W912HV-19-R-0008_ESR_502-19_SPEC_&_DWGS.pdf

PDF 33 MB Posted

Attached to
ESR 502-19 Replace R-22 HVAC Chillers, Various USMC Camps, Okinawa, Japan
Solicitation number
W912HV-19-R-0008
Issued by

About this file

Specifications and Concept Drawings Documents.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912HV-19-R-0008

US Army Corps of Engineers

Japan District

ESR 502-19 FY19 Replace R-22 HVAC Chillers

Various Locations, Okinawa, Japan

SPECIFICATIONS

RTA Submittal

16 MAY 2019

This page was intentionally left blank for duplex printing.

ESR 502-19 FY19 Replace HVAC Chillers 19MC0005 Various Locations, Okinawa, Japan

W912HV-19-R-0008 PROJECT TABLE OF CONTENTS Page 1

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 01 11 00-A 01 11 00-B 01 11 00-C 01 11 00.00 10 01 22 00.00 10 01 32 01.00 10 01 33 00 01 33 00-A 01 33 00-B 01 33 16 01 33 16-A 01 35 26 01 35 26-A 01 42 00 01 42 15 01 45 00.10 20 01 45 00.15 10 01 50 00 01 50 00-A 01 57 19 01 74 19 01 75 00.00 40 01 78 00 01 78 00-A 01 78 23

STATEMENT OF WORK

DESIGN CRITERIA

CONCEPT DRAWINGS

ACCEPTABLE ALTERNATIVE JAPANESE STANDARDS LIST

GENERAL CONTRACT REQUIREMENTS

PRICE AND PAYMENT PROCEDURES

PROJECT SCHEDULE

SUBMITTAL PROCEDURES

ENG FORM 4025-R

SUBMITTAL REGISTER

DESIGN AFTER AWARD

TRACKING COMMENTS IN DR CHECKS

GOVERNMENTAL SAFETY REQUIREMENTS

USACE ACCIDENT PREVENTION PLAN CHECKLIST

SOURCES FOR REFERENCE PUBLICATIONS

METRIC MEASUREMENTS

QUALITY CONTROL FOR MINOR CONSTRUCTION

RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

PROJECT SIGN

TEMPORARY ENVIRONMENTAL CONTROLS

CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

STARTING AND ADJUSTING

CLOSEOUT SUBMITTALS

DRAFT DD 1354

OPERATION AND MAINTENANCE DATA

ESR 502- 19 FY19 Repl ace R- 22 HVAC Chi l l er s 19MC0005 Var i ous Camps, Oki nawa

SECTI ON 01 11 00

STATEMENT OF WORK

PART 1 GENERAL

1. 1 General

The Cont r act or shal l r epl ace t he chi l l er syst ems at Camp Fost er Bui l di ngs 1004, 1005, 4136, 5634, 5674, 5832, and 5836; Camp Lest er Bui l di ngs 6038, 6040, and 6071; Camp Schwab Bui l di ngs 3128, 3330, 3418, 3423, and 3535;

Camp Cour t ney Bui l di ng 4233; and Mar i ne Cor ps Ai r St at i on ( MCAS) Fut enma Bui l di ngs 461 and 525; Camp Ki nser Bui l di ngs 110, 114C, 424, 520, 835, 864, 866, 1091, 1227, and 1307; and Camp Hansen Bui l di ngs 2134, 2340, 2375, 2382, 2407, 2418, 2519, 2530, 2618, 2622, 2665, 2667, 2818, 2820, 2821, 2892, and 2893 r esul t i ng i n compl et e and usabl e syst ems.

The i nt ent of t hi s sect i on i s t o speci f y t he mi ni mum desi gn and const r uct i on r equi r ement s f or qual i t y , f unct i on, mat er i al s, and t ypes of const r uct i on i n suf f i c i ent det ai l f or Cont r act compl et i on.

Desi gn anal ysi s, const r uct i on document dr awi ngs, and speci f i cat i ons shal l be pr epar ed t o compl y wi t h t hi s sect i on and Sect i on 01 33 16 DESI GN AFTER AWARD. No devi at i ons f r om t hese sect i ons shal l be al l owed unl ess pr i or appr oval i s obt ai ned f r om t he Cont r act i ng Of f i cer . Al l quest i ons or pr obl ems encount er ed by t he Cont r act or i n f ol l owi ng t he r equi r ement s i n t hi s sect i on shal l be pr ompt l y submi t t ed wi t h r ecommendat i ons t o t he Cont r act i ng Of f i cer f or r esol ut i on.

PART 2 PRODUCTS ( NOT USED)

PART 3 EXECUTI ON

3. 1 ATTACHMENTS

I nf or mat i on pr ovi ded i n t he at t achment s i s i nt ended t o pr ovi de desi gn r equi r ement s and i nf or mat i on.

3. 1. 1 01 11 00- A

Desi gn Cr i t er i a: Desi gn and const r uct i on f or t hi s pr oj ect shal l compl y wi t h At t achment 01 11 00- A. Secur e any necessar y r ef er ence at Cont r act or ' s own expense and r esour ces.

3. 1. 2 01 11 00- B

Concept Dr awi ngs: Pr ovi ded f or desi gn and coor di nat i on pur poses.

I nf or mat i on depi ct ed i n t he Concept Dr awi ngs ser ves as a gui de onl y.

Fur t her devel opment shal l r equi r e coor di nat i on wi t h t he usi ng agency and base per sonnel .

3. 1. 3 01 11 00- C

Li st i ng of " Accept abl e Al t er nat i ve Japanese St andar ds" whi ch ar e consi der ed accept abl e al t er nat i ves t o t he US st andar ds wi t hi n t he Cont r act speci f i cat i ons. Thi s l i s t i s pr ovi ded f or desi gn and coor di nat i on pur poses.

The Desi gner of Recor d shal l be r esponsi bl e f or i ncor por at i ng t he

W912HV-19-R-0008 SECTI ON 01 11 00 - Page 1

ESR 502- 19 FY19 Repl ace R- 22 HVAC Chi l l er s 19MC0005 Var i ous Camps, Oki nawa appl i cabl e st andar ds f r om t hi s l i s t i nt o each r el evant i ndi v i dual t echni cal sect i on speci f i cat i on.

3. 2 DESI GN COORDI NATI ON, SUBMI TTALS, AND OTHER REQUI REMENTS

Ref er t o Sect i on 01 33 16 DESI GN AFTER AWARD.

- - End of Sect i on - -

W912HV-19-R-0008 SECTI ON 01 11 00 - Page 2

01 11 00-A: Design Criteria (Statement of Work)

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW TOC 1-1

ESR 502-19 FY19 Replace R-22 HVAC Chillers 19MC0005

Various Locations, Okinawa, Japan Statement of Work

TABLE OF CONTENTS

Chapter 1 DESIGN AND CONSTRUCTION OBJECTIVES ............................... 1-1

1-1 Scope of Work ......................................................1-1

1-2 Applicable Criteria ................................................1-9

1-3 Design/Build Conditions ............................................. 1-9

1-4 Design Freedom .....................................................1-9

1-5 As-Built Drawings with Proposed Changes ............................1-9

1-6 Construction Phasing Plan ..........................................1-9

Chapter 2 FUNCTIONAL AND AREA REQUIREMENTS .................................2-1

2-1 Not Used ...........................................................2-1

Chapter 3 SITE PLANNING AND DESIGN ......................................... 3-1

3-1 Site Verification ..................................................3-1

3-2 Existing Conditions ................................................3-1

3-3 Excavation Permits .................................................3-1

3-4 Construction Drawings ..............................................3-1

3-5 Temporary Construction Fence........................................ 3-1

Chapter 4 SITE ENGINEERING AND DESIGN ......................................4-1

4-1 General–Reference Design Requirements, Standards and Criteria .......4-1

4-2 Applicable Criteria ................................................4-1

4-3 Disposal ...........................................................4-1

4-4 Demolition .........................................................4-1

4-5 Existing Utilities .................................................4-1

4-6 Detailed Specifications ............................................4-2

Chapter 5 ARCHITECTURAL DESIGN ............................................. 5-1

5-1 Not Used ...........................................................5-1

Chapter 6 STRUCTURAL DESIGN ................................................ 6-1

6-1 Not Used ...........................................................6-1

Chapter 7 STRUCTURAL WORK ..................................................7-1

7-1 Not Used ...........................................................7-1

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW TOC 1-2

Chapter 8 MECHANICAL WORK ..................................................8-1

8-1 Applicable Codes and Standards .....................................8-1

8-2 Design Calculations ................................................8-1

8-3 Materials and Equipment ............................................8-1

8-4 Testing, Balancing, and Adjusting ...................................8-2

8-5 Other requirements, Considerations and Background ...................8-2

8-6 Detailed Specifications ............................................8-3

Chapter 9 ELECTRICAL WORK ..................................................9-1

9-1 Design Goals and objectives ........................................9-1

9-2 Applicable Codes and Standards .....................................9-2

9-3 Electrical Distribution system .....................................9-4

9-4 Design Calculations ................................................9-5

9-5 Materials and Equipment ............................................9-5

9-6 Detailed Specifications ........................................... 9-6

Chapter 10 HEATING, VENTALIZATING AND AIR CONDITIONING ....................10-1

10-1 Not Used ..........................................................10-1

Chapter 11 ENERGY CONSERVATION EQUIPMENT ..................................11-1

11-1 Not Used ..........................................................11-1

Chapter 12 FIRE PROTECTION SYSTEM .........................................12-1

12-1 Not Used ..........................................................12-1

Chapter 13 SUSTAINABLE DESIGN ............................................. 13-1

13-1 Not Used ..........................................................13-1

Chapter 14 INTERIOR DESIGN ................................................14-1

14-1 Not Used ..........................................................14-1

Chapter 15 SPRINKLER SYSTEM ...............................................15-1

15-1 Not Used ..........................................................15-1

Chapter 16 ENVIRONMENTAL REQUIREMENTS .....................................16-1

16-1 Not Used ..........................................................16-1

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW TOC 1-3

(Page Intentionally Left Blank)

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-1

Chapter 1

DESIGN AND CONSTRUCTION OBJECTIVES

1-1 Scope of Work

Design and construction shall comply with the specifications and requirements contained in this Request for Proposal (RFP). The design and technical criteria contained and cited in this RFP establishes minimum standards for design and construction quality.

1-1.1 Project Site

Projects are located throughout Okinawa, Japan at 54 locations; Camp

Foster Buildings 1004, 1005, 4136, 5634, 5674, 5832 and 5836; Camp

Lester Buildings 6038, 6040, and 6071; Camp Schwab Buildings 3128, 3330, 3418, 3423 and 3535; Camp Courtney Building 4233; Marine Corps

Air Station (MCAS) Futenma Buildings 461 and 525; Camp Kinser Buildings

110, 114C, 424, 520, 835, 864, 866, 1091, 1227 and 1307; and Camp

Hansen Buildings 2134, 2340, 2375, 2382, 2407, 2418, 2519, 2530, 2618, 2622, 2665, 2667, 2818, 2820, 2821, 2892 and 2893.

1-1.2 Scope of Work Description

General Information: This work is to replace the chiller systems as described in the following paragraphs. The Contractor is responsible for installing a chiller system that constitutes a complete and usable system. A complete and usable system includes but is not limited to what is covered in statement of work. Temporary mobile chiller systems will be required to cover outage periods that take place between 1

April and 30 November. Recommissioning is a requirement for all chiller locations per the commissioning specification Division 01 91

00.15. No Direct Digital Control (DDC) connection to a building automation system or installation energy management and control system is required for any location.

The current chillers use R-22 refrigerant and the intent of this Scope of Work (SOW) is to have the chillers replaced with chillers that use

R-410A refrigerant.

1-1.2.1 Base Schedule

1) Mechanical Work

a. Remove and demolish the existing chillers shown below in Base schedule Tables 1 and 2 to include the chilled water supply and return piping from the chiller up to the isolation valves (to remain), piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge, supply and return water temperature sensors, control system, stainless steel jacket and insulation.

b. Install new packaged air cooled chillers that correspond with the existing Air Handling Units (AHUs) capacity for the buildings shown below in Base schedule Tables 1 and

2 to include the chilled water supply and return piping up to the isolation valves (to remain), piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge, supply and return water

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-2 temperature sensors, control system, stainless steel jacket and insulation.

c. Refer to Chapter 8: Mechanical Work for details.

2) Electrical Work: Apply 200V class voltage system (208V/230V) to the buildings shown below in Base Tables 1 and 2.

a. Remove existing electrical power wirings, conduits, associated fittings and accessories.

b. Remove existing control wirings. Coordinate with mechanical work.

c. Remove existing step-up transformers with an enclosure cabinet and circuit breaker. Dispose of materials, equipment and devices.

d. Provide new heavy duty type safety disconnect switch or an enclosed circuit breaker in accordance with NEC 440.21.

Locate in the chiller enclosure station or within sight of the HVAC equipment in accordance with NEC 440.14.

e. Provide new electrical power wirings, conduits, pull-boxes, associated fittings and accessories. Upgrade the entire electrical distribution system for a new chiller system and air handling unit system.

f. Provide new conduit and wiring for system controls.

Coordinate with mechanical work.

g. Provide new Weatherproof (WP) plug-in use type, extra duty 20A, 120V ground fault circuit interrupter (GFCI) receptacle within 25 feet of the chiller equipment (NEC

210.63 & NEC 406.9). Provide new GFCI circuit breaker.

Modify existing panelboard or provide new enclosure, as required.

h. Obtain and analyze transformer peak load data for each location with MCB Butler, FMB (Facilities Maintenance

Branch), and Electric Distribution Shop W/C 3052, Bldg 359.

Provide power system analysis documentation to include the first upstream device on the existing portion of the system

(Japan District Design Guide 2019, 13.7) in design analysis.

(Transformer replacements/upgrades are not in the scope of work).

i. Provide grounding system for all new chillers and associated equipment and devices.

j. Replace all existing power cables of the chiller system located between the circuit breaker in the service transformer station or Main Distribution Panel and the chiller equipment.

3) General Work

a. Fill any unused holes through the foundation or pads.

This fill shall provide for structural soundness.

b. For the buildings without a temporary backup chiller, the contractor is required to maintain the building interior temperature at or below 78F during construction.

c. Temporary mobile chiller systems will be required to cover outage periods that are show in the Temp Chiller

Quantity column in tables Base Table 1 and Base Table 2.

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-3

Foster

Buildings

Chiller

Quantity

Chiller

Tonnage each unit

Temp Chiller

Quantity

1004 2 100 2

1005 1 34 0

4136 1 34 1

5626 1 20 0

5634 1 54 2

5634 1 16 0

5674 2 38 0

5832 1 15 0

5836 1 100 0

Base Table 1

Lester

Buildings

Chiller

Quantity

Chiller

6038 1 34 1

6040 1 80 1

6071 1 60 1

Base Table 2

1-1.2.2 Option 1

1) Mechanical Work

a. Remove and demolition of the existing chillers shown below in schedule Option 1 Tables 1, 2 and 3 to include the chilled water supply and return piping from the chiller up to the isolation valves (to remain), piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge supply and return water temperature sensors, control system, stainless steel jacket and insulation.

b. Install new packaged air cooled chillers that correspond with the existing Air Handling Units (AHUs) capacity for the buildings shown below in schedule Option 1 Tables 1, 2 and 3 to include the chilled water supply and return piping from the chiller up to the isolation valves (to remain), piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge, supply and return water temperature sensors, control system, stainless steel jacket and insulation.

c. Refer to Chapter 8 Mechanical Work for details.

2) Electrical Work: Apply 200V class voltage system (208V/230V) to the buildings shown below in Option 1 Tables 1, 2 and 3

a. Remove existing electrical power wirings, conduits, associated fittings and accessories.

b. Remove existing control wirings. Coordinate with mechanical work.

c. Remove existing step-up transformers with an enclosure cabinet and circuit breaker. Dispose of materials, equipment and devices.

d. Provide new heavy duty type safety disconnect switch or an

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-4 enclosed circuit breaker in accordance with NEC 440.21. Locate in the chiller enclosure station or within sight of the HVAC equipment in accordance with NEC 440.14.

e. Provide new electrical power wirings, conduits, pull-boxes, associated fittings and accessories. Upgrade the entire electrical distribution system for a new chiller system and air handling unit system.

f. Provide new conduit and wiring for system controls. Coordinate with mechanical work.

g. Provide new Weatherproof (WP) plug-in use type, extra duty

20A, 120V ground fault circuit interrupter (GFCI) receptacle within 25 feet of the chiller equipment (NEC 210.63 & NEC

406.9). Provide new GFCI circuit breaker. Modify existing panelboard or provide new enclosure, as required.

h. Obtain and analyze transformer peak load data for each location with MCB Butler, FMB (Facilities Maintenance Branch), and

Electric Distribution Shop W/C 3052, Bldg 359. Provide power system analysis documentation to include the first upstream device on the existing portion of the system (Japan District

Design Guide 2019, 13.7) in design analysis. (Transformer replacements/upgrades are not in the scope of work).

i. Provide grounding system for all new chillers and associated equipment and devices.

j. Replace all existing power cables of the chiller system located between the circuit breaker in the service transformer station or Main Distribution Panel and the chiller equipment.

a. Fill any unused holes through the foundation or pads. This fill shall provide for structural soundness.

b. For the buildings without a temporary backup chiller, the contractor is required to maintain the building interior temperature at or below 78F during construction.

c. Temporary mobile chiller systems will be required to cover outage periods that are show in the Temp Chiller Quantity column in tables Option 1 Table 1, Option 1 Table 2 and

Option 1 Table 3.

Schwab

Chiller

Quantity

Chiller

3128 1 16 0

3330 1 100 1

3418 2 18 0

3423 1 15 1

3535 1 50 1

Option 1 Table 1

Courtney

Chiller

Quantity

Chiller

4233 1 50 1

Option 1 Table 2

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-5

Futenma

Chiller

Quantity

Chiller

461 1 18 0

525 1 40 0

Option 1 Table 3

1-1.2.3 Option 2

1) Mechanical Work

a. Remove and demolish the existing chillers shown below in schedule Option 2 Table 1 to include the chilled water supply and return piping from the chiller up to the isolation valves

(to remain), piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge, supply and return water temperature sensors, control system, stainless steel jacket and insulation.

b. Install new packaged air cooled chillers that correspond with the existing Air Handling Units (AHUs) capacity for the buildings shown below in Option 2 Table 1 to include the chilled water supply and return piping from the chiller up to the isolation valve, piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge, supply and return water temperature sensors, control system, stainless steel jacket and insulation.

the buildings shown below in Bid Option 2 Tables 1

a. Remove existing electrical power wirings, conduits, associated fittings and accessories.

b. Remove existing control wirings. Coordinate with mechanical work.

c. Remove existing step-up transformers with an enclosure cabinet and circuit breaker. Dispose of materials, equipment and devices.

d. Provide new heavy duty type safety disconnect switch or an enclosed circuit breaker in accordance with NEC 440.21. Locate in the chiller enclosure station or within sight of the HVAC equipment in accordance with NEC 440.14.

e. Provide new electrical power wirings, conduits, pull-boxes, associated fittings and accessories. Upgrade the entire electrical distribution system for a new chiller system and air handling unit system.

f. Provide new conduit and wiring for system controls. Coordinate with mechanical work.

g. Provide new Weatherproof (WP) plug-in use type, extra duty 20A, 120V ground fault circuit interrupter (GFCI) receptacle within 25 feet of the chiller equipment (NEC 210.63 & NEC

406.9). Provide new GFCI circuit breaker. Modify existing panelboard or provide new enclosure, as required.

h. Obtain and analyze transformer peak load data for each location with MCB Butler, FMB (Facilities Maintenance Branch), and

Electric Distribution Shop W/C 3052, Bldg 359. Provide power system analysis documentation to include the first upstream device on the existing portion of the system (Japan District

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-6

Design Guide 2019, 13.7) in design analysis. (Transformer replacements/upgrades are not in the scope of work).

i. Provide grounding system for all new chillers and associated equipment and devices.

j. Replace all existing power cables of the chiller system fill shall provide for structural soundness.

b. For the buildings without a temporary backup chiller, the contractor is required to maintain the building interior temperature at or below 78F during construction.

c. Temporary mobile chiller systems will be required to cover outage periods that are show in the Temp Chiller

Quantity column in Option 2 Table 1.

Kinser

Chiller

Quantity

Chiller

110 2 55 0

114C 1 35 0

424 1 10 0

520 1 20 0

835 1 35 1

864 1 30 1

866 1 35 1

1091 1 35 1

1227 2 55 2

1307 1 70 1

Option 2 Table 1

1-1.2.4 Option 3

1) Mechanical Work

a. Remove and demolition of the existing chillers shown below in schedule Option 1 Tables 1, 2 and 3 to include the chilled water supply and return piping from the chiller up to the isolation valves (to remain), piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge supply and return water temperature sensors, control system, stainless steel jacket and insulation.

b. Install new packaged air cooled chillers that correspond with the existing Air Handling Units (AHUs) capacity for the buildings shown below in Base schedule Tables 1, 2 and

3 to include the chilled water supply and return piping from the chiller up to the isolation valves (to remain), piping brackets, chilled water pressure differential transducer, pressure gauge, temperature gauge, supply and return water temperature sensors, control system, stainless steel jacket and insulation.

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-7 the buildings shown below in Option 1 Tables 1, 2 and 3

a. Remove existing electrical power wirings, conduits, associated fittings and accessories.

b. Remove existing control wirings. Coordinate with mechanical work.

c. Remove existing step-up transformers with an enclosure cabinet and circuit breaker. Dispose of materials, equipment and devices.

d. Provide new heavy duty type safety disconnect switch or an enclosed circuit breaker in accordance with NEC 440.21. Locate in the chiller enclosure station or within sight of the HVAC equipment in accordance with NEC 440.14.

e. Provide new electrical power wirings, conduits, pull-boxes, associated fittings and accessories. Upgrade the entire electrical distribution system for a new chiller system and air handling unit system.

f. Provide new conduit and wiring for system controls. Coordinate with mechanical work.

g. Provide new Weatherproof (WP) plug-in use type, extra duty 20A, 120V ground fault circuit interrupter (GFCI) receptacle within 25 feet of the chiller equipment (NEC 210.63 & NEC

406.9). Provide new GFCI circuit breaker. Modify existing panelboard or provide new enclosure, as required.

h. Obtain and analyze transformer peak load data for each location with MCB Butler, FMB (Facilities Maintenance Branch), and

Electric Distribution Shop W/C 3052, Bldg 359. Provide power system analysis documentation to include the first upstream device on the existing portion of the system (Japan District

Design Guide 2019, 13.7) in design analysis. (Transformer replacements/upgrades are not in the scope of work).

i. Provide grounding system for all new chillers and associated equipment and devices.

j. Replace all existing power cables of the chiller system fill shall provide for structural soundness.

b. For the buildings without a temporary backup chiller, the contractor is required to maintain the building interior temperature at or below 78F during construction.

c. Temporary mobile chiller systems will be required to cover outage periods that are show in the Temp Chiller Quantity column in table Option 3 Table 1.

Hansen

Chiller

Quantity

Chiller

2134 1 60 0

2340 2 50 2

2375 1 55 0

2382 1 55 0

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-8

2407 1 40 1

2418 1 35 0

2519 1 35 1

2530 1 40 1

2618 1 40 1

2622 2 50 2

2665 2 55 2

2667 2 50 2

2818 1 55 0

2820 2 55 2

2821 1 50 0

2892 1 10 0

2893 1 35 0

Option 3 Table 1

1-1.3 Demolition Considerations and Requirements

Contractor shall survey the site to determine the extent of the work and which items are to remain in place. The Contractor shall take the necessary precautions to avoid damage to existing utilities and structures remaining in place, to be reused, or remaining the property of the government; any damaged items shall be repaired or replaced as approved by the Contracting Officer. Where removal of existing utilities and pavement is involved, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities Contactor shall provide traffic control during work times when trenches are exposed and construction is ongoing.

a. Patching: When removals leave damaged surfaces exposed in the finished work, patch and repair these damaged surfaces to match adjacent finished surfaces. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish.

b. Unforeseen Hazard: Notify the Contracting Officer of any unforeseen hazard or unforeseen site condition during work.

1-1.4 Environmental Consideration and Mitigation Requirements

Hazardous materials are assumed as present and as part of this contract, including without limitations, asbestos in all wire and pipe insulation and lead based paint in all layers of paint, including under top coat. The Contractor is required to test for the presence of asbestos and lead paint on any suspected hazardous materials being disturbed and notify the Contracting Officer immediately if found. The asbestos and lead containing materials shall be removed and disposed of in accordance with the Japan Environmental Governing Standards

(JEGS) and base environmental office. Disposal shall be at the designated disposal site off base.

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-9

1-2 Applicable Criteria

Applicable design and construction criteria references are listed in the RFP sections and Attachments of the Statement of Work. Criteria shall be taken from the most current references as of the RFP issue date. Referenced codes and standards are minimum acceptable criteria.

Administrative, contractual, and procedural features of the contract shall be as described in other sections of the RFP.

1-3 Design/Build Conditions

This requirement shall be awarded as Design/Build (DB). Design/Build

Contractor entity shall bear full responsibility for development of the final facilities Architectural/Engineering (AE) designs and construction of complete and usable facility. The DB Contractor’s AE shall be “the Architect/Engineering of Record” and as such, shall bear full responsibility for design and construction Quality Control.

Construction shall be authorized when the Contracting Officer considers that design is sufficient to permit the construction start. The DB

Contractor or their AE is fully responsible for coordination as required with the installation, contracting agency and the end user for both design and construction of the projects.

1-4 Design Freedom

Requirements stated in this RFP are minimums. Innovative, creative, or cost-saving proposals, which meet or exceed these requirements are encouraged and will be considered more favorably. Designs may incorporate factory fabricated components or modules. Government shall consider substitute materials for products which currently do not note

JIS equivalents in this RFP, if the contractor can prove it is an equivalent or superior product. The Site and Floor plans are established and approved as shown on the As-Built design drawings.

Minor deviations to the layouts may be required to accommodate various engineering, equipment manufacturer’s detailed requirements and space needs and other necessary or specified equipment. Any deviation to the layout shall be subject to approval by the Government. Design quality is achieved through the optimization of interior planning, sustainability, selection of building systems for low-cost maintenance and operation, and an overall balance of aesthetics and functionality.

1-5 As-Built Drawings with Proposed Changes

Existing As-Built Drawings are available on DVD. Offeror is responsible for verifying all existing conditions and the government is not responsible for the accuracy of the drawings.

1-6 Construction Phasing Plan

Construction phasing is not required. See section 01 33 16, Design

After Award, for Sequence of Design and Construction.

End of Chapter 1

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 1-10

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 2-1

Chapter 2

FUNCTIONAL AND AREA REQUIREMENTS

2-1 Not Used

End of Chapter 2

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 2-2

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 3-1

Chapter 3

SITE PLANNING AND DESIGN

3-1 Site Verification

For projects requiring exterior site work, such as the removal of chiller systems, the Contractor shall perform site survey and a detailed site analysis to verify the site for design development and construction of this project.

3-2 Existing Conditions

The Project sites are a nearly flat terrain primarily covered with sod. Contractor shall repair site to existing conditions after completion of the work

3-2.1 Existing Utilities

The locations of existing utilities shown on the as built drawings are approximate only. Excavation is not expected to be needed but if excavation is needed the Contractor shall scan the construction site with electromagnetic or sonic equipment and mark the surface of the ground where existing underground utilities are discovered.

Immediately contact the Contracting Officer if actual conditions vary from the drawings.

3-3 Excavation Permits

Excavation is not expected to be needed but if excavation is needed excavation permits shall be obtained from the Government Agency 45 days prior to any excavation work.

3-4 Construction Drawings

Develop site layout, utility plan, etc. and create the details necessary to provide a complete design. Construction drawings shall include but are not limited to Cover Sheet, Demolition Plan, Site Plan and Details.

3-5 Temporary Construction Fence

As soon as practicable, after the date established for commencement of work, the Contractor shall furnish and erect temporary project safety fencing approved by the contracting officer at the work site. The safety fencing shall be maintained by the Contractor during the life of the contract, and upon completion and acceptance of the work, shall become the property of the Contractor and shall be removed the work site.

End of Chapter 3

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 3-4

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 4-1

Chapter 4

SITE ENGINEERING AND DESIGN

4-1 General – Reference Design Requirements, Standards and Criteria

The design objective for site engineering is to provide efficient and functional infrastructure site systems adhering to existing conditions and minimizing impact to the site for this project. The Earthwork, Pavement, Storm Drainage, and Sodding as part of the site engineering in support of this project to provide a new facility that shall be designed and installed using the references listed below and all pertinent references in Chapter

1. (Note: Where a conflict between requirements and/or standards occurs, the more stringent shall apply.)

4-2 Applicable Criteria

Applicable design and construction criteria references are listed below, but are not limited to the criteria listed. Criteria shall be taken from the most current references as of the RFP issue date. Referenced codes and standards are minimum acceptable criteria.

a. UFC 3-201-02, Landscape Architecture

b. Japan Environmental Governing Standards (JEGS)

c. Unified Facilities Guide Specifications (UFGS)

d. ASTM International (ASTM)

e. National Fire Protection Association (NFPA) National Fire Code

4-3 Disposal

Materials not owned by the Government and not used in construction shall be disposed of off government property. The Contractor shall obtain approval of the disposal site from the Contracting Officer and submit haul tickets for material disposed of off of Government property. Permits for the disposal of materials shall be the responsibility of the Contractor.

4-4 Demolition

Materials not owned by the Government and not used in construction shall be disposed of off government property. The Contractor shall obtain the approval of the disposal site from the Contracting Officer and submit haul tickets for material disposed of off Government property.

4-5 Existing Utilities

Utilities within the project limits shall be adjusted, relocated or modified as required to remain functional. The Contractor shall coordinate all utility adjustment work with the appropriate utility agencies/departments. All existing paved areas, drainage and utility systems at the interface with the demolition shall be properly coordinated and new construction provided for the continued functionality, operation and maintenance of adjoining and remaining facilities and systems. All existing utility structure and related appurtenances, which will not be utilized in the project shall be removed and disposed. Abandonment in-place shall not be permitted unless approved by the Contracting Officer.

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 4-2

4-6 Detailed Specifications

During the design stage, the contractor shall submit the appropriate UFGS specifications to specify the materials, installation procedures, and testing requirements for all applicable systems or design elements.

4-6.1 UFGS 02 41 00 Demolition

End of Chapter 4

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 4-3

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 5-1

Chapter 5

ARCHITECTURAL DESIGN

5-1 Not Used

End of Chapter 5

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 5-2

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 6-1

Chapter 6

STRUCTURAL DESIGN

6-1 Not Used

End of Chapter 6

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 6-2

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 7-1

Chapter 7

STRUCTURAL WORK

7-1 Not Used

End of Chapter 7

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 7-2

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 8-1

Chapter 8

MECHANICAL WORK

8-1 Applicable Codes and Standards

Mechanical design criteria and guidance are contained in the following documents. Latest editions for the RFP shall apply applicable codes and standards include but are not limited to:

8-1.1 Government Standards

a. Unified Facilities Criteria:

UFC-3-420-01 Plumbing Systems

UFC 3-410-01 Heating, Ventilating and Air

Conditioning

UFC 3-440-05N Tropical Engineering

8-1.2 Industry Standards and Codes

a. National Fire Protection Association:

NFPA 70 National Electrical Code

NFPA 101 Life Safety Code

b. American Society for Testing and Materials (ASTM)

c. American Society of Mechanical Engineers (ASME)

8-1.3 Japanese Industrial Standard (JIS):

JIS G 3452 Carbon Steel Pipes for Ordinary

JIS G 3454 Carbon Steel Pipes for Pressure Service

JIS B 2031 Gray Cast Iron Valves

JIS G 3302 Hot-dip-zinc coated steel sheet and strip

JIS G 5525 Cast Iron Drainage Pipe and Fittings

JIS K 6739 Unplasticized Poly (PVC-U) Pipe and Fittings for Drain

8-2 Design Calculations

In addition to Section 01 33 16, DESIGN AFTER AWARD, the Offeror shall provide the design to include, as a minimum, the calculations of the following.

8-2.1 Chiller

Size the chillers to the buildings existing AHU’s capacities as described in chapter 1. The chillers must meet or exceed the minimum efficiency standards of ASHRAE 90.1 2016. The chiller shall have a scroll or screw type compressor. The chiller shall not have compressors with magnetic bearings. The chillers shall use R-410A refrigerant type.

R-22 refrigerant shall not be used. Replacement chillers with a capacity of 35 tons or greater shall have 2 independent refrigerant circuits and

4 or more capacity steps. Chillers with a capacity of less than 35 tons shall have 2 or more capacity steps. The condenser coil and fins shall be copper or aluminum and be coated with a uniform epoxy electrodeposition phenolic vinyl coat that meets the standards stated in

UFGS-23 64 10.

8-3 Materials and Equipment

All materials and equipment shall be the standard catalogued products of manufacturers regularly engaged in the production of such equipment and material, and shall be the manufacturer’s latest design. All equipment and material shall conform to the requirements of American National

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 8-2

Standards Institute (ANSI), American Society of Testing and Materials

(ASTM), National Fire Protection Association (NFPA), Japanese Industrial

Standards (JIS) or other national trade association as applicable. Where standards exist, materials and equipment shall bear the label and be listed by Underwriters Laboratories, Inc. (UL) or other recognized testing organization.

8-3.1 Chilled Water Supply and Return Piping

Size the chilled water supply and return piping to the current piping diameters and wall thicknesses. The intent is to use much of the current piping only replacing up to the isolation valve. The piping material shall match the current material and shall mate with the existing isolation valve.

8-3.2 Insulation

Insulation and stainless jacket shall be installed such that parts requiring periodic inspection, operation maintenance and repair are readily accessible (i.e. test valve port, temperature sensor connection and etc.).

8-3.3 Pressure Gauges and Sensors

Pressure gauges shall conform to ASME B40.100. The housing and trim shall be corrosion resistant stainless steel. Dial range shall be in Kpa and psi and shall cover the full operating range of the chilled water pumps.

8-3.4 Temperature Gauges and Sensors

The temperature gauges shall be dial type and fluid filled (mercury is not acceptable) with a nominal scale diameter of 127 mm (5 inches). The gauges shall be a hermetic stainless steel case with molded glass cover, stainless steel stem and bulb. The gauges shall cover the full operating range of the chillers.

8-3.5 Concrete Pad and Equipment Area

The chillers and all supporting equipment shall meet all life safety and

NFPA requirements within the equipment area. The equipment shall fit within the equipment area and on the existing pad. If deconstruction of any of the existing containment area walls are necessary the contractor is required to construct a new containment area that fully contains the chiller and supporting equipment.

8-3.6 Chiller Controls

The controls shall conform to UFGS 23 64 10 water chillers, Vapor

Compression Type. The chillers shall be complete with a factory based microprocessor based operating and control system, digital display, on-auto-off switch, power wiring and control wiring. Controls shall provide operating controls, monitoring capabilities, programmable set points, safety controls and BAS interfaces.

8-4 Testing, Adjusting, and Balancing (TAB)

Whole building TAB is not required for this project. The chillers are being replaced with chillers of similar capacities. The flow and temperature shall be matched to the chillers being replaced for each building location to ensure the systems work as designed.

8-5 Other requirements, Considerations and Background

Contractor shall provide 8 hours of training to (12) Government maintenance personnel on the programming, operation and maintenance of the new chiller systems.

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 8-3

Training shall include trouble shooting and periodic preventive maintenance required for the new equipment. Recommended spare parts list needed for maintenance as recommended by the manufacturer shall also be provided by the Contractor. Training shall be conducted by the manufacturer’s authorized representative. Training shall be done with the aid of video in English and Japanese.

8-6 Detailed Specifications

During the design stage, submit UFGS specifications to specify the quality, characteristics, installation procedures and testing requirements for all applicable sections. Some of the following specification sections may apply specification section include but not limited to:

a. UFGS 22 00 00 PLUMBING, GENERAL PURPOSE

b. UFGS 23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION AIR

EXHAUST SYSTEM c. UFGS 23 03 00 00

BASIC MECHANICAL MATERIALS AND METHODS

d. UFGS 23 05 48.00

VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING

AND PIPONG AND PIPING AND PIPING AND EQUIPMENT

e. UFGS 23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

f. UFGS 23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT

g. UFGS 23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE

h. UFGS 23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER

PIPIING SYSTEMS

End of Chapter 8

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 8-4

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 9-1

Chapter 9

ELECTRICAL WORK

9-1 Design Goals and Objectives:

The main objective of each project is to provide a new replacement HVAC systems. Modify the existing electrical system to allow the installation of new chillers and air handling units and associated electrical system auxiliaries. New electrical distribution system for HVAC systems shall also be designed to protect from corrosive environments and typhoons.

This will provide a reliable electrical power system with longer service life. Each project shall maximize the design quality and optimize operational functions and system reliability.

The work includes, but is not limited to installation of new enclosure cabinets, circuit breakers, disconnect switches, GFCI receptacles and

GFCI circuit breakers, conduits, wirings, fittings, and associated accessories and installation of new control systems. Each HVAC equipment shall have dedicated disconnect switches or circuit breakers to ensure loads are separated.

The electrical distribution system shall be designed in accordance with the applicable standards contained in the design criteria listed in

Section 9-2. Where the requirements of the standards and the requirements defined herein disagree, the more stringent ones shall apply. JIS and JCS standards included in Section 9-2 may be used in lieu of the applicable standards referred to in this section and in the UFGS guide specifications.

9-1.1 Requirements, Considerations and Background

a. Contractor shall provide 8 hours of training to (12) Government maintenance personnel on the programming, operation and maintenance of the new chiller system. Training shall include trouble shooting and periodic preventive maintenance required for the new equipment. Spare parts list needed for maintenance as recommended by the manufacturer shall also be provided by the Contractor. Training shall be conducted by the manufacturer’s authorized representative. Training may use video both in English and

Japanese.

Scheduled electrical outages shall be kept to a minimum, outages exceeding

8 hours shall require a temporary emergency generator to maintain power to the facility. Contractor shall do all work that will not require power outage initially. Power outages shall be carefully coordinated and scheduled to accommodate the user’s needs. Contractor shall provide all temporary power supplies and connections for temporary chillers.

b. Before installing any wires or conduits, the Contractor shall obtain the exact equipment requirements and shall install wires, conduits, circuit breakers (or disconnect switches), and other items of the correct size for equipment actually installed.

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 9-2

c. Electrical system shall include all necessary devices, accessories and miscellaneous items required for a complete operating system even though each item or process is not specifically mentioned or described.

Electrical system shall be complete and ready for operation.

d. New electrical power distribution system shall be coordinated with the manufacturer recommendations for mechanical equipment. Overcurrent protection size and circuit ampacity shall be per equipment manufacturer requirements.

e. Metallic materials shall be protected against corrosion. All enclosures, cabinets, and boxes exposed to the weather shall be NEMA 4X, Type 316 stainless steel.

f. All items required to be removed shall be removed. No items including buried conduits and pipes shall be abandoned.

g. Contractor is required to conduct detailed site investigation and perform measurements of the existing electrical system to adequately assess site conditions.

9-2 APPLICABLE CODES AND STANDARDS:

Electrical design criteria and guidance are contained in the following documents. Editions that are current at the date of issue of the RFP shall apply.

9-2.1 Government Standards:

a. Unified Facility Guide Specifications (UFGS):

b. Unified Facilities Criteria:

UFC 3-400-05N Tropical Engineering

UFC 3-501-01 Electrical Engineering

UFC 3-520-01 Interior Electrical Systems

UFC 3-550-01 Exterior Electrical Power Distribution

UFC 3-560-01 Electrical Safety, O&M

9-2.2 Industry Standards and Codes:

a. National Fire Protection Association:

NFPA 70 National Electrical Code

NFPA 70E Standard for Electrical Safety in Workplace

NFPA 101 Life Safety Code

b. Institute of Electrical & Electronics Engineers:

IEEE C2 National Electrical Safety Code

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 9-3

9-2.3 Japanese Cable Makers’ Association Standard (JCS):

JCS 1226 Annealed Copper Strand Conductors

JCS 3416 600V Flame Retardant Polyethylene Insulated Wires, EM-IE

JCS 4418 600V Flame Retardant Polyethylene Sheathed Cables, EM-CE

9-2.4 Japanese Industrial Standards (JIS):

JIS C 2336 Pressure-Sensitive Adhesive Polyvinyl Chloride Tapes for

Electrical Purposes

JIS C 2804 Compression Terminals

JIS C 2805 Crimp-Type Terminal Lugs for Copper Conductors

JIS C 2806 Non-Insulated Crimp-Type Sleeves for Copper Conductors

JIS C 2807 Insulated Closed-End Connectors

JIS C 3102 Annealed Copper Wires for Electrical Purposes

JIS C 3105 Hard-Drawn Copper Stranded Conductors

JIS C 3362 600 V Cross-linked polyethylene insulated cables

JIS C 3605 600V Polyethylene insulated cables

JIS C 3612 600V Polyvinyl chloride insulated and sheathed cables

JIS C 8305 Rigid Steel Conduits

JIS C 8309 Flexible Metal Conduits

JIS C 8330 Fittings for Rigid Metal Conduits

JIS C 8350 Fittings for Flexible Metal Conduits

JIS C 8340 Boxes and Box Covers for Rigid Metal Conduits

JIS C 8430 Unplasticized Polyvinyl Chloride (UPVC) Conduits

JIS C 8432 Fittings of Unplasticized Polyvinyl Chloride (UPVC) Conduits

9-3 ELECTRICAL DISTRIBUTION SYSTEM

9-3.1 General: The exterior electrical distribution system shall be designed in accordance with the applicable standards contained in the previous section. Where the standards and the requirements defined herein disagree, the more stringent shall apply. JIS standards can be used in lieu of the standards referred.

a. Electrical System: Refer to the as-built electrical distribution single line diagrams, site plans, and transformer details. (As-built drawings do not exist for some locations).

b. Ducts and Conductors:

W912HV-19-R-0008 – SECTION 01 11 00-A - SOW Chapter 9-4

(1) All underground electrical utility lines shall be installed in non-metallic ducts (PVC 40). All underground conductors shall be copper. Aluminum conductors shall not be allowed. Overcurrent protection shall be provided for all current carrying conductors except for neutrals. The Offeror shall perform the design and construction to include but not limited to the following:

(a) Underground ducts for power shall be installed in concrete encased ducts 610 mm below grade in areas accessible to traffic. Concrete encasement shall be a minimum of 76 mm of concrete around each duct. Separators or spacing blocks shall be made of steel, concrete, plastic, or a combination of these materials placed not further apart than 1219 mm on centers. Ducts shall be securely anchored to prevent movement during the placement of concrete, and joints shall be staggered at least 152 mm vertically. For areas not accessible to traffic, use sand cushion in lieu of concrete encasement. Direct burial of electrical cables shall not be allowed.

(b) All low voltage conductors shall be 600 volts, type THWN, XHHW or RHW. All busses shall be copper.

(2) Duct line markers shall be provided. The Contractor shall perform the design and construction to include but not limited to the following:

(a) Markers shall be a 0.1016 mm minimum thickness brightly colored red plastic tape not less than 76 mm in width and suitably inscribed at not more than 3048 mm on centers with a continuous metallic backing and a corrosion resistant 1-mil metallic foil core to permit easy location of the duct line, and shall be placed approximately 305 mm below finished grade levels of such lines.

(b) Red colored tape only applies to electrical duct lines.

(3) All exterior electrical connections and terminations will be made with an anti-oxidant joint compound to reduce corrosion.

c. Utility Outages: The Contractor shall initiate requests for outages no less than 45 calendar days prior to any interruption of service in the existing electrical system. Written requests shall be forwarded to the

Contracting Officer. The Contractor shall submit detailed plan with an outline of the equipment,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.