September 11, 2019 Page 1 of 17
US Army Corps of Engineers Europe District
APO AE 09049
Statement of Work Project Number: ISB-19-0148
FY19 EDI, NSTA Projects
1) 350m MAT Access Road
2) Resurface Helicopter Apron, Taxiway, and Pad
Novo Selo Training Area (NSTA), Bulgaria
Prepared by: Project Design Section
Installation Support Branch
AMENDED
September 11, 2019
September 11, 2019 Page 2 of 17
September 11, 2019 Page 3 of 17
SECTION 01 10 10
STATEMENT OF WORK
SECTION TABLE OF CONTENTS
1.0 GENERAL
2.0 CIVIL AND GEOTECHNICAL
3.0 ARCHITECTURAL
4.0 STRUCTURAL DESIGN
5.0 ELECTRICAL & COMMUNICATIONS
6.0 MECHANICAL DESIGN
7.0 FIRE PROTECTION
8.0 SUSTAINABILITY .............................................................................................. Error! Bookmark not defined.
Attachments
Appendix 1 UFC 1-300-09N Design Procedures
Attachment - EDI-NSTA 350 M Moving Armor Target (MAT) Access Road Drawings
Attachment - EDI-NSTA Resurface Rotary Wing Apron Drawings
September 11, 2019 Page 4 of 17
1.0 GENERAL
1.1 PROJECT DESCRIPTION
The Request for Proposal (RFP) provides parameters for the following three (3) design-build projects at Novo Selo Training Area (NSTA), Bulgaria. The technical requirements for each individual project are provided in this 01 10 10 and the Drawing Attachments listed below.
Drawing Attachment - EDI-NSTA 350 M Moving Armor Target (MAT) Access Road Drawings Attachment - EDI-NSTA Resurface Helicopter Apron, Taxiway, and Parking Areas
1) 350-meter Moving Armored Target (MAT) Access Road. This is a dirt and gravel road that must be able to support a 5-ton vehicle and include design for any required necessary drainage. In addition, see
1.2.1 in this document and drawing attachments that are part of the Scope of Work.
2) Resurface Helicopter Apron, Taxiway and Parking Areas to support UH-60 Blawkhawk United States Army Helicopters. There is an existing gravel base that will be modified and upgraded as required to support these helicopters. The Apron and Taxiway will be Asphalt and the Helicopter Parking Areas will be concrete. There will be no standing water on the pad and apron. Include helicopters tie-downs to secure four UH-60 Blawkhawks, and helicopter apron and parking markings. In addition, see 1.2.2 in this document and drawing attachments that are part of the Scope of Work.
This scope is to be performed under a design-build method in which this statement of work represents a concept design. The design-build contractor is responsible for further developing the design and executing the construction of these projects. Concept plans are provided for reference. Neither these attachments, nor the described scope, referenced standards, or omitted standards relieve the design-build contractor from hiring their own designer to evaluate the existing conditions and design the new systems required to meet the performance criteria specified in the scope of this contract. As an example, pavement sections and any other requirements are included as a minimum for planning purposes only. The design-build contractor is responsible for determining the actual sections required for the project.
The contractor shall be responsible for planning and utilizing the appropriate equipment for executing the scope of work. This includes all general conditions associated with site mobilization, hoisting, scaffolding, etc.
1.2 GENERAL REQUIREMENTS
The Contractor shall deliver fully functional, turnkey type facilities and all associated work as described in this document. The work includes but is not limited to design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment shall be constructed IAW UFC 1-201-01.
The Contractor shall provide to the Contracting Officer’s Representative (COR) all design drawings, shop drawings and certificates as well as calculations prior to the beginning of construction. The contractor shall obtain all Permits necessary for the projects in accordance with FAR 52.236-7, Permits and Responsibilities. A copy of all permits, with English translation, shall be furnished to the COR prior to the start of construction work. The facilities in these projects shall be complete and usable to meet codes and technical and functional requirements per this SOW. All design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, G&A and general conditions to complete these projects as described in the SOW shall be included in the proposal price.
All projects shall be designed and constructed in accordance with current standards and building codes as described in these documents. The Contractor shall provide design and construction using the best blend of cost, construction
September 11, 2019 Page 5 of 17 efficiency, system durability, ease of maintenance and environmental compatibility. Compliance with the provisions of this section by subcontractors shall be the responsibility of the Contractor.
Base access for Contractor employees and sub-contractors is the responsibility of the Contractor including translating documents to English. The Contractor shall coordinate with the Base and follow all Base procedures.
1.2.1 350-Meter Moving Armor Target (MAT) Access Road The scope of work described in this document is for the design and construction of a new road that will provide access from the Maneuver Road to the existing maintenance road that runs along the 350-Meter Moving Armor Target (MAT), and associated improvements in the areas adjacent to the new road.
The site of the new proposed road is located at Military Grid 35TMH6440729788.
The work to be performed includes:
- New aggregate surfaced road (approximately 50 m) from the existing Maneuver Road to the starting point of the MAT maintenance road. The location shown in drawing C-01 is conceptual only. The Contractor shall select the most cost effective alignment.
- Repair areas adjacent to the new road, 25 m in each direction (50 m total) on both the north and south ends of the new road (150 m total), Repair area of spur road north of the adjacent road 100 m, approximately 250 m of total Road Repair, see drawing C-02. The intent of the repair is to restore the road surface to a condition similar to the new road.
- Site work required to construct the above improvements which includes, but not limited to, clearing and grubbing, rock removal, removal of unsuitable materials, earthwork including excavation and placement of compacted fill (cut and fill), grading, and any other associated work required for completion of the project.
The road is located at Military Grid 35TMH6440729788.
1.2.2 Resurface Rotary Wing Apron Requirements and Considerations
The scope of work for this project consists of design and construction of improvements to the existing rotary wing parking apron and the taxiway that connects it to the helipad located at Novo Selo Training Area (NSTA) Bulgaria.
These improvements include:
- Asphalt concrete pavement for the taxiway and the circulation area of the apron.
- Portland cement concrete (PCC) pavement for the designated parking spaces in the apron.
- Installation of new aircraft tie-downs (mooring points).
- Installation of lightning protection system.
- Drainage improvements to manage surface runoff from the taxiway and apron.
- Pavement markings.
- - Installation of oil-water separators and required drainage and piping for the four helicopter parking areas.
- Site work required to construct the above improvements which includes, but not limited to, demolition of existing aircraft tie-downs, removal of existing gravel layer, earthwork including excavation and placement of fill, grading, landscaping, and any other associated work required for completion of the project.
September 11, 2019 Page 6 of 17
The apron is located at Military Grid 35TMH6903329115.
1.3 GOVERNMENT REFERENCES
All references to “Government” included herein shall be interpreted as being US Government unless otherwise specified as HN Government (Host Nation Government).
1.4 MATERIALS AND EQUIPMENT
Any material installed that does not meet the requirements of this RFP shall be removed and replaced with materials that meet RFP requirements at the Contractor’s expense. See Specification 01 33 16 Design after Award for additional information.
Materials and products used, shall be durable, heavy duty industry standard. The equipment shall be the manufacturer’s standard quality and shall be compatible with all other equipment and materials within the system or assembly. Equipment and materials shall include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.
All equipment shall have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number on a plate secured to the piece of equipment. Operation and Maintenance manuals shall be provided for each piece of equipment. These shall be clearly labeled, bound and delivered at one time within 30 days of contract completion. Provide two (2) each of any unique tools required to operate or maintain each piece of equipment.
All equipment delivered and placed in storage shall be stored with protection from the weather and temperature variation, dirt and dust, and other contaminants. The contractor shall be responsible for the materials safety and condition while in storage. The Government shall not be responsible for damaged or missing equipment.
1.5 DESIGN DIMENSIONS
All design and construction documents shall be developed using the US Standard and metric system.
1.6 GENERAL DESIGN INSTRUCTIONS
The design and product requirements established in this Statement of Work are minimum requisites. The Contractor is responsible for designing and building a facility that meets all applicable codes and standards and is cost effective.
See Specification 01 33 16 Design after Award for additional information. Below are additional project-specific requirements. This RFP scope of work shall govern in case of conflicts between the scope and standard specifications.
Designer of Record shall have "related experience" on projects of the same type and nature as the work identified in this scope of work and be on contracts with the Government of the United States of America, either with the US Army Corps of Engineers or Department of Defense agencies. References and experience must be sufficiently detailed to allow for verification of experience. See specification section 01 30 00 General Requirements for additional information.
- Designer of Record shall attend the contractors Weekly Progress Meeting as required.
-Designer of Record site visits shall be coordinated with the COR and be in accordance with the quality control phases described in specification section 00 45 00 USACE QUALITY CONTROL. DOR shall provide a Trip report detailing meeting notes, issues and/or corrective actions from each site visit within 48 hours of each visit.
September 11, 2019 Page 7 of 17
1.7 DESIGN CRITERIA
Project design, site facilities, utility systems and material standards shall be in accordance with the latest editions of the US and Host Nation building codes. If there is difference between US and Host Nation standards or specifications, then the most stringent of the US or the Host Nation standards or specifications shall apply.
Unless otherwise noted, the design-build contractor shall base his design off the latest versions of the referenced standards and document and which versions are being utilized in a design narrative included in the 35% design submission. Note that the latest versions may be newer than those referenced in the design-build request for proposal.
The design-build contractor shall expect that referenced standards and performance criteria may change during design development. These changes could have minor impacts on placement, orientation, and/or shape of minor construction features, which shall be addressed at no additional cost to the Government if the change occurs prior to construction. The change shall be documented in the as-builts.
The design-build contractor shall consider applicable US and Host Nation Codes to include but not be limited to the following:
TC 25-8, Training Ranges, Headquarters Department of the Army, 2016 NFPA 101 Life Safety Code UFC 1-300-09N - Design Procedures
Uniform Facility Criteria (UFC) documents are available on the internet at:
http://www.wbdg.org/ccb/browse_cat.php?c=4 Use UFC 1-200-01 DoD Building Code (General Building Requirements) as the guiding UFC.
1.7.1 350-Meter Moving Armor Target (MAT) Access Road The design and construction of the proposed improvements must comply as a minimum with the following standards, in addition to the standards referenced above in 1.7:
- USACE Range Design Guide RDG RDG, Range Design Guides, USACE, Engineering and Support Center, Huntsville
The RDG is available by contacting team members of the Sustainable Range Program, USACE, Huntsville, Alabama, USA. Email requests for documents should be sent to DLL-CEHNC-RTLP@usace.army.mil.
- UFC 3-202-01 Civil Engineering
- UFC 3-250-09FA Aggregate Surfaced Roads and Airfields Areas
The road surface shall be designed to support a5-ton vehicle and M1A1 Armored Tank. During the design phase the Contractor shall verify dimensions of typical 5-ton and M1A1 Armored Tank vehicle used at the range and ensure the road geometrics are adequate.
The minimum road width shall be at least 3-Meter for a 5-ton and wider for a Tank.
1.7.2 Resurface Rotary Wing Apron Requirements and Considerations The design and construction of the proposed improvements must comply as a minimum with the following standards, in addition to the standards referenced above in 1.7:
- UFC 3-260-01 Airfield and Heliport Planning and Design
- UFC 3-260-02 Pavement Design for Airfields
- Army TM 5-820-1 Surface Drainage Facilities for Airfields and Heliports
- UFC 3-260-04 Airfield and Heliport Markings http://www.wbdg.org/ccb/browse_cat.php?c=4
September 11, 2019 Page 8 of 17
- UFGS 32 17 23 Pavement Markings
- ETL 12-8 Contingency Aircraft Tie-Downs in Portland Cement Concrete Pavements.
1.7.1 DESIGN SUBMITTALS
The contractor shall make formal design submittals at 35%, 65%, and 95% design as well as a corrected final 100%.
This includes a design analysis, a complete set of drawings, calculations and technical specifications at each submittal. Each ERI project shall be treated as a separate design package with its own cover sheet. In other words, the 35%, 65%, 95%, and 100% design shall consist of separate design packages for each project at each submission.
All projects shall be submitted under a singular transmittal for the relevant design submission, however; plans and specifications shall not all be combined into one package.
See Specification 01 33 00 SUBMITTAL PROCEDURES and Appendix 1 UFC 1-300-09N Design Procedures for additional information. The contractor shall submit all documents in electronic format .pdf for text and calculations, (.pdf and .dwg; AutoCAD, latest version) for drawings to the following individuals:
US Army Corps of Engineers, Attn: Michael Huntanar, PM, Konrad-Adenauer Ring 39, 65187 Wiesbaden 35%, 65%, 95% shall be submitted in Electric Copies (2 CD’s) only, corrected final 100% design submittal shall consists of: 2 CDs (Electronic Copies), 1 Full size and 2 Half size set, 1 set of Specification Binders (English and Bulgarian)
US Army Corps of Engineers, Attn: COR – contact info provided by request after contract award (delivery info to be provided upon award) 35%, 65%, 95% shall be submitted in Electric Copies (2 CD’s) only, corrected final 100% design submittal shall consists of: 2 CDs (Electronic Copies), 1 Full size and 2 Half size set, 1 set of Specification Binders (English) The construction schedule shall be provided prior to construction and included with the design submittals. The schedule shall be displayed in a Gantt chart with detailed description of all construction activities and clearly identifying the critical path of execution. The schedules shall be approved by the U.S. Government at each design review. The Contractor is responsible for providing updated schedules on a monthly basis during construction.
Unless specified otherwise, the Contractor shall assume a review time of 30 days for each submittal.
Additionally, with the 95% design submittal the Contractor is required to provide a DRAFT DD Form 1354 in accordance with UFC 1-300-08 CRITERIA FOR TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY
Submittal Register to be developed by the Contractor during the design phase.
1.7.2 ADDITIONAL DESIGN SUBMITTAL REQUIREMENTS
The following list further describes the requirements for design submittals and provides minimum criteria for each submittal.
Demolition Plan: GA:
The design-build contractor shall be responsible for developing a comprehensive demolition plan. The plan shall be submitted to the COR for approval no later than the 35% design submittal.
Sequencing Plan; GA
Provide a Sequencing Plan with the 95% Final Design Submittal. The Sequencing Plan must describe the proposed performance of construction operations to comply with the stated sequencing requirements. The Sequencing Plan
September 11, 2019 Page 9 of 17 must include a graphical depiction of the sequencing of each work area and mobilization/staging area. The Sequencing Plan is in addition to the requirements of Section 01 32 01 PROJECT SCHEDULE.
1.7.3 DESIGN CONFERENCES AND MEETINGS
The contractor and designated design team shall participate in design review conference at the 35%, 65%, and 95% design submittal. The Design Quality Control Manager must participate. No design review conference shall be required for the 100% corrected final.
All design review conferences shall be held via teleconference or be reviewed and comments resolved as described below.
All design review comments shall be logged and managed using ProjNet’s Dr. Checks system which can be accessed at this link: https://www.projnet.org. Please contact Europe District USACE to create accounts and gain access.
The Contractor shall provide meeting minutes during construction in English.
Unless otherwise noted, minimum Government review periods shall be IAW Specification 01 33 00 SUBMITTAL PROCEDURES. The Government will provide comments in ProjNet's Dr. Checks system after each design submission. Upon review of the design submission, the design-build contractor shall respond by evaluating these comments in Dr. Checks prior to the design review conferences. The design-build contractor shall provide any necessary corrections to the design with their evaluations and shall identify which design submission the issue will be corrected in. Comments will remain open until the issue is resolved. Once resolved, the commenter will backcheck their comments and close the comment.
1.8 TECHNICAL CRITERIA AND STANDARDS
Project design shall be in accordance with the requirements outlined in section 1.6.
The referenced standards in these specifications are incorporated only to the extent that they describe a technical standard to which the contractor has to perform the work described in the specifications. Any language that does not describe a technical standard, such as payment procedures, how specifications are to be drafted, are not included in these specifications.
1.8.1 LIFE-SPAN
The facilities shall be designed as semi-permanent according to UFC 1-201-01 - Non-Permanent DOD Facilities in Support of Military Operations.
1.8.2 MAINTAINABILITY
Low maintenance materials and systems must be employed and shall be appropriate for the project climate and location.
1.8.3 OPERABILITY
Systems including but not limited to mechanical, electrical, communications, shall be industry standard, low maintenance.
1.8.4 STANDARDIZATION
https://www.projnet.org/
September 11, 2019 Page 10 of 17
The Contractor shall use standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.
1.9 SPECIAL CONSTRUCTION PHOTOGRAPH DOCUMENTATION
1.9.1 PRECONSTRUCTION PHOTOS
Preconstruction Photos/Survey shall be performed in accordance with specification 01 30 00 General Requirements.
Contractor shall perform a Preconstruction Survey and submit to the COR prior to commencement of any work.
1.9.2 CONSTRUCTION PROGRESS PHOTOS
Photos shall be performed in accordance with specification 01 30 00 General Requirements.
1.10 PERMITS
In accordance with specification section 00 74 00 the obtaining of all permits needed to complete the work shall be the responsibility of the Contractor. The Contractor shall prepare all necessary documentation required for requesting permissions and making notifications to the HN authorities in accordance with public law and other applicable requirements and regulations. All necessary application documents shall be prepared by the Contractor in HN and English languages and submitted to U.S. Forces. Where the Contractor is responsible for obtaining the permit, the Contractor shall obtain approval and signatures as needed for the HN permitting and notification process from the COR. A copy of all permits shall be furnished to the COR prior to the start of construction work. All costs for permitting and notifications shall be borne by the Contractor.
Prior notice of at least 5 days shall be given to the COR, showing a permit was obtained in advance, before commencing work on the following work operations:
- Photo permit
- Site clearance
- UXO survey as required for digging permits
- Demolition
- Welding or metal-cutting work (‘Hot Work’ Permit)
- Work involving contaminated material
- Earthwork (The notice to the COR shall include provision of site drawings indicating the earthwork which will be performed, the schedule of when the work will be performed, and locations of all utilities near the earthwork site.
Drawings shall be of sufficient scale to clearly show the proposed work.)
- Tree felling
Prior notice of at least 3 days shall be given to the COR before commencing work on the following work operations:
- Backfilling over installed utility lines
- Video inspection of utility lines
1.11 REAL PROPERTY RECORD
Provide a Draft DD Form 1354 “Transfer and Acceptance of DoD Real Property” with the 95% Final Design Submittal. Complete the Draft DD Form 1354 in accordance with the instructions contained in UFC 1-300-08 CRITERIA FOR TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY
Contractor must provide a DRAFT DD Form 1354 in accordance with UFC 1-300-08 CRITERIA FOR TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY
September 11, 2019 Page 11 of 17
1.12 ADDITIONAL HOST NATION SPECIFIC REQUIREMENTS
The following information is provided as additional Host Nation requirements and information.
Design work shall include, but is not limited to the following:
- Prepare necessary plans and specifications for proper execution of each project.
- The drawing set shall require “wet” stamps and signatures of the Designer of Record. The Contractor shall submit three (3) sets of the calculations and drawings. The drawings shall include English with Host Nation translations.
The Designer of Record shall be licensed according to host nation laws and regulations.
- The contractor shall comply with and provide for any Host Nation design proofing requirements as part of the contract. This includes any design proofing and/or site supervision as required by Host Nation requirements.
- The Contractor is not allowed to commence demolition or construction work of any kind before all the designs have been proved and released. The Contractor shall coordinate his construction work with the proofing engineer.
Upon submission of the 100% designs, the Contractor shall delay (at no additional cost) the start of construction for up to 120 days in order for the (US) Government to present the 100% designs to the host nation Ministry of Defense (MoD) for coordination. The Contractor shall be responsible to revise the 100% designs by Architectural Supplemental Instruction to incorporate any host nation MoD requests and comments that are determined acceptable by the (US) Government. Construction activities shall only start upon direction from the (US) Government. It is possible that the entire 120 days MoD review period will not be required for all of the individual projects. In those cases construction activities will be able to start earlier. (Note: If the Government determines that the 35% design submission meets the minimum design submission requirements as outlined above and in UFC 1-300-09N, the Government may present the designs to the MoD to attempt early host nation approval.)
The Contractor will coordinate with the HN Government, in conjunction WITH THE U.S. Forces, to determine the requirements for proper final inspection by the HN and provide any information required for proper final acceptance. The contractor shall incorporate the requirements for final acceptance into the design and construction of the project.
1.13 OTHER CONTRACTS
It’s anticipated that other projects will be in construction in the vicinity at the time these projects have begun or finished, the COR will provide coordination with the contractors performing work on the other projects. The Contractor is also responsible for coordinating the efforts related to this contract in order to prevent rework on all Government contracts. In other words, the design-build contractor is responsible for complying with FAR 52.236-8 Other Contracts to ensure coordination of his schedule with adjacent projects managed by others. To the extent possible, work shall be coordinated with other contracts and/or the Contracting Officer or their representatives as needed to prevent schedule delays and rework under all Government contracts.
2.0 CIVIL AND GEOTECHNICAL
2.1 CIVIL
This section includes all services required for civil engineering and exterior site work within the scope of the design and construction.
The services covered by this section include all civil engineering labor, material supplies, and incidental work required for the demolition, design, fabrication, delivery, installation, and construction that serve each project.
Extensive coordination will be required between the civil/geotechnical work and the architectural, structural, fire protection, mechanical, and electrical requirements of each project.
September 11, 2019 Page 12 of 17
See individual project Attachments for additional information regarding the scope.
2.1.1 DESIGN SUBMITTALS
The contractor shall make the civil design submittals after contract award in accordance with Specification 01 33 16 Design after Award and in compliance with the GENERAL REQUIREMENTS section of this SOW.
This includes but is not limited to provision of the following documentation:
- Design Analysis for all civil construction works
- Geotechnical and hydrological reports
- Structural calculation / verification of appropriate construction of the foundations for the planned loads and use Contractor’s design analysis shall state and list the basis of design for all project aspects and features. The Contractor shall reference applicable local and national design documents, standards, and specifications used. All calculations and verifications are to be conducted and documented by the contractor in compliance with the applicable codes and criteria. Other calculation / verification are to be provided as required.
Additional base data being used for contractor’s calculations and verifications like rainfall data etc. shall be obtained from state approved sources only, which is to be documented by the contractor.
The Contractor shall provide civil design drawings of sufficient detail to address the requirements of each design submittal (see GENERAL REQUIREMENTS section of this SOW). Civil drawings shall include but are not limited to site plans, utility maps, longitudinal profiles as well as regular and characteristic cross sections of pavements and utility runs, details and construction drawings for engineering structures as well as a job site mobilization plan showing staging area, haul and access routes and any other features planned for contractor’s site mobilization.
2.1.2 DESIGN CRITERIA
Project design shall be in accordance with the requirements outlined in the GENERAL REQUIREMENTS section of this SOW.
2.1.3 CIVIL ENGINEERING AND SITE WORK
2.1.3.1 SITE LAYOUT
Unless otherwise noted, any existing utilities shall remain in place or be reconnected if disconnected. All impacted areas shall be restored to previous original or new condition as required.
2.1.3.2 SITE SURVEY
The Contractor is required to survey each project site and the features that will be affected by construction as part of the contract work effort, and furnish a final topographic survey of the existing conditions for impacted areas. The survey shall include all documentation in compliance with applicable standards.
The survey shall provide all data needed to design and construct the projects. The survey shall include location and elevation of all features within the project site limits, as well as all features and utilities outside of the site that will be tied into or included in the project scope of work. The survey shall also include sufficient documentation and analysis of the existing drainage to allow for a new proper drainage design, including areas which will be affected by new drainage patterns and surfaces which new construction will abut or adjoin.
September 11, 2019 Page 13 of 17
Upon completion of construction, the original survey shall be updated with an As-built survey of the site as constructed.
The As-built survey shall be submitted to the COR for approval.
2.1.3.3 HAZARDOUS MATERIALS AND CONTAMINATION
There is no prior knowledge of any hazardous materials at the site. However, it is possible that hazardous material may be found from previous use of the site, or that materials to be removed contain hazardous materials.
If hazardous materials are found to exist, the Contractor shall immediately notify the COR, cease work in the area, and secure the site. The Contractor shall take precautions to protect the site from surface run-off and precipitation, and prevent leaching of any hazardous material in the surrounding area. A change request shall be made by the contractor per FAR 52.236-2, Differing Site Conditions.
2.1.3.5 SITE MOBILIZATION & SEQUENCING
The Contractor shall provide mobilization and demobilization of all vehicles, material, and equipment to the project area. The Contractor shall prepare the site and perform all necessary preparatory work for digging and excavation.
The Contractor shall submit a site mobilization plan for Government approval, indicating proposed locations for staging, storage, trailers, parking and other Contractor use of the site, and shall work with Government to arrive at a final plan acceptable to the Government.
Disruption to “Normal” base operations by the contractor SHALL be coordinated and approved by the COR and Base Operation prior to commencement of work.
The Contractor shall maintain the site organized and free from debris. All standard security/safety measures shall be complied with. In addition, no open fires or burning of trash will be allowed within the confines of the project sites.
The Contractor shall develop thoughtful planning and phasing of the construction works as required ensuring that normal base operations are not disturbed in an unacceptable manner.
The Contractor shall submit a Sequencing Plan for Government approval as described above, indicating proposed sequence of construction as well as sequence related temporary swap space for parking or any other sequence related temporary construction or relocation of any existing site features and facilities.
The Contractor shall be responsible for any required temporary relocation or protection of existing facilities and site features and their reconstruction as well as for any other work related to Contractor-planned phasing and site mobilization.
This includes coordination and consideration of work to be done by impacted third party.
Any damage to structures, drainage facilities, utility lines, or other existing features on the site as a result of Contractor operations shall be repaired, or the damaged items replaced, at the Contractor's expense.
The Contractor is required to include information about the number/height of cranes, UTM coordinates of where the cranes will be placed, and duration that the crane will remain in use.
September 11, 2019 Page 14 of 17
Additional site mobilization and sequencing requirements are described elsewhere in the scope of work and shall be incorporated accordingly.
2.1.3.6 DEMOLITION AND REMOVAL
Civil demolition and removal shall be developed to minimize the amount of civil demolition and removal required.
Any structure, utility, pavement, feature, or landscaping to be demolished shall be shown on the demolition site plan. The Contractor shall stake-out the limits of disturbance before starting work. Demolition and removal work includes, but is not limited to: existing building structures, foundations, slabs, pavements, utilities, other building elements, trench excavation, spoil materials, rubbish piles, spent construction related materials and material canisters, miscellaneous debris, and leftover materials which have been abandoned. Clearing and grubbing of vegetation includes, but is not limited to: stumps, roots larger than 75 mm in diameter, brush, shrubs and other landscaping obstacles that obtrude, encroach upon, or otherwise obstruct the work. All debris generated during demolition, including excess soil/rock/topsoil, shall be removed from the project sites and properly disposed of by the Contractor in accordance with Host Nation requirements.
Existing trees within the site construction areas which are to remain in place shall be properly protected during construction work in accordance with HN standards. Any trees or shrubs which are to remain in place and are damaged by the Contractor shall be, irrespective of the degree of damage, replaced in kind and number.
Any existing utilities within the site boundary that interfere with each project shall be relocated. Where relocation of utility lines is not possible the Contractor must ensure that they are adequately secured to ensure uninterrupted services to other facilities. The Contractor shall coordinate all utility closures and disruptions with the COR. All shutdowns shall be coordinated a minimum of 14 days in advance. The Contractor shall disconnect utility lines (as required) before the commencement of demolition work. Utilities shall be properly capped, plugged or abandoned in place.
To determine the exact location of any exterior underground utility systems (e.g. water, sewer, gas, electrical, and/or telephone lines) including their dimensions, type of material and condition, the Contractor shall coordinate with the local personnel familiar with the site. The Contractor shall ensure that no underground pipes or cables of any kind and their accessories will be damaged during the performance of the work. Any repair shall be done at the Contractor’s expense and at the entire satisfaction of the COR.
Disposal of uncontaminated demolition material shall be official disposal sites (i.e. landfills, recycling centers, etc.).
The Contractor shall be responsible for determining and meeting the requirements of the disposal site authorities regarding the material delivered there and for paying any dumping fees. The Contractor shall not dispose of the demolition material on the project site. The Contractor shall also provide the COR with documentation verifying the material has been properly disposed.
2.1.3.7 EARTHWORK
The Contractor shall perform all earthworks necessary to provide compatible surface elevations and slopes, and laying of utility lines (as required).
Surplus excavated material not required for fill shall be disposed of offsite at approved dump sites, and shall be the responsibility of and at the expense to the Contractor.
September 11, 2019 Page 15 of 17
Control Tests shall be performed on all prepared subgrades in accordance with local codes. The location of all tests shall be selected by the COR or his designated representative, and copies of all test results shall be furnished to the
COR.
2.1.3.8 SITE GRADING
Site grading shall be developed to minimize the amount of earthwork required.
Finished grades adjacent to structures on earth/grass/gravel surfaces will be selected which direct runoff away from structures at 5% for the first 3 meters. Finished grades adjacent structures on paved surfaces will be selected which direct runoff away at 2.0% for the first 3 meters.
2.1.3.9 PAVEMENT FOR RESURFACE HELICOPTER APRON, TAXIWAY, AND LANDING PADS
Pavement design for both asphalt concrete and Portland cement concrete (PCC) pavements shall be performed with PCASE software which is available free of charge and can be downloaded from the following link:
https://transportation.erdc.dren.mil/pcase/software.aspx
The concrete pavement shall be plain concrete (unreinforced).
The design aircraft shall be Sikorsky UH-60 Black Hawk helicopter.
The Contractor shall design and construct the pavement in compliance with the applicable standards, RFP requirements, and in consideration of the results from the geotechnical survey and determined loads. The designer shall also consider the variation in temperature throughout the year in this region. The Contractor shall ensure that the pavements can withstand the shrinkage and expansion effects associated with these temperature variations.
Contractor shall provide compaction tests and pavement density tests, thickness and evenness tests, to the frequency listed in local codes. The location of all tests, and the layers to be tested, shall be selected by the COR, and copies of all test results shall be furnished to the COR.
2.1.3.10 HELICOPTER PAVEMENT MARKINGS FOR RESURFACE HELICOPTER APRON, TAXIWAY,
AND LANDING PADS
The contractor shall provide taxiway and apron markings in accordance with UFC 3-260-04. The painting of marking shall be in accordance with UFGS 32 17 23 Pavement Markings.
2.1.3.11 AIRCRAFT TIE-DOWNS FOR RESURFACE HELICOPTER APRON, TAXIWAY, AND LANDING
PADS
Design and construction of aircraft tie-downs shall be in accordance with ETL 12-8 Contingency Aircraft Tie- Downs in Portland Cement Concrete Pavements.
2.1.3.12 UTILITIES – GENERAL
The Contractor shall verify the specific location, depth, capacity and condition of the existing utilities impacted by each project.
The COR shall be notified of any utility lines found to be missing from or incorrectly shown on any existing plans showing existing conditions and made available to the Contractor. Any indication of existing utility lines on such plans shall not mean the existence, location, depth and/or alignment of the lines is accurately represented. The Contractor shall protect those lines that are to be kept in operation.
https://transportation.erdc.dren.mil/pcase/software.aspx
September 11, 2019 Page 16 of 17
2.1.3.13 STORM DRAINAGE
The Contractor shall take maximum advantage of connecting to existing drainage patterns and systems to ensure the likelihood of ponding based on a 10-year return storm frequency is minimized. To ensure proper drainage, the design build contractor shall perform a camera survey of all storm water drain lines prior to 35% design submittal.
Any storm drainage line in the existing system that is damaged or consider in to poor/unusable condition shall be reported to the COR immediately. The COR will provide direction for corrective actions.
The facilities shall be provided with positive surface slope so that rainfall runoff does not collect adjacent or seep into the ground in the vicinity of structures and associated facilities. In other words, roof drainage shall be coordinated with storm water drainage so that water from roofs does not collect on or seep into the ground adjacent or beneath structures.
2.2 GEOTECHNICAL
The Contractor shall be responsible for conducting a geotechnical investigation of the project limits and shall provide an assessment regarding all geotechnical data required for the design and construction of the planned facilities and features. The following additional requirements apply as described in sections 2.2.1 through 2.2.3.
2.2.1 DESIGN CERTIFICATION
The Contractor and their professional geotechnical engineer consultant shall certify in writing that the design of the projects has been developed consistent with the Contractor’s Final Geotechnical Report. The certification shall be stamped by the consulting professional geotechnical engineer and shall be submitted with the first design submission. If revisions are made to the initial design submission, a new certification shall be provided with the final design submission.
2.2.2 GEOTECHNICAL INVESTIGATION
The Contractor is required to investigate subsoil conditions at the proposed location of buildings, structures, pavements, etc. as far as required per applicable codes and standards, the contractor shall perform borings validating the soil is suitable for the design and construction of the intended facilities.
2.2.3 GEOTECHNICAL REPORT
The investigation shall be performed and the report shall be provided to the COR prior to finalizing design features that are dependent upon soil condition and characteristics. The report will be provided for review at the first design submittal. The contractor shall use the data from this investigation to provide bearing capacity analyses and settlement calculation, if necessary lateral earth pressure parameters general soil conditions, compaction requirements, fill requirements and soil percolation rates.
As well as more general information, the geotechnical report shall specifically address the following:
- It shall clearly describe the subsurface conditions and the regional geology and seismic conditions at the site.
- It shall also recommend any soil replacement or improvement requirements for earthworks, general fill and backfill placement procedures, and types of compaction equipment to be used.
- It shall recommend the type of foundation structure to be used. It shall also provide, as applicable, recommendations for soil replacement or soil improvement under structures and compaction requirements for soil preparation under structures.
Based on the findings, the contractor shall provide evaluation of the most appropriate rainwater drainage features in compliance with the applicable standards and in consideration of low maintenance exigency. If the evaluation should identify that existing drainage features are incompatible with the applicable standards, the contractor shall
September 11, 2019 Page 17 of 17 plan for replacing them. The report shall compile information in sufficient detail to enable an engineer to satisfactorily design new rainwater drainage systems.
3.0 ARCHITECTURAL
The concrete walkway around the perimeter of the building will be demolished and a new concrete walkway will be constructed.
4.0 STRUCTURAL DESIGN
This section is not applicable for the two projects listed herein at Novo Selo Training Area, Bulgaria.
5.0 ELECTRICAL & COMMUNICATIONS FOR RESURFACE HELICOPTER APRON, TAXIWAY, AND
LANDING PADS
Contractor shall complete resurfacing without damaging existing electrical communication lines. Based on as-built drawings, it appears the conduit crossing is approximate 2 m below the existing surface.
Contractor shall verify location and depth of conduit prior to commencement of work. If any conduit is found with the work area the contractor shall inform the Contracting Officer or COR and request direction on how to proceed.
The Contractor shall install grounding and lightning protection systems in support of the rotary wing apron. A lightning protection system shall be provided and be connected to the grounding system.
Contractor shall apply UFC 3-550-01 for general grounding system requirements.
See Airforce Static Ground Detail in Attachment B-1-EDI-NSTA-051- Resurface Rotary Wing Apron Drawings-E-
01. Apply UFC 3-550-01 for general grounding system requirements.
6.0 MECHANICAL DESIGN
The existing fire hydrants on the Helicopter apron will remain in place. The contractor will either pave to the same existing elevation of the fire hydrant or extend the fire hydrants height.
7.0 FIRE PROTECTION
This section is not applicable for the two projects listed herein at Novo Selo Training Area, Bulgaria.
Attachments Appendix UFC 1-300-09N Design Procedures
Attachment - EDI-NSTA 350 M Moving Armor Target (MAT) Access Road Drawings
Attachment - EDI-NSTA Resurface Rotary Wing Apron Drawings
Attachment – NSTA, Bulgaria – Helicopter Apron As-Built Drawings 22MAY17
| 1.0 GENERAL |
| 1.2.1 350-Meter Moving Armor Target (MAT) Access Road |
| 2.0 CIVIL AND GEOTECHNICAL |
| 4.0 STRUCTURAL DESIGN |
| 5.0 ELECTRICAL & COMMUNICATIONS FOR RESURFACE HELICOPTER APRON, TAXIWAY, AND LANDING PADS |
| 6.0 MECHANICAL DESIGN |
| 7.0 FIRE PROTECTION |
| Attachments |