant monitoring system will not be installed for this project. Pressure sensors shall be installed to monitor the refrigerant pressure in the overall Variable Refrigerant Flow (VRF) system.
The following shall be performed:
Contractor shall install two (2) pressure sensors at each outdoor condensing unit to monitor the high pressure side and low pressure side of the refrigerant piping. The sensors shall provide a 4‐20 ma output signal designed to measure a range from 0 to 725 psi (based on condensing unit manufacturer’s operating pressures). If the pressure is not in the defined range (per the manufacturer’s installation manual), an alarm signal shall be sent to the Fire Alarm Control Panel and the Building Management System. In the event of an alarm, the sequence of operations for gas leak detection, described on the mechanical drawings (M‐504), shall be performed.
Q72. ABI #3 scope includes replacing floor material at Stairwell No. 1 second floor landing and Stairwell No. 2 first floor and second floor landing. There is no indication of any new flooring at the intermediate stair landing or stair treads and risers. Please confirm that intermediate landings, stair treads and risers are not scheduled for new floor finishes.
A72. Intermediate landings and stair treads, risers, are to remain. Not included in scope.
Q73. Drawing A‐603 Window Schedule lists the windows as being hollow metal (HM) framed. The details and specification indicate aluminum. Please confirm.
A73. Please follow details and specifications indicating Aluminum.
Q74. Drawing A‐113, Keynote 1 requires the installation of new yellow reflective warning lines prior to new clear coat slip resistant concrete sealer. The drawings do not indicate where the required warning lines are to be installed.
A74. Yellow warning lines are to be included at all truck aisle clearances within the egress paths indicated in the Basis‐of‐design document, Part 1, Section 1.2.5 Existing Floor Plans. Also, yellow lines located at all emergency eye wash stations, to match existing.
Q75. Drawing A‐114, Keynote 16 states that existing carpet tile to remain (Dining/Living/Day Room 210).
Replace damaged tiles or required additional tiles to match existing carpet. How is the contractor to quantify the amount of carpet tile to be replaced?
A75. The damaged/replaced tiles shall be quantified be in the areas of demolition adjacent to the new kitchen tiles below the island millwork on the dining and all other millwork locations within the room. A running length of millwork, and depth of new millwork, should cover approximate quantities.
Q76. Please give a location of the shelf and rod detail (6/A‐411) we cannot find where these are being called for.
A76. See A67 above, previously answered.
Q77. Both sections 096519 and 096813 are requiring the floor RH be at 75%. In our experience this cannot be achieved and would require moisture mitigation. Please clarify the intent.
A77. Intent is to follow ASTM F 2170.
Q78. In regards to Pre‐Award RFI Question 11, is it required that the contractor carry the cost for a temporary standpipe and hose on this project?
A78. No.
Q79. In regards to Pre‐Award RFI Question 12 above, is it required that the contractor carry a Pest Control Service on this project?
A79. Pest control in work areas during construction will be by the Contractor as needed.
Q80. In regards to Pre‐Award RFI Question 23 above, does the contractor need to carry the excess power company charge for relocation this pole or is an allowance called out for or is the Owner paying this cost? Has anyone contacted Emera to see what the charge is for relocating this pole?
A80. See response to Q23, Q46 and Q99.
Q81. Is testing of structural steel by owner or contractor?
A81. By owner. See S‐001 – Special Inspections – Note #1
Q82. Drawing A‐101, Keyed note #5 Steel Industrial Shelving. What make, model, material, and size of shelving is to be installed here?
A82. Basis‐of‐Design Product: Global Industries heavy Duty Industrial Shelving, Model #WG258180
Q83. Drawing A‐102, Rm 201, Specification 122116 states E10 has rough opening of 72’ 8” which is too long for one vertical blind, should they be separated as individual panels, please advise.
A83. Previously answered in A60, A61 & A62
Q84. Drawing A‐102, Rm 205, Specification 122116 states E10 has rough opening of 72’ 8” which is too long for one vertical blind, should they be separated as individual panels, please advise.
A84. Previously answered in A60, A61 & A62
Q85. In regards to drawing A‐603, Specification 122116 and 122413. Confirm if two window treatments are desired for E1, E4, E5 & E9, note both are light filtering.
A85. As per Key note 10a, on drawing A‐114, Window E4, E5 and E9 receive two window treatments. E1 only receives blinds, not roller type sunshade.
Q86. The insulated wall panel specification, 074213 makes general references to backer board and furring, but the specific details on the bid drawings show the siding being directly attached to the existing exterior wall studs. Please advise if backer board and/or furring is required to be installed over the existing studs and if required please also indicate if this has any impact on other details.
A86. Backer Board is not required. Furring attached to face of existing metal stud framing is also not required, however, intermediate attachments need to be installed in accordance with metal panels and manufacturers standards to allow new panel widths to be installed and attached according to elevations.
Q87. There is a specification section for weather barrier, 072500, however there are no weather barriers shown on the bid set of drawings. If required, please advise where the barrier is to be installed.
A87. There is no weather barrier. The insulated metal panels act as a barrier when full sealed in accordance to manufacturers standards.
Q88. Detail 2/A333 shows waterproofing and drainage material on the foundation wall, however, there are no other details showing this and there is no specification for foundation waterproofing and drainage.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .