Questions and Answers_25Q0010_UPS Maintenance.docx
DOCX document 17 KB Posted
- Attached to
- UPS Maintenance
- Solicitation number
- W912GY25Q0010
About this file
This is a Questions and Answers document for solicitation W912GY-25-Q-0010 regarding UPS maintenance and repair services. The key questions addressed technical requirements around Schneider Electric CPCS certification, which was subsequently removed from the solicitation requirements via an amendment to the PWS.
The Q&A clarifies that the system has a 250KV server with capability for both 250/500KVA, and contains 60 batteries that were last inspected in 2016 and 2018 (age unknown). The maintenance coverage is primarily for the UPS system and batteries, with no other ancillary equipment specified. The document addresses concerns about third-party maintenance capabilities and removes initial restrictions that would have limited service to Schneider Electric certified technicians only.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912GY25Q0010 UPS Solicitation Extended.pdf | ||
| Questions and Answers_25Q0010_UPS Maintenance.docx | DOCX document | |
| Questions and Answers_25Q0010_UPS Maintenance.docx | DOCX document | |
| Questions and Answers_25Q0010_UPS Maintenance.docx | DOCX document | |
| W912GY25Q0010 UPS Solicitation Updated.pdf | ||
| W912GY25Q0010 UPS Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers W912GY-25-Q-0010 UPS Maintenance and Repair
Question:
Does this requirement exclude a third-party business like ours from proposing a maintenance agreement that would be performed by our technicians, given that only technicians directly employed by Schneider Electric would hold this certification?
Answer:
We have removed this requirement from the Solicitation. Please see Amended PWS in the Solicitation uploads.
Question:
5.3. Preventive Maintenance Service. The Preventive Maintenance Service will be provided by trained Schneider Electric CPCS certified service personnel. The Contractor shall perform on-site service quarterlyfour (4) times a year. The Contractor shall provide updates, inspections, cleaning, and repairs and optimization of existing equipment and software. All repairs and changes in designed operation shall be discussed and approved by the COR prior to any implementation.
As far as I am aware, Schneider does not certify third parties to maintenance their equipment. So technically, Schneider Electric is the only company that could perform on this. While they do not certify, we are perfectly capable of performing maintenance on this unit. We hold many government contracts for preventative maintenance on similar APC Systems.
Let me know if we would be able to submit our offer even though we are not technically Schneider certified.
Answer:
We have removed this requirement from the Solicitation. Please see Amended PWS in the Solicitation uploads.
Question:
Needs to know if the system/s are 250Kva or 500Kva. Can you verify with your customer please?
Answer:
The system is capable of both 250/500 but it has a 250KV server.
Question:
1. Would it be possible to get an equipment list for the ancillary equipment that needs to be covered under this contract?
Answer:
Currently we are only aware of the System itself and the Batteries.
Question:
Could you also provide the number of Battery Modules (SYBTU2-PLP) the unit currently has? This will help us provide an accurate estimate for any "Over and Above" work for battery replacement.
Answer:
There are 60 Batteries
Question:
I was unable to find the information of the number of batteries that are with each UPS. Can you elaborate? And the age of the batteries?
Answer:
There are 60 batteries they were last inspected January of 2016 and 2018. We do not have an age.