About this file

This document is a set of Questions and Answers related to a federal contract opportunity for Intrusion Detection System (IDS) Preventative and Corrective Maintenance Services for the 81st Readiness Division (81st RD) of the U.S. Army Corps of Engineers.

The key details are:

  • The solicitation number is W912HP24Q1002 for a single award, indefinite-delivery/indefinite-quantity, firm fixed-price contract with a period of performance from 30SEP2024 to 30SEP2029.
  • Offerors are requested to provide fixed labor rates and markups for Corrective Maintenance (CM) services, which will be determined after site inspections.
  • The government approved a 24-hour extension for the quote submission, moving the due date to 24SEP2024 at 1100 EST.
  • The solicitation is a 100% small business set-aside under NAICS code 561621 (Security Systems Services).
  • Offerors are advised that the government may perform a comparative analysis and may reject any or all offers if it is in the public interest.

View the file

Other files for this federal contract opportunity

Other files attached to 81st Readiness Division (RD) Intrusion Detection System (IDS) Preventative and Corrective Maintenance Services, newest first.
File Type Posted
Quote Schedule (Revised) - 23SEP24.xlsx XLSX spreadsheet
B.08- RFQ AMD0002 24Q1002 IDS IDIQ.pdf PDF
Questions and Answers v2 19SEP24 .pdf PDF
B.08 RFQ AMD0001 24Q1002 IDS IDIQ.pdf PDF
Questions and Answers 18SEP24.pdf PDF
PWS Attachment 5 - IDS CM Estimate - 2024.07.20.pdf PDF
PWS Attachment 7 - Historical Parts List - 2024.09.09 1130.xlsx XLSX spreadsheet
PWS Attachment 3 - IDS PM Inventory Sheet - 2024.07.20.pdf PDF
PWS Attachment 6 - IDS GFP - 2024.08.23 0600.xlsx XLSX spreadsheet
PWS Attachment 4 - IDS CM Trip Ticket - 2024.07.20.pdf PDF
PWS Attachment 2 - IDS PM Checklist - 2024.07.20.pdf PDF
PWS Attachment 1 - IDS Panel Locations - 2024.08.23 0900.xlsx XLSX spreadsheet
Wage Determinations 12SEP24.xlsx XLSX spreadsheet
A.02- Performance Work Statement IDS 12SEP24.pdf PDF
W912HP12Q1002 Released 12SEP24.pdf PDF
Quote Schedule - 12SEP24.xlsx XLSX spreadsheet
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

81st RD IDS IDIQ

W912HP24Q1002

Questions and Answers

18SEP24:

1. Can you please clarify the CLIN’s for Corrective Maintenance FFP? There is a request to provide

CM costs on a spreadsheet indicating fixed labor rates and markups. Should this CLIN be responded to by requesting the reviewer to reference the attachment which includes the line item costing? Since CM costs are determined after site inspection there is not a acute way to assume max cost or unit price aside from the spreadsheet. Can you please clarify the intent?

Answer: Bid an hourly price for each Labor line-item and percentage for Overhead & Profit that will be applied to each Corrective Maintenance (CM) order during the life of the contract. The number of labors hours will be determined later during Preventative Maintenance (PM) inspection at which time the contractor will submit number of labor hours to the government for approval.

19SEP24:

2. Would the government consider an extension of the due date for this RFQ to 9/25/2024.

We would like that for addition time rudiments for research purposes for equipment pricing and potential subcontractors.

Answer: An extension is approved for 24 hours from the original due by date. This extends the RFQ period to Tuesday, 24SEP24 at 1100 EST. A formal amendment has been posted with this change.

23SEP24:

3. Do we know how many devices are included with each system? How many devices, typically, would a vault have etc. for each system type?

Answer: The panel attachment in the Performance Work Statement (see PWS Attachment 1- IDS Panel Locations) are all panels associated with this solicitation. Peripheral devices are unknown at this time. Preventative Maintenance for this project requires the awardee to inventory the panels/ devices as per the Performance Work Statement (Section 5.2.4.).

Per the contract, with emergency services to prevent the need for an armed guard, this somewhat assumes that the contractor must stock systems and supplies on hand to be able to make repairs quickly. Could you give us an approximation of equipment we should have in stock so we can reasonably cover providing up front stock that can be replenished?

Answer: Response in 24-48 hours is to assess the emergency, then follow-on action to repair it.

Please reference PWS section 5.3.4.1- POP for Emergency Task Orders.