B.08 Projnet RFI`s Responses .pdf

PDF 155 KB Posted

Attached to
Seymour Johnson Air Force Base-Berkeley Gate Construction Federal contract opportunity
Solicitation number
W912HN21B3004
Issued by
Department of the Army Corps of Engineers Engineering District Savannah

About this file

This document summarizes a bid inquiry report and related federal contract opportunity for construction work at Seymour Johnson Air Force Base. The bid inquiry report addresses 39 questions from potential offerors relating to specifications, drawings, and requirements for the Berkeley Gate Entry Control Point project. This project involves demolishing and removing the existing entry control point configuration and constructing a new layout that meets security force requirements. Key work includes installing new active vehicle barriers, a passive brick barrier system, a privately operated vehicle search area, and an overwatch facility. The federal contract opportunity is issued by the Department of the Army Corps of Engineers Engineering District Savannah for the construction of Seymour Johnson Air Force Base's new main gate in Goldsboro, North Carolina. The period of performance is 365 calendar days.

View the file

Other files for this federal contract opportunity

Other files attached to Seymour Johnson Air Force Base-Berkeley Gate Construction, newest first.
File Type Posted
Criminal and Drivers History Consent Form 190-6.pd.pdf PDF
C.04 Berkeley Gate Bid Open_ sign in sheet.pdf PDF
C.04 W912HN21B3004 - Bid Abstract.pdf PDF
B.08 W912HN21B3004 Amendment 0003 (Conformed Copy) .pdf PDF
B.08 W912HN21B3004 Amendment 0003.pdf PDF
B.08 W912HN21B3004 Amendment 0003 (Conformed Copy).pdf PDF
B.08 W912HN21B3004 Amd 0002 Specifications .pdf PDF
B.08 W912HN21B3004 Amendment 0002 (Conformed Copy).pdf PDF
B.08 W912HN21B3004 Amendment 0002.pdf PDF
B.08 W912HN21B3004 Amd 0002 Drawings Vol 2 .pdf PDF
B.08 W912HN21B3004 Amd 0002 Drawings Vol 1 .pdf PDF
B.08 21B3004 Amd01 Specs vol1.PDF PDF
B.08 W912HN21B3004 Amendment 0001.pdf PDF
B.08 W912HN21B3004 Amendment 0001(Conformed Copy).pdf PDF
B.08 VF102_SD_Pipe.pdf PDF
B.08 LaydownArea.pdf PDF
B.08 REVISED_DETAIL_3_A-310.pdf PDF
B.08 21B3004 Amd01 Specs vol2.PDF PDF
B.07 W912HN21B3004 Site Visit sign- in sheet.pdf PDF
B.08 W912HN21B3004 - Solicitation .pdf PDF
H.08 W912HN21B3004 Specifications Vol-1.pdf PDF
A.02 J&A Cummins Generator - Seymour Johnson Berkeley Gate (Redacted).pdf PDF
H.08 W912HN21B3004 Drawings Vol-1.pdf PDF
H.08 W912HN21B3004 Specifications vol-3.pdf PDF
H.08 W912HN21B3004 Drawings Vol-2.pdf PDF
H.08 W912HN21B3004 Drawings Vol-3.pdf PDF
H.08 W912HN21B3004 Specifications Vol-2.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Controlled Unclassified Information (CUI) Only

Bid Inquiry Contractor Report All Inquiries

Project: Berkeley Gate Entry Control Point Review: Berkeley Gate Bidder Inquiry (00001) (sorted by CommentID ) Displaying 39 inquiries.

Id Discipline Sheet Detail Spec 9263487 Architectural 04 20 00 Unit Masonry Comment Classification: Controlled Unclassified Information (CUI)

Please provide the manufacture and color of the brick required. It appears there may be multiple brick colors existing.

On: Jun 02 2021.

Government Response. . Offerors/bidders should determine the best method to accomplish the work as show in the plans, specifications and drawings. Bid/Propose as shown in the plans and specifications. The type and color of brick(field and accents) should match the brick of the existing Gate building which is immediately adjacent to the site of the proposed new Inspection Building and Overwatch. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9263499 Architectural A603 Vehicle Inspection Comment Classification: Controlled Unclassified Information (CUI) the two doors are stated to be hollow metal. No hollow metal specs are in the specifications.

On: Jun 02 2021.

Government Response. . closed On: Jun 07 2021 Government Response. . The text below appends or clarifies ALL previous replies.

An Amendment will be issued to address the issue. Hollow metal door spec. will be included. On: Jun 09 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9263509 Architectural 03 45 00 Precast Arch Concrete Comment Classification: Controlled Unclassified Information (CUI) the precast arch panels specs appear to be for precast wall panels. Are their wall panels to be provided or just the precast banding?

On: Jun 02 2021.

Government Response. . closed On: Jun 07 2021 Government Response. . The text below appends or clarifies ALL previous replies.

An amendment will be issued to address the issue. There are no wall panels the precast window sills. On:

Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9264396 Structural SB101 Comment Classification: Controlled Unclassified Information (CUI)

Please provide the dimensions of the column pads as well as the 12" pad under the building.

On: Jun 03 2021.

Government Response. . closed On: Jun 07 2021 Government Response. . The text below appends or clarifies ALL previous replies.

An amendment for this comment will be provided.

Column Footings sizes are indicated on 1/SB501. Pads over the base plates are the same size as the

6/16/2021 pilaster shown in the Architectural. Information for determining the mat dimensions are in the drawings. On:

Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9264972 Structural A603 Comment Classification: Controlled Unclassified Information (CUI)

A603 states to see structural for foundation design for the monument sign. Do not find the sign foundation in the structural, please provide

On: Jun 03 2021.

Government Response. . closed On: Jun 07 2021 Government Response. . The text below appends or clarifies ALL previous replies.

See 8/SB501 in Volume 3 for foundation for Electronic Sign. On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9264975 Architectural A603 Comment Classification: Controlled Unclassified Information (CUI)

Are we to include the monument sign in CLNS 2?

On: Jun 03 2021.

Government Response. . closed On: Jun 04 2021 Government Response. . The text below appends or clarifies ALL previous replies.

The brick monument is included under CLIN 001 On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9264978 Architectural A603 Comment Classification: Controlled Unclassified Information (CUI)

A603 does not show any sign items on the monument sign, please confirm contractor not to provide or install any sign items.

On: Jun 03 2021.

Government Response. . Closed. On: Jun 09 2021 Government Response. . The text below appends or clarifies ALL previous replies.

An Amendment will be issued to address the issue. Electronic sign is to be provided and installed.

Additional information will be added to Spec section 10 14 00.10 On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9264982 Architectural SB501 7 Comment Classification: Controlled Unclassified Information (CUI)

Please provide dismissions for the equipment pad

On: Jun 03 2021.

Government Response. . closed On: Jun 07 2021 Government Response. . The text below appends or clarifies ALL previous replies.

Dimensions for equipment pads shall be coordinated by the Contractor for the equipment used for project.

On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9265209 Architectural A101 Watch Bldg Comment Classification: Controlled Unclassified Information (CUI)

Drawings state steel pan stairs and shows a concrete landing, please confirm the treads are concrete filled as well and.

On: Jun 03 2021.

Government Response. . closed On: Jun 07 2021 Government Response. . The text below appends or clarifies ALL previous replies.

The treads of the stairs are to concrete filled. On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9265238 Architectural A301 Watch Bldg 3 Comment Classification: Controlled Unclassified Information (CUI) detail shows 7/8" hat channel securing to what appears to be metal stud framing. Please clarify and provide size of framing required

On: Jun 03 2021.

Government Response. . The attachment will be included as an amendment. On: Jun 07 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9265242 Architectural A301 Watch Bldg 3 Comment Classification: Controlled Unclassified Information (CUI)

Detail 3 shows an air barrier on the inside of the crawl space as well as the exterior of the block. Is this air barrier required in the crawl space as well?

On: Jun 03 2021.

Government Response. . This attachment will be included as an amendment. On: Jun 07 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9265607 Architectural Laydown area Comment Classification: Controlled Unclassified Information (CUI)

Specs state we are to enclose our laydown area and job trailer w/ temp fencing. Please provide the location we are to use for our laydown area

On: Jun 03 2021.

Government Response. . The Stakeholder's preferred location is shown within the red clouded area for the Contractor's laydown staging area.

The attachment will be included in an amendment. On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9265633 Civil Base utilities Comment Classification: Controlled Unclassified Information (CUI)

Please confirm all of the the utility work (water, sewer, and electrical) shown on the plans is to be perform by the base utilities and not the contractor. Please confirm this includes the demo of these utilities as well.

On: Jun 03 2021.

Government Response. . An amendment will be issued to address the inquiry. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9265789 Civil CD102 Comment Classification: Controlled Unclassified Information (CUI)

Shows to remove and replace w 15" RCP, what size and type of pipe is the existing? What is the depth of this pipe?

On: Jun 03 2021.

Government Response. . The attachment will be included in an amendment.

The information is located on sheet VF102 in volume 1 drawings, for this storm drain pipe. (attached and highlighted for clarity) The pipe in question is shown as an 8 inch CPP, depth can be determined by information given at the manholes. On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9266664 Civil CS503 Comment Classification: Controlled Unclassified Information (CUI)

Please clarify if the masonry wall shown on CS503 which is shown to be 1'-6" wide is to be the passive vehicle barrier shown on CS102 & CS103, which states to be 2' wide

On: Jun 04 2021.

Government Response. . An amendment will be issued to address the inquiry. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9269030 Construction Management 01 35 26 and 01 45 00 Comment Classification: Controlled Unclassified Information (CUI)

Section 01 35 26 paragraph 1.6.1.1 allows the SSHO to serve as QC manager but not Superintendent which conflicts with Section 01 45 00 paragraph 3.4.2 stating the QC manager has duties as Superintendent. Please clarify that QCM/Supr/SSHO can be a single person assignment

On: Jun 05 2021.

Government Response. . An amendment will be issued to address the inquiry. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9269031 Construction Management 01 45 00 Comment Classification: Controlled Unclassified Information (CUI)

Paragraph 3.4.3 requires the QC support staff to be directly employed by the prime. This restriction adds un-neccessary costs to the project because most trades will not be continuously on-site. Being employees of the prime, the specailized QC personnel will be a continuous cost to the project. Please eliminate the requirement, and allow the specialized personnel to be suppliers or subcontractors.

On: Jun 05 2021.

Government Response. . An amendment will be issued to address the inquiry. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9269609 Architectural CS503 Comment Classification: Controlled Unclassified Information (CUI)

Drawing shows a barrier wall column. Please provide clarifications for the spacings of these columns if required.

On: Jun 07 2021.

Government Response. . An amendment will be issued to address the inquiry. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9269682 Architectural CS103 Comment Classification: Controlled Unclassified Information (CUI)

There is a 100' section of sidewalk shown to have a synthetic surface. Please confirm this one section of sidewalk is the only area to receive this surface.

On: Jun 07 2021.

Government Response. . Confirmed. This section of sidewalk has it's own unique hatching, and when compared to the hatch on sheet GC004 under proposed work hatch patterns, you can see that this is the only area where the synthetic 'black top' surface is applied. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9269699 Contracting Construction Schedule Comment Classification: Controlled Unclassified Information (CUI)

Do to the permitting, submittals, documentation required prior to starting, the phasing of the work, traffic control and outages, we anticipate this project will take at least 450 days in lieu of the 365 given. Please consider extending the duration of this project

On: Jun 07 2021.

Government Response. . Offerors/bidders should determine the best method to accomplish the work as show in the plans, specifications and drawings. Bid/Propose as shown in the plans and specifications. On:

Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9269805 Architectural 08 34 02 Comment Classification: Controlled Unclassified Information (CUI)

What manufacture is the bases of design for the blast windows and door?

On: Jun 07 2021.

Government Response. . closed On: Jun 07 2021 Government Response. . The text below appends or clarifies ALL previous replies.

No specific manufacturer was used as a basis of design. The offerer shall make their own determination based on the solicitation and any means and methods shall be determined by the contractor. Bid as shown in the plans and specifications. On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9270168 Landscape Architecture N/AN/A N/A Comment Classification: Controlled Unclassified Information (CUI)

Irrigation for sod / plants- hydrant or water truck?

On: Jun 07 2021.

Government Response. . The Bidder shall make their own determination based on the solicitation and any means and methods shall be determined by the contractor. On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9270170 Landscape Architecture N/A N/A N/A Comment Classification: Controlled Unclassified Information (CUI)

Does pine straw mulch go in all planting areas on area A and B at Lirope and Juniper plantings Thanks

On: Jun 07 2021.

Government Response. . An Amendment will be issued to address the issue. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9270173 Landscape Architecture N/A N/A N/A Comment Classification: Controlled Unclassified Information (CUI)

Pine straw mulch around Pine trees on area C? Thanks

On: Jun 07 2021.

Government Response. . An Amendment will be issued to address the issue. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9271940 General Projnet Comment Classification: Controlled Unclassified Information (CUI)

We are seeing the government is closing questions but not giving responses. Will these all be addressed in a forth coming addendum?

On: Jun 08 2021.

Government Response. . All closed comments have been updated to reflect all Government responses and for all comments that will require an amendment for any drawings and specification revisions. On: Jun 09 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9276476 Contracting N/A N/A N/A Comment Classification: Controlled Unclassified Information (CUI)

SF-1442 states construction time @ 365 days.

Bid schedule issued with solicitation, on Page 13 of 80 states 900 days.

Please confirm period of performance. Thanks

On: Jun 10 2021.

Government Response. . An amendment will be provided to address comment.

The period of performance of this solicitation will be 365 days, the bid schedule will be updated in the forthcoming amendment. On: Jun 11 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277804 Civil CD102 Comment Classification: Controlled Unclassified Information (CUI)

What is the depth of the removable bollard's concrete footers?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277808 Civil CD103 Comment Classification: Controlled Unclassified Information (CUI)

What is the depth of the recessed barricade's concrete structure?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277809 Civil CD103 Comment Classification: Controlled Unclassified Information (CUI)

How thick is the concrete on the existing concrete speed humps?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277812 Civil CS503 Comment Classification: Controlled Unclassified Information (CUI)

Barrier Wall Typical Section Show the 4" Brick Ea. Side as "Optional". Please clarify what is optional? Where are we to price the option?

On: Jun 11 2021.

Government Response. . An Amendment will be issued to address the issue. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277814 Civil CS103 Comment Classification: Controlled Unclassified Information (CUI)

What is typical detail for the new concrete splitter island?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277816 Civil CG501 Comment Classification: Controlled Unclassified Information (CUI)

What is typical detail for the new concrete splitter island?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277817 Civil CD103 Comment Classification: Controlled Unclassified Information (CUI)

What is the depth of the concrete pads to be removed?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277818 Civil CD103 & CD104 Comment Classification: Controlled Unclassified Information (CUI)

What are the dimensions of the concrete landscaping borders to be removed?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021

Current Request Status: Request Closed Information for this report is procurement sensitive.

9277820 Civil CD104 Comment Classification: Controlled Unclassified Information (CUI)

What is the depth of the valley gutter to be removed?

On: Jun 11 2021.

Government Response. . Offeror/ bidder should determine the best method to accomplish the work as shown in the plans, specifications, and drawings. Bid/ propose as shown in the plans and specifications.

On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277871 Civil CG501 Bio-Swale Comment Classification: Controlled Unclassified Information (CUI)

What are the specific "Native Plants" required for this area? Where is this Bio-Swale shown on the Landscape Plans?

On: Jun 11 2021.

Government Response. . An amendment will be issued to address the inquiry. On: Jun 14 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9277960 Architectural A101 overwatch Comment Classification: Controlled Unclassified Information (CUI)

The finish schedule shown indicates finiahes for Rooms 104 and 105, but the floor plan only shows Room 103.

Where are Rooms 104 and 105 located.

On: Jun 11 2021.

Government Response. . An amendment will be issued to address the issue. There is no room 104 or

105. They have been deleted from the schedule. On: Jun 15 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9278515 Contracting N/A N/A N/A Comment Classification: Controlled Unclassified Information (CUI)

The SF1442 is requesting that we hold price for 365 days. Is this correct? thanks (Offers providing less than ___3_6_5__ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.)

On: Jun 11 2021.

Government Response. . STANDARD FORM 1442 will be amended to reflect the following; D. Offers providing less than 120 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. On: Jun 16 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

9279425 General N/A N/A N/A Comment Classification: Controlled Unclassified Information (CUI)

Bid schedule revised to say 365 days. Question is we need 365 working days, calendar days is not enough time.

Please consider extending the period of performance to 450 calendar days. thanks

On: Jun 11 2021.

Government Response. . The period of performance will remain at 365 days. On: Jun 16 2021 Current Request Status: Request Closed

Information for this report is procurement sensitive.

Report Complete

Controlled Unclassified Information (CUI) Only Patent 11/892,984 ProjNet property of ERDC since 2004.