AM_0006_-_P994,_Truck_Fuel_Facilities_(26_May_17).pdf
PDF 733 KB Posted
- Attached to
- P994 - Construct Truck Fuel Offload & Load Facilities, Marine Corps Air Station (MCAS) Iwakuni, Japan
- Solicitation number
- W912HV-17-R-0003
About this file
Amendment 0006 - P994, Construct Truck Fuel Facilities
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See continuation page.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HV-17-R-0003
X 9B. DATED (SEE ITEM 11)
31-Mar-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
26-May-2017
CODE
CONTRACTING DIVISION
USACE-JAPAN DISTRICT
RM 147, BLDG. 250
CAMP ZAMA
ZAMA-CITY, KANAGAWA 252-8511
JAPAN
W912HV 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
X
Am-0006 Standard Form 30 IFB No. W912HV-17-R-0003 Page 2 of 2 Item 14 (Continued)
14. DESCRIPTION OF AMENDMENT (continued)
A. CHANGES TO DRAWINGS (ISSUED) – The amendment mark “(Am-0006)” is shown on each sheet of the amended drawing sheet(s).
(1) Revised Sheet(s) to Drawings. Attached hereto are the following revised sheets to the drawings. Revised sheets will replace like-numbered sheets in the subject solicitation drawings. Changes are indicated in revision clouds. All portions of the revised sheet(s) shall apply whether or not changes have been indicated.
DRAWING NO. REVISION DATE
FM-001 5/26/2017
B. The following page contains questions that were submitted by potential offerors. Answers provided to the respective questions do not amend the solicitation (specifications, drawings, etc.) unless revision to the specifications or drawings is specifically noted and incorporated into the solicitation. Please see attached list of questions.
C. The proposal due date and time remains unchanged.
AM-0006
RFI RFP / SOW
Location, P # ti titl / btitl
Question Answer
FM-403 & Government's Response for Question #63 in Amend 0005
We understand that the government requires outage of these facilities to be a minimum, however the work cannot be completed in one week. Please provide work descriptions and procedures which justify the work can be done in one week, otherwise we request the duration of the outage to be determined by discussions between the government and the contractor.
See revised drawing, FM-001 issued in this amendment.
FM-404 & Government's Response for Question #64 in Amend 0005
We understand that the government requires an outage of these facilities to be a minimum, however the work cannot be completed in three days. Please provide work descriptions and procedures which justify the work can be done in three days, otherwise we request the duration of the outage to be determined by discussions between the government and the contractor.
See revised drawing, FM-001 issued in this amendment.
FM-405 & Government's Response for Question #65 in Amend 0005
We understand that the government requires an outage of these facilities to be a minimum, however the work cannot be completed in one week. Please provide work descriptions and procedures which justify the work can be done in one week, otherwise we request the duration of the outage to be determined by discussions between the government and the contractor.
See revised drawing, FM-001 issued in this amendment.
AM-0006
33 08 53 3.2, FM-403 &
Government's Response for Question #67 in Amend 0005
Please confirm flushing scope of work for FM- 403 and Flow Diagram on FM-003 indicated on attachment 2. We understand spec 33 08 53 Para 3.2 "Samples of fuel shall be taken and tested by the designated government agency and shall be free of gross contamination, maximum of 8.0 mg/gallon solids and free water not to exceed 2 ml per quart." for flashing/cleaning scope of work, however "The offload and portable pantograph hydrant hose truck lines shall be flushed...." does not apply to the work indicated on the attachment. We will prepare detailed work plan, but lack of specific work description will be unfair to bidders.
Bid as advertised. Means and methods used to meet spec 33 08 53 Para 3.2 contract requirements shall be determined by the Contractor.
33 08 53 3.2, FM-404 &
Government's Response for Question #68 in Amend 0005
Please verify flushing scope of work for piping at pump house 1027 indicated on attachment 1, FM-004. We will prepare detailed work plan, but lack of specific work description will be unfair to bidders.
Bid as advertised. Means and methods used to meet spec 33 08 53 Para 3.2 contract requirements shall be determined by the Contractor.
1. IN GENERAL, DRAWINGS ARE DIAGRAMMATIC IN NATURE. NOT ALL
COMPONENTS ARE SHOWN IN ALL VIEWS. THE CONTRACTOR SHALL MAKE
USE OF THE ENTIRE SET OF DRAWINGS AND REQUIREMENTS IN
SPECIFICATIONS IN ORDER TO INCLUDE ALL COMPONENTS NECESSARY TO
CONSTRUCT A FULLY OPERATIONAL FUELING SYSTEM.
2. WRITTEN DIMENSIONS ON DRAWINGS SHALL HAVE PRECEDENCE OVER
SCALED DIMENSIONS. DRAWINGS WITHOUT A SCALE BAR ARE NOT TO SCALE.
3. THE CONTRACTOR AND SUB CONTRACTORS SHALL COORDINATE ALL WORK
WITH ALL OTHER TRADES BEFORE ANY INSTALLATION IS MADE.
4. ALL EQUIPMENT SHALL BE INSTALLED IN ACCORDANCE WITH
MANUFACTURER'S APPROVED PUBLISHED LITERATURE.
5. INSTALLATION OF EQUIPMENT SHALL PERMIT ACCESSIBILITY FOR SERVICE
AND/OR REPLACEMENT.
6. ALL UNITS ARE MILLIMETERS UNLESS OTHERWISE NOTED, ALL PIPE SIZES
ARE DIAMETER NOMINAL (DN).
A
PIPE SUPPORT LOCATION
DIFFERENTIAL PRESSURE GAUGE
TURBINE FLOW METER
S SOLENOID
CONNECT TO EXISTING
FUELING HOSE
SWIVEL JOINT
BALL JOINT
AUTOMATIC TANK GAUGE
90 DEG ELBOW DOWN
OR MANUAL AIR VENT
LOW POINT DRAIN
BASKET STRAINER
PRESSURE GAUGE
LINE SIZE REDUCER
BALL CHECK RELIEF
RELIEF VALVE SETTING
BALL VALVE, FULL PORT
PLUG VALVE, DOUBLE BLOCK AND BLEED
OR
IF
INSULATING FLANGE
SAMPLE CONNECTION
RELIEF VALVE
SIGHT FLOW INDICATOR
BLIND FLANGE
FLEXIBLE CONNECTION
QUICK CONNECTOR
CAP
ABOVEGROUND PIPE
UNDERGROUND PIPE
FLOW SWITCH
BUTTERFLY VALVE
WYE STRAINER
CONTROL VALVE
CHECK VALVE
BALL VALVE
GALV
GA
FP
FCV
FSR
FTG
FSCV
FOB
FS
FOT
FFE
EX
IF
LSHH
LSL
LSH
LPD
MFR
MAX
MIN
MAV
NO
NC
ID
HP
LI
AT@
ANCHOR BOLTAB
AAV
AFF
OAE
AND
ABOVE FINISHED FLOOR
AUTOMATIC AIR VENT
OFFLOAD AIR ELIMINATOR
ALUMINUM
ABOVEGROUND
A/C
ALUM
A/G
API
ASTM
AWS
AWG
ATG
AMERICAN WELDING STANDARDS
ABOVE CEILING
AUTOMATIC TANK GAUGING
AMERICAN WIRE GAUGE
AMERICAN PETROLEUM INSTITUTE
BPCV
CENTER LINE
CLEAR
CONCRETE
CLR
CFM
CL
CONC
CUBIC FEET PER MINUTE
BACK PRESSURE CONTROL VALVE
AMERICAN STANDARDS FOR TESTING AND MATERIALS
CONTINUATIONCONT
CV
DEGREE
DOUBLE
DIAMETER
DEG
DBL
DIA
CONTROL VALVE
DRAWING
DIAMETER NOMINAL
DWG
DN
EACH
EACH FACE
ECCENTRIC
EA
EF
ECC
ELBOW
ELEVATION
EL
ELEV
CONNECTIONCONN
OCV
OPERATIONS
OD
OPS
OP
OV
OSHA
OFFLOADING CONTROL VALVE
OUTER DIAMETER
OVERFLOW VALVE
PUMP CONTROL PANEL
OFFLOADING PUMP
PD
PDM
PRESSURE
PDMO
POL
PRESS
POSITIVE DISPLACEMENT METER OFFLOADING
PETROLEUM OIL LUBRICANT
POSITIVE DISPLACEMENT METER
PRESSURE DROP
REINFORCE
RADIUS
REDUCER
PRT
RAD
REINF
RED
REQUIRED
RAISED FACE
SCHEDULE
REQ'D
RF
SCH
RPM REVOLUTIONS PER MINUTE
PRODUCT RECOVERY TANK
PUMP DISCHARGE CONTROL VALVEPDCV
PCP
STANDARD
STEEL
SS
STD
STL
STAINLESS STEEL
TYPICAL
WITH
VACUUM
VALVE
U/G
TYP
W/
VAC
V
WEIGHTWT
UNDERGROUND
OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION
O/C ON CENTER
NATIONAL PIPE THREADNPT
NTS NOT TO SCALE
GALVANIZED
GAUGE
FLAT ON BOTTOM
FILTER SEPARATOR CONTROL VALVE
FILTER SEPARATOR RECEIPT
FLOW CONTROL VALVE
FUEL PUMP
FOOTING
FLOW SWITCH
FINISH FLOOR ELEVATION
FLAT ON TOP
EXISTING
LEVEL SWITCH LOW
LEVEL SWITCH HIGH
LEVEL SWITCH HIGH HIGH
INSULATING FLANGE
MANUFACTURER
MAXIMUM
MINIMUM
MANUAL AIR VENT
LOW POINT DRAIN
LEVEL INDICATOR
NORMALLY OPEN
NORMALLY CLOSED
NET POSITIVE SUCTION HEAD AVAILABLE
INSIDE DIAMETER
HYDRANT PIT
POSITION SWITCH
UNION
DOUBLE WALLDW
LEGENDABBREVIATIONS
1. THE FUEL SYSTEM SCOPE FOR THIS PROJECT INCLUDES, BUT IS NOT LIMITED TO, THE
FOLLOWING SYSTEMS AND ASSOCIATED COMPONENTS:
- DEMOLITION OF EXISTING FILLSTANDS AND PIPING LOCATED AT THE TRUCK OFFLOAD AREA, FACILITY NO.'S M1-35 & 2115
-DEMOLITION OF EXISTING UNDERGROUND DRAIN TANK 26160601, ASSOCIATED PUMPS AND
PIPING AT BUILDING 2616
- INSTALLATION OF FOUR NEW OFFLOAD SKIDS & OFFLOAD PIPING TO HEADER AT TRUCK
OFFLOAD AREA
- INSTALLATION OF TWO NEW TRUCK FILLSTANDS WITH ONE RETURN TO BULK CONNECTION
AT TRUCK FILLSTAND AREA
- MODIFICATION OF VALVE PIT 'B' PIPING IN HYDRANT SYSTEM MC909-T AT TRUCK FILLSTAND
AREA
- INSTALL CROSSOVER VALVE IN PUMPHOUSE 1027
- INSTALL JUMPER NEXT TO PUMPHOUSE 2614
- INSTALL JUMPER AT PUMP SHED 2125
GENERAL NOTES (APPLIES TO ALL FUELING WORK):
SCOPE:
CS CARBON STEEL
BARRELBBL
PIPE SUPPORTPS
SS
SURGE SUPPRESSOR
PUMP
M
POSITIVE DISPLACEMENT METER
S
BASKET STRAINER w/ DIFFERENTIAL PRESSURE GAUGE
PLUG VALVE, FULL PORT
FTP FUEL TRANSFER PUMP
FSI FILTER SEPARATOR ISSUE
THICKTHK
PRP PRODUCT RECOVERY PUMP
CONTROL VALVE - CHECK
GLOBE VALVE
LSLL LEVEL SWITCH LOW LOW
SINGLE POINT RECEPTACLESPR
PRESSURE/VACUUM VENT
LEVEL INDICATOR
IVP ISOLATION VALVE PIT
TEST CONNECTION
TC TEST CONNECTION
HLCV HIGH LEVEL CONTROL VALVE
PRESSURE SENSOR
NPSHA
S
ATG
DP
M
LI
HLA HIGH LEVEL ALARM
HHLA HIGH HIGH LEVEL ALARM
LLLA
LLA LOW LEVEL ALARM
LOW LOW LEVEL ALARM
kPa KILOPASCAL kW KILOWATT
LPS LITERS PER SECOND
SUMP PUMPSP
HPV HIGH POINT VENT
JP JOCKEY PUMP
SHEET
IDENTIFICATION
W F
D
D E
S I G
N E
D
B
Y
D W
N
B
Y
C K
D
B
Y
S O
L I C
I T
A T
I O
N
N
O
C O
N T
R A
C T
N
O
P L O
T
S
C A
L E
S U
B M
I T
T E
D
B
Y
F I L E
A M
E
S I Z
E
US Army Corps of Engineers
A
B
C
D
1 2 3 4 5
M A
R K
D E
S C
R I P
T I O
N D
A T
E A
P P
R
SIGNED
THIS WORK WAS
PREPARED BY ME OR
UNDER MY SUPERVISION
C H
R I S
P
T
T E
R S
O N
SHEET
U S
A
R M
Y
C
O R
O
F
E
N G
I N
E E
R S
J A
P A
N
E
N G
I N
E E
R
D
I S
T R
I C
T
A P
O
A
P
D R
A W
I N
G
C
O D
E
Japan Engineer District
S U
B M
I T
T A
L
D
A T
E
P L O
T
D
A T
E
F
I S
O
A
SHEETSHEET OF 93
100% DESIGN
F Y
P
R O
J E o
D
E S
C
C O
N S
T R
U C
T
T
R U
K
U E
L
O
F F
L O
A D
A N
D
L O
D
C
I L I T
I E
S
M C
I W
A K
U N
I
J A
P A
N
F I
T
H
M
U
S A
C E
O m a h a
D i s t r i c t
I w a k u n i
O f f l o a d D
R A
W I N
G S
F
M d w g
O
T T
B
Y
T h u r s d a y
A p r i l
P
M
GATE VALVE
F U
E L I N
G
G
E N
E R
A L
N
O T
E S
FM-001
F M d w g
C F
G T
H S
C F
G kW
LPS
RPM
MOTOR DATA
V/PH/HZ
OF FLUIDFLUID
m
OF
FLUID
NPSHA
m
LOCATIONTYPE OF PUMP
PUMP SCHEDULE
DESIGNATION
GRAVITY
SPECIFIC
OP-3
OP-4
IN-LINE CENTRIFUGAL TRUCK OFFLOADING JP-5 38
IN-LINE CENTRIFUGAL TRUCK OFFLOADING JP-5 38
0.81
0.81
78.5 9 35 440/3/60 3600
360078.5 9 35
OP-5 IN-LINE CENTRIFUGAL TRUCK OFFLOADING JP-5 380.81 360078.5 9 35
OP-6 IN-LINE CENTRIFUGAL TRUCK OFFLOADING JP-5 380.81 360078.5 9 35
TLCV TRUCK LOADING CONTROL VALVE
440/3/60
440/3/60
440/3/60
LPSFLUIDLOCATIONTYPE OF TANK
TANK SCHEDULE
DESIGNATION
GRAVITY
SPECIFIC
OAE-3
OAE-4
ASME BPVC SEC VIII D2 TRUCK OFFLOADING JP-5 38
ASME BPVC SEC VIII D2 TRUCK OFFLOADING JP-5 38
0.81
0.81
OAE-5 ASME BPVC SEC VIII D2 TRUCK OFFLOADING JP-5 380.81
OAE-6 ASME BPVC SEC VIII D2 TRUCK OFFLOADING JP-5 380.81
(LITERS)
CAPACITY
CON CONCENTRIC
PANTOGRAPH
2-8-2017
1. PROJECT SHALL BE CONDUCTED IN TWO PHASES.
2. PHASE 1 SHALL INCLUDE CONSTRUCTION OF THE TWO TRUCK FILLSTAND
POSITIONS.
3. PHASE 1 SHALL ALSO INCLUDE THE CONSTRUCTION OF THE CANOPY OVER
THE FILLSTAND POSITIONS.
4. ALL ELEMENTS OF PHASE 1 SHALL BE COMPLETED AND SHALL BE ACCEPTED
BY THE GOVERNMENT BEFORE ACTIVITIES IN PHASE 2 ARE STARTED.
5. PHASE 2 SHALL INCLUDE THE CONSTRUCTION OF THE FOUR OFFLOAD
POSITIONS, THE CROSSOVER VALVE IN PUMP HOUSE 1027, THE JUMPER
CONNECTION AT PUMP HOUSE 2614, THE JUMPER CONNECTION AT PUMP
SHED 2125. AND THE MODIFICATIONS TO THE FENCE AROUND THE POL
OPERATIONS BUILDING.
6. OFFLOAD POSITIONS 1 & 2 SHALL REMAIN OPERATIONAL DURING ALL PHASES
OF CONSTRUCTIO WITH THE EXCEPTION OF A MAXIMUM SHUTDOWN OF 2
(TWO) WEEKS TO INSTALL NEW PIPING AND TIE INTO THE EXISTING OFFLOAD
SYSTEM.
7. LOSS OF SERVICES TO FACILITIES 2614 & 2125 SHALL BE MINIMIZED WITH A
MAXIMUM ALLOWABLE DURATION OF 10 (TEN) DAYS.
8. LOSS OF SERVICES TO FACILITY 1027 SHALL BE MINIMIZED WITH A MAXIMUM
ALLOABLE DURATION OF 10 (TEN) DAYS.
9. LOSS OF SERVICES TO THE HYDRANT LOOP SERVICED BY PUMPHOUSE
SHALL BE MINIMIZED WITH A MAXIMUM ALLOWABLE DURATION OF 10
(TEN) DAYS.
10. PHASE 2 SHALL ALSO INCLUDE THE CONSTRUCTION OF THE CANOPY OVER
THE NEW BULK OFFLOADING EQUIPMENT ISLAND.
PROJECT PHASING
R E
V I S
H A
S I N
G
N
O T
E S
5/
6/
(AM-0006)
j2ee9cms Polygon
| Page 1SF30 - AM 0006, P994 |
| SF30 |
| A. CHANGES TO DRAWINGS (ISSUED) – The amendment mark “(Am-0006)” is shown on each sheet of the amended drawing sheet(s). |
| (1) Revised Sheet(s) to Drawings. Attached hereto are the following revised sheets to the drawings. Revised sheets will replace like-numbered sheets in the subject solicitation drawings. Changes are indicated in revision clouds. All portions of th... |
| Additional RFIs - P994, Truck Fuel Facilities |
| Table 1 |
W912HV-17-R-0003 Am-0006 Drawings
File details come from the government source that posted it. Updated .