Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
FY15 Replace/Renovate EJ King High School, Commander Fleet Activities, Sasebo, Japan
The purpose of this amendment is to:
1) Revise Draw ings and Specifications
2) Provide As-Built Draw ings for informational purposes only
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HV18B0005
X 9B. DATED (SEE ITEM 11)
21-Sep-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Nov-2018
CODE
CONTRACTING DIVISION
USACE-JAPAN DISTRICT
RM 147, BLDG. 250
CAMP ZAMA
ZAMA-CITY, KANAGAWA 252-8511
JAPAN
W912HV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HV18B0005
14. DESCRIPTION OF AMENDMENT (continued)
A. CHANGES TO SPECIFICATIONS – The amendment mark “(Am-0002)” is shown on each page of the amended specification section(s).
(1) Revised Section(s) to Project Specifications. Attached hereto are the following revised section(s) to the specifications. Revised section(s) will replace like-numbered section(s) in the subject solicitation specifications. Changes are indicated by a red line in the left margin of revised areas. All portions of the revised section(s) shall apply whether or not changes have been indicated.
Revised Section(s)
Section 01 91 00.00 40 Section 05 50 13 Section 09 72 00 Section 23 08 00.00 10 Section 26 05 48.00 10 Section 26 20 00 Section 31 23 01.00 20 Section 33 71 02
(2) Deleted Section(s). The following section(s) are deleted entirely from the specifications:
Deleted Section(s):
Section 32 18 23
B. CHANGES TO DRAWINGS (ISSUED) – The amendment mark “(Am-0002)” is shown on each sheet of the amended drawing sheet(s).
(1) Revised Sheet(s) to Drawings. Attached hereto are the following revised sheets to the drawings. Revised sheets will replace like-numbered sheets in the subject solicitation drawings. Changes are indicated in revision clouds. All portions of the revised sheet(s) shall apply whether or not changes have been indicated.
DRAWING NO. REVISION DATE
GC101 11/2018
GC102 11/2018
GI101 11/2018
GI104 11/2018
H-001 11/2018 H-101 11/2018 C-100 11/2018
C-101 11/2018 C-102 11/2018 C-509 11/2018
CD101 11/2018
CD102 11/2018
CU103 11/2018
S-610 11/2018
AD101 11/2018
1A-160 11/2018 1A-202 11/2018 1A-420 11/2018 1A-430 11/2018 1A-432 11/2018 1A-434 11/2018 1A-436 11/2018 1A-439 11/2018 1A-440 11/2018 1A-444 11/2018 1A-445 11/2018 A-502 11/2018 A-507 11/2018 A-562 11/2018 A-602 11/2018 A-605 11/2018 A-701 11/2018 A-710 11/2018 A-801 11/2018
ES-001 11/2018
ES101 11/2018
ES104 11/2018
1EP601 11/2018
1EP701 11/2018
2ED101 11/2018
2EP101 11/2018
2EP602 11/2018
3EP701 11/2018
E-501 11/2018
(2) Deleted Sheet(s) from Drawings. The following drawing sheets are deleted from the drawings and are no longer part of the solicitation:
DRAWING NO.
C-520 C-521
C-522
TA001
TA002
TA003
TA101
TA102
TA103
TA104
TA105
TA106
TA107
TA200
TA300
TA301
TA302
TA303
C. All questions and the Government responses regarding this solicitation are to be viewed through the web-based program “Bidder Inquiry Module”. This program is located on the world-wide internet and can be accessed at https://www.projnet.org/projnet. Answers provided to the respective questions through the ProjNet do not amend the solicitation (specifications, drawings, etc.) unless revision to the specifications or drawings is specifically noted and incorporated into the solicitation via an amendment.
D. "As-Built" drawings are provided in this Amendment for informational purposes only (FIO). These "As-builts" drawings are not part of the solicitation (and will not become part of the contract) and do not amend the solicitation (specifications, drawings, etc.). "As-builts" drawings may not be complete or depict existing conditions. The contractor will be responsible for verifying actual conditions at the site. These files are listed as “FIO – Bldg 1530 AsBuilts.pdf”, “FIO – Bldg 1618 AsBuilts.pdf”, and “FIO – Bldg 1665 AsBuilts.pdf”.
E. The bid due date and time is unchanged.
File details come from the government source that posted it.