Amendment 0002 Spec change 1.pdf

PDF 35 KB Posted

Attached to
Lock & Dam 7 Outdraft Modification
Solicitation number
W912ES25BA001
Issued by

About this file

This document is a specification amendment (Specification 01 14 00.00 13, paragraph 1.3.4) addressing loading dock and river access details for the Lock & Dam 7 Outdraft Modification project. The specification outlines shared use requirements for the loading dock and parking lot, with the contractor required to keep the area clear of equipment and materials and be prepared to vacate within 24 hours of government notice. The government anticipates specific dates (22 July, 24 July, 29 July, and 31 July) for miter gate replacement, though these dates are subject to change.

For river access at the LD7 loading dock, the contractor must provide a 30-day notice to the Contracting Officer for approval, with the government providing a 100-foot wide, 9-foot deep channel. The loading dock and river access may be utilized by multiple contractors and the government, necessitating coordination with the Contracting Officer. This specification is part of a small business set-aside contract valued between $5 million and $10 million for the Department of the Army Corps of Engineers Engineering District St. Paul.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specification 01 14 00.00 13, paragraph 1.3.4, Loading Dock and River Access

Loading Dock and River Access

The loading dock, and the lane through the parking lot accessing the loading dock, may be used by the Contractor and will be a shared use area with the Government and other potential Contractors. The shared lane through the parking lot must remain clear of equipment and materials. The loading dock and/or the parking lot must be cleared within 24 hours of notice from the Government.

Anticipated Government needs are 22 July, 24 July, 29 July, and 31 July for the purpose of miter gate replacement. These dates are subject to change.

If the Contractor chooses to use the loading dock at LD7 for river access, provide the Government a 30-day notice for approval by Contracting O icer before intended use. The Government will provide a 100ft wide channel 9ft deep to the loading dock.

The LD7 loading dock and river access may be utilized by multiple Contractors and the Government. Coordination with the Contracting O icer will be required.