This document is an Amendment (0003) to a federal solicitation for a Lock & Dam 7 Outdraft Modification project. The amendment updates Wisconsin wage rates to 23 May 2025, replaces three plan sheets (G-003, C-305, & C-317), and adds a website for USACE Hydrographic Surveys. The contract requires the contractor to use a commercially available electronic system for processing Davis-Bacon Act certified payrolls, with specific functional criteria including compatibility with Excel, data security, and the ability to generate record copies.
The solicitation is a small business set-aside for construction work with a project value between $5-10 million, classified under NAICS code 237990. The contract involves constructing a mooring cell and mooring dolphin for navigation efficiency. Key requirements include maintaining radio communications, complying with safety regulations, following specific insurance requirements, and adhering to wage determinations for Illinois, Wisconsin, and Minnesota. The amendment also outlines procedures for time extensions due to unusually severe weather, using historical meteorological data from La Crosse Regional Airport.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section 00 73 00 - Supplementary Conditions
Miscellaneous text in this section has been modified to:
CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR PROCESSING DAVIS
BACON ACT CERTIFIED PAYROLLS
a. The contractor will use a commercially available electronic system to process and submit certified payrolls electronically to the Government. The Davis-Bacon Act establishes the requirements for preparing, processing, and providing certified labor payrolls.
b. The contractor shall be responsible for obtaining and providing access for all licenses and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis- Bacon Act and related statutes. When the contractor uses an electronic Davis-Bacon Act payroll service, it shall be used to prepare, process, and maintain the relevant payrolls and basic records for all work under the construction contract. The electronic payroll service shall be capable of preserving the payroll and related basic records for the required three years after contract completion. The contractor shall obtain and provide electronic system access including electronic review to the Government, as required to comply with the Davis- Bacon Act and related statutes through the duration of the construction contract.
c. The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria:
(1) commercially available;
(2) compliant with appropriate Davis-Bacon Act payroll provisions in the FAR;
(3) able to accommodate the required number of employees and subcontractors that will be employed under the contract;
(4) capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records for export into an Excel spreadsheet to be imported into the contractor's mode of Resident Management System 3.0;
(5) demonstrated security of data and data entry rights;
(6) able to produce contractor-certified electronic versions of weekly payroll data;
(7) able to identify erroneous entries and track the date/time of all versions of the certified Davis-Bacon Act payrolls submitted to the government over the life of the contract; and
(8) capable of generating a durable record copy in a Compact Disc (CD) or Digital Versatile Disc (DVD) and Portable Document Format (PDF) file record of data from the system database at the end of the contract closeout. This durable record copy of data from the electronic payroll processing system shall be provided to the Government during contract closeout.
d. All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.
W912ES25BA0010003
PARTNERING
The Government proposes to form a partnering relationship with the contractor. This partnering relationship will strive to facilitate communication and draw on the strengths of each organization in an effort to achieve a quality project, within budget, and on schedule. Participation will be totally voluntary.
Partnering will not alter or supersede any provision of this contract, nor will it provide either party with any additional contractual rights or obligations. Participation in partnering will not affect award of this contract. Any cost associated with this partnering will be agreed to by both parties and will be shared equally, with no change in contract price.
BIDDER'S QUALIFICATIONS
Before a bid is considered for award, the bidder may be requested by the Government to submit a statement regarding their previous experience in performing comparable work, their business and technical organization, financial resources, and plant available to be used in performing the work.
ALL OR NONE QUALIFICATIONS
A vendor must provide a price on all items in this solicitation to be eligible for award. The Government will award on an "All or None" basis. Evaluation of bids/offers will be based upon only the total price included on the pricing schedule for all items. If options are included in the pricing schedule the evaluation will be conducted in accordance with the applicable option clause in the solicitation.
REQUIREMENT FOR BID GUARANTEE
Each bidder shall submit with its bid a Bid Bond (current version of Standard Form 24) with good and sufficient surety or sureties acceptable to the Government or other security as provided in the clause BID GUARANTEE in the form of twenty percent (20%) of the bid price or $3,000,000 whichever is lesser.
The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents.
INVOICE PROCEDURES
In accordance with CONTRACT CLAUSE titled "PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS", the contractor shall submit invoices as follows:
a. In order to qualify for a periodic payment, the Contractor must submit a proper invoice (request for payment) to the Contracting Officer's Representative (COR) and a determination must be made that supplies or services conform to the contract requirements. This determination will be made for the sole purpose of processing progress payments and will not constitute formal acceptance. The due date for making progress payments shall be as stated in the contract clause: PROMPT PAYMENT FOR
CONSTRUCTION CONTRACTS.
b. The submitted request for payment must be accompanied with documentation adequate to substantiate the amount requested. Substantiation shall be consistent will the clauses in the solicitation titled Quantity Surveys, Purchase Orders, Invoices, etc. satisfactory to the COR.
c. The Contractor must also include with the payment request a certification as described in the Clause
"PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS".
d. Payment requests will be reviewed for propriety by the COR. Defective invoices will be returned to the Contractor for resolution with defects identified. Along with the returned invoice, the COR may include, at its option, an ENG FORM 93-PAYMENT ESTIMATE reflecting the substantiated and uncontested payment amount. The Contractor will then be given the option of signing and returning the FORM 93 for payment along with the original invoice and certification or resubmitting a revised invoice and certification. To expedite payment, the Contractor may request in writing that the COR retain the defective invoice and immediately process the payment request at the amount determined to be acceptable to the Government.
WORK PERFORMED BY THE CONTRACTOR
The successful bidder must furnish the Contracting Officer within 10 days after the award, the items of work which he will perform with their own forces, the percentage of the total work this represents, and the estimated cost thereof.
UNAVAILABILITY OF UTILITY SERVICES
The responsibility shall be upon the Contractor to provide and maintain at its expense, adequate utilities for its use for construction and domestic consumption, and to install and maintain necessary connections and lines for same, but only at such locations and in such manner as may be approved by the Contracting Officer. Before final acceptance, temporary connections and lines installed by the Contractor shall be removed in a manner satisfactory to the Contracting Officer.
SAFETY AND HEALTH REQUIREMENTS MANUAL INTERIM CHANGES, EM 385-1-1
This paragraph applies to contracts and purchase orders that require the contractor to comply with EM 385-1-1 (e.g., contracts that include the Accident Prevention clause at FAR 52.236-13 and/or other safety provisions). EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/Portals /76/Publications/EngineerManuals/EM_385-1-1.pdf. The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
BASIS FOR SETTLEMENT OF PROPOSALS
"Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under FAR 49.206-2(b). In evaluating a terminations settlement proposal using the total cost basis, the following principles will be applied to determine allowable equipment costs:
(1) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.
(2) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.
(3) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.
(4) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of FAR 31.205-11).
(5) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate."
APPARENT CLERICAL MISTAKES
(a) For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:
(1) Obviously misplaced decimal points will be corrected;
(2) Discrepancy between unit price and extended price, the unit price will govern;
(3) Apparent errors in extension of unit prices will be corrected;
(4) Apparent errors in addition of lump sum and extended prices will be corrected.
(b) For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends it's bid to be evaluated on the basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.
EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
(a) This clause does not apply to terminations. See 52.249-5000, Basis for Settlement of Proposals and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region [insert Roman numeral for the appropriate region of the schedule]. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-
36. Rates for equipment rented from an organization under common control, lease purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.
S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
- U.S. Department of Labor Veterans' Employment and Training Service (VETS): https://www.dol.gov /vets/
- Federal Veteran Employment Information: https://www.fedshirevets.gov/
- Veterans Opportunity to Work (VOW) Program: https://www.benefits.va.gov/vow/
- U.S. Army Warrior Transition Command Employment Index: https://wct.army.mil/modules/employers /index.html
- Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes
INSURANCE
As referenced in Contract Clause: INSURANCE--WORK ON A GOVERNMENT INSTALLATION, the following types and amounts of insurance are required under this contract.
Type Amount
Worker's Compensation and Employer's Liability Insurance:
Coverage A Compliance with States of Illinois, Minnesota and Wisconsin Worker's Compensation Worker's Compensation Law
Coverage B $ 100,000 Employer's Liability
General Liability Insurance:
Bodily Injury $1,000,000 per occurrence Property Damage Not Required
Automobile Liability Insurance (Comprehensive Policy Form):
Bodily Injury $500,000 per person and $1,000,000 per occurrence Property Damage $100,000 per occurrence
FLOATING PLANT EQUIPMENT
When mechanized equipment is operated on floating plant, the contractor shall provide positive and acceptable means of preventing this equipment from moving or falling into the water. The type of equipment addressed by this clause includes front-end loaders, bulldozers, trucks (both on and off-road), backhoes, track hoes, and similar equipment. If the Contractor plans to use such equipment on floating plant, an activity hazard analysis must be developed for this feature of work. The plan must include a detailed explanation of the type or types of physical barriers, curbs, structures, etc., which will be incorporated to protect the operator and prevent the equipment from entering the water. Nonstructural warning devices may be considered for situations where the use of structural barriers is determined to be impracticable. The activity hazard analysis must thoroughly address the procedure and be submitted to the U.S. Army Corps of Engineers for review and acceptance prior to start of this feature of work.
OBSTRUCTION OF CHANNEL
The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the Provisions of Section 7 of the River and Harbor Act approved August 8, 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible. The Contractor shall consult with the appropriate Coast Guard office to determine whether a Notice to Mariners will need to be issued for construction-related activities that might interfere with navigation or be interfered with by such navigation. (Point of Contact: Sector Upper Mississippi River, St. Louis, Missouri, 24 hour #314-269-2332). If the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon the completion of the work the Contractor shall promptly remove their plant, including ranges, buoys, piles, and other marks placed by them under the contract whether in navigable waters or on shore.
SIGNAL LIGHTS
The Contractor shall display signal lights and conduct their operations in accordance with the General Regulation of the Department of the Army and the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels or floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard instruction M16672.
2B, navigation rules: International-Inland (COMDTINST) M16672.2B, or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR (Inland) as applicable.
RADIO
The Contractor shall maintain a staff that is knowledgeable about radio communications to advise oncoming navigation of appropriate passing directions while the Contractor's floating plant is in the navigation channel. In particular, the Contractor shall monitor Marine Band Channel 13 for commercial navigation and Channel 16 for emergency communication.
General security requirements and guidance The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
Physical security and access control requirements All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation /facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.
Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.
Escorting in classified and/or sensitive areas
In accordance with applicable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.
Pre-screen candidates using E-Verify Program Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.
gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/ eligible candidates shall be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
Applicable Wage Decision The terms "dredging" and "dredging equipment" are defined for the purpose of providing the Contractor with guidance as to which Davis-Bacon Act wage determination applies to various portions of the project work. The Davis-Bacon Wage Decision entitled L20250018 Dredging shall apply to all "dredging" as I that term is defined below. The Davis-Bacon Wage Decisions MN20250236 and WI20250015 shall apply to all contract work that is not "dredging" as that term is defined below. Wage Decisions IL20250018, MN20250236, and WI20250015 are incorporated into this solicitation. Definitions
A. "Dredging" is defined as the excavation of material from the confines of a water body and its transportation to a designated placement site by the use of dredging equipment.
B. Hydraulic "dredging equipment" consists of the dredge, its attendant plant and the pipeline (including booster pumps, both floating and land based) used to excavate material and transport the dredged slurry to the disposal site or sites.
C. Mechanical "dredging equipment" consists of a clamshell, dragline, backhoe, bucket ladder or other suitable floating plant and the barges and tenders used to transport the dredged spoil to shore.
D. Dredging equipment does not include land-based equipment used for attending disposal areas or off-loading barges at the placement site. The contractor shall segregate the work performed under each wage determination on its payrolls. In the event that it is impracticable to segregate an employee's work, or in the event of a conflict as to the place of performance of that work, the wage classification (and rate) resulting in the highest rate of pay / fringe benefits to that employee will apply.
DAVIS-BACON WAGE DETERMINATION - CONFLICTING SCHEDULES -- , Wisconsin & Illinois Minnesota
Work under this contract will be performed in , Wisconsin and Minnesota. Wage determinations Illinois for , Wisconsin and Minnesota are incorporated into this contract. Some work under this contract Illinois may require members of the contractor's work force to perform work in both states. The contractor shall segregate the work performed in each state and under each wage determination on its payrolls. In the event that it is impracticable to segregate an employee's work, or in the event of a conflict as to the place of performance of that work, the wage classification (and rate) resulting in the highest rate of pay/fringe benefits to that employee will apply.
TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the CONTRACT CLAUSES: DEFAULT (FIXED-PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The weather station selected for this analysis was La Crosse Regional Airport, WI US and used a period of record of the past 10 years (2014 - 2023). Data shown is for precipitation of 0.1 inch or more and maximum daily temperatures less than 32 degrees Fahrenheit. The actual numbers have been multiplied by 6/7 to account for the workweek. The contractor's progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities.
c. MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORKDAYS BASED ON (6) DAY WORKWEEK.
Month JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Days 17 14 7 6 7 7 6 5 6 4 5 12
d. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled workday. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair-weather workdays, and issue a modification in accordance with the
CONTRACT CLAUSES: DEFAULT (FIXED-PRICE CONSTRUCTION).
USACE Hydrographic Surveys https://www.arcgis.com/apps/dashboards/4b8f2ba307684cf597617bf1b6d2f85d
Section 01 00 00 - General Requirements
Miscellaneous text in this section has been modified to:
Construction Wage Rates:
MN20250236 from 2 May 2025
WI20250015 from 23 May 2025
IL20250018 from 3 Jan 2025
| IDCode: J |
| Page: 1 |
| Pages: 10 |
| AmendNo: 0003 |
| EffDate: 29 MAY 2025 |
| ReqNo: |
| ProjNo: P2 511276 |
| IssCode: W912ES |
| AdmCode: |
| IssuedBy: W07V ENDIST ST PAUL |
KO CONTRACTING DIVISION, 332 MINNESOTA STREET SUITE 1500
SAINT PAUL, MN 55101-1323
UNITED STATES
JUSTIN ROSE, EMAIL: JUSTIN.H.ROSE@USACE.ARMY.MIL TELEPHONE: 651 290-5422
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W912ES25BA001 |
| SolDate: 05 MAY 2025 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: THE PURPOSE OF THIS AMENDMENT IS TO: UPDATE THE WISCONSIN WAGE RATES TO 23 MAY 2025; UPDATE / REPLACE THREE PLAN SHEETS (G-003, C-305, & C-317) AND ADD ONE ADDITIONAL PLAN SHEET (C-320) FOR MORE INFORMATION; AND ADD A WEBSITE FOR USACE HYDROGRAPHIC SURVEYS. |
| ContNameTitle: |
| CoNameTitle: SHARON M. FRANK-SCHEIERL |
| ContDate: |
| CODate: 29 MAY 2025 |
File details come from the government source that posted it. Updated .