LD7OD_RTA_SPECS.pdf

PDF 5 MB Posted

Attached to
Lock & Dam 7 Outdraft Modification
Solicitation number
W912ES25BA001
Issued by

About this file

This document is a comprehensive solicitation for the Lock & Dam 7 Outdraft Modification project, detailing construction requirements for modifying an existing rock weir at Lock and Dam No. 7, located near La Crescent, Minnesota. The project involves notching and modifying the existing rock weir constructed between 2018-2020, with work to be performed upstream of the existing structure along the Mississippi River. The construction will include creating a dog-leg weir structure approximately 725 feet in length, with three notches at the downstream end to facilitate sand movement and improve navigation efficiency.

The solicitation (W912ES25BA001) is a small business set-aside contract with an estimated value between $5-10 million, classified under NAICS code 237990 with a small business size standard of $45 million. The work will be executed by the U.S. Army Corps of Engineers St. Paul District and is scheduled for completion by May 2025. Key technical requirements include constructing a weir with a top elevation of LCP+1, a 5-foot wide top, side slopes of 4H:1V for the top 3 feet and 3H:1V for the remainder, and notches at the bottom with an elevation of LCP-12. The project aims to mitigate the outdraft current that makes lock navigation challenging for vessels traveling in both directions.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. W912ES25BA001

Lock & Dam 7 - Outdraft Modification Mississippi River

Lock & Dam 7 La Crescent, Minnesota

CONSTRUCTION

DOCUMENTS

FOR

May 2025

US Army Corps of Engineers Saint Paul, MN

Lock & Dam 7 - Outdraft Modification W912ES25BA001

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 13 GENERAL

01 11 00 SUMMARY OF WORK

01 14 00.00 13 WORK RESTRICTIONS

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20.00 13 ENVIRONMENTAL PROTECTION

01 58 00 PROJECT IDENTIFICATION

01 71 23.05 13 CONTRACTOR SURVEYS

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING/UNDERWATER EXCAVATION

35 20 23.40 13 PLACEMENT OF EXCAVATED MATERIAL

35 31 19.00 13 STONE PROTECTION (RIPRAP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00.00 13

GENERAL

PART 1 GENERAL

1.1 ORGANIZATION OF SPECIFICATIONS

1.2 USE OF REFERENCES

1.3 SUBMITTALS

1.4 GOVERNMENT OPERATIONS

PART 2 PRODUCTS

2.1 RECYCLED/RECOVERED MATERIALS

PART 3 EXECUTION

3.1 DISPOSAL OF DEBRIS AND WASTE

3.1.1 Burning

3.1.2 Disposal offsite for useful purposes

3.1.3 Disposal in a locally operated sanitary landfill

3.1.4 Disposal of Solid Construction Debris and Waste

3.2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, FACILITIES, AND

VEGETATION

3.2.1 Preconstruction and Postconstruction Condition Survey

3.2.2 Preconstruction and Postconstruction Condition Survey Reports

3.3 SCHEDULING

3.3.1 General

3.3.2 Notification

3.3.3 Government Operations

3.3.4 Lock and Dam Operations

3.3.5 Notification of U.S. Coast Guard Prior to Beginning of Work and Completion of Work

3.3.6 Dredging Operations

3.4 Local Emergency Responders

3.5 OTHER CONTRACTS

3.5.1 List other contracts

3.6 OTHER WORK

-- End of Section Table of Contents --

04/30/25 SECTION 01 00 00.00 13 Page 1

SECTION 01 00 00.00 13

GENERAL

PART 1 GENERAL

Work on this contract includes but not limited to notching and modifying the existing rock weir, constructed from 2018 to 2020, upstream of the river wall. This work will construct an additional portion upstream of the existing weir at Lock and Dam No. 7 (LD7) in accordance with contract drawings and specifications. Lock and Dam No. 7 is located on the right bank of the Mississippi River in Winona County, Minnesota, approximately

2.4 miles upstream of La Crescent, Minnesota.

1.1 ORGANIZATION OF SPECIFICATIONS

The specifications which govern the materials and equipment to be furnished and the work to be performed under this contract are listed in the Table of Contents. No attempt has been made in the specifications to segregate work to be performed by any trade, craft, or subcontractor. Any segregation between the trades or crafts must be solely a matter for agreement between the Contractor, Contractor's employees, and subcontractors.

1.2 USE OF REFERENCES

Reference to the standards, specifications, or codes of any technical society, organization, or association, or local, State, or Federal authority must mean the specific edition or revision listed.

Various publications are referenced in other sections of the specifications to establish requirements for the work. Any referenced publication is to be used solely for technical requirements. Measurement and payment and any other matters respecting the administration of this contract must be governed by the terms of this contract without considering any referenced publication. These references are identified in each section by document number, date and title. The addresses, phone numbers, and Internet addresses (if available) for references cited in these specifications are listed in the Unified Facilities Guide Specification: UFGS 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS. The UFGS 01 42 00 is available on the TECHINFO page of the Corps of Engineers Huntsville District Internet site:

http://www.hnc.usace.army.mil/Missions/Engineering-Directorate/TECHINFO/ .

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Preconstruction Condition Survey Report; G, SURV

Disposal Site

04/30/25 SECTION 01 00 00.00 13 Page 2

Coast Guard Notifications

SD-11 Closeout Submittals

Post Construction Condition Survey Report; G, SURV

1.4 GOVERNMENT OPERATIONS

The roller gates are anticipated to be pulled up out of the water at approximately 82,000 cubic feet / second (CFS) as flooding may occur.

River flow rates are reported on the following website:

https://www.mvp-wc.usace.army.mil/. Contractor must include USACE calculated flow information on all Contractor Quality Control daily reports.

PART 2 PRODUCTS

2.1 RECYCLED/RECOVERED MATERIALS

Government procurement policy is to acquire, in a cost effective manner, items containing the highest percentage of recycled and recovered materials practicable consistent with maintaining a satisfactory level of competition without adversely affecting performance requirements or exposing suppliers' employees to undue hazards from the recovered materials. The Environmental Protection Agency (EPA) has designated certain items which must contain a specified percent range of recovered or recycled materials. EPA designated products specified in this contract comply with the stated policy and with the EPA guidelines. A list of EPA designated products can be found at https://www.epa.gov/greenerproducts/recommendations-specifications-standards-and-ecolabels-federal-purchasing .

The Contractor must make all reasonable efforts to use recycled and recovered materials in providing the EPA designated products and in otherwise utilizing recycled and recovered materials in the execution of the work.

PART 3 EXECUTION

3.1 DISPOSAL OF DEBRIS AND WASTE

The Contractor's attention is directed to Section 01 57 20.00 13 ENVIRONMENTAL PROTECTION and to the following CONTRACT CLAUSES: 52.236-7

PERMITS AND RESPONSIBILITIES; 52.236-9 PROTECTION OF EXISTING VEGETATION,

STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS; 52.236-10 OPERATIONS

AND STORAGE AREAS; and 52.236-12 CLEANING UP.

Debris or waste must not be left on the site.

3.1.1 Burning

Burning will not be permitted at the project site.

3.1.2 Disposal offsite for useful purposes

In the interest of conservation, it is required that Contractors make a reasonable effort to dispose of the material offsite for some useful

04/30/25 SECTION 01 00 00.00 13 Page 3 purpose. For example, cut timber into convenient lengths and utilized for saw logs, posts, cordwood, wood chips, paper making or other uses.

3.1.3 Disposal in a locally operated sanitary landfill

Select the disposal site with the approval of the Contracting Officer.

Secure the required permits for disposal and provide copies of the permit to the Contracting Officer.

3.1.4 Disposal of Solid Construction Debris and Waste

Remove and dispose of solid construction debris and waste in compliance with Federal, State, and local requirements for solid waste disposal.

Select the disposal site(s) with the approval of the Contracting Officer.

3.2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, FACILITIES, AND

VEGETATION

Multiple Contractors will utilize the loading dock and the access road to the loading dock.

If the LD7 facilities are utilized by the Contractor, document existing conditions and any changes that occur over the contract duration in accordance with the following paragraphs.

3.2.1 Preconstruction and Postconstruction Condition Survey

Prior to commencement of operations, make a detailed survey of all existing structures, staging and parking areas, roadways, boat landings, and other facilities that may affect construction operations. Conduct the survey with the Contracting Officer and submit documentation describing findings of concern. Survey sufficiently in scope to provide advance agreement among all concerned as to the condition of the existing structures, Contractor staging and parking areas, roadways, boat landings, embankments, utilities, bridges, culverts or water control structures under access roads, boat ramps, and other facilities.

After completion of the work, and prior to final acceptance of the work, make a detailed post-construction condition survey of the same structures, Contractor staging and parking areas, roadways, boat landings, embankments, utilities, bridges, culverts or water control structures under access roads, boat ramps, and other facilities previously surveyed with the Contracting Officer, and obtain signatures from both parties.

Survey sufficiently in scope to provide for agreement among all concerned as to the post-project condition of the existing structures, Contractor staging and parking areas, roadways, boat landings, embankments, utilities, bridges, culverts or water control structures under access roads, boat ramps, and other facilities.

Provide notification to the Contracting Officer a minimum of 14 calendar days prior to performing the pre and post construction condition surveys.

Include, but do not limit the surveys to, photographs, videos, sketches, and written descriptions. Submit all documentation to the Contracting Officer.

If it is determined by the post-construction condition survey that damage has occurred to structures, Contractor staging and parking areas, roadways, boat landings, and other facilities, then repair such damage to

04/30/25 SECTION 01 00 00.00 13 Page 4 a condition equal to the pre-Contract conditions, as approved by the Contracting Officer, at the Contractor's expense.

3.2.2 Preconstruction and Postconstruction Condition Survey Reports

Prepare one electronic file of each Condition Survey Report containing surveys, photographs, and video recordings, sketches and diagrams, field notes taken, descriptions and reports, all signed and witnessed by the persons involved in the survey.

Provide supporting evidence, as a minimum, photographs in full color in a pdf format. The survey report must contain as a minimum a title cover page, a short narrative stating the names of the persons who took the photos, the date the photos were taken, any items of pre-existing damage, and each photo must contain a descriptive caption.

Submit the Preconstruction Condition Survey report prior to mobilization to the Contracting Officer for approval. Submit the Post Construction Condition Survey Report after demobilization to the Contacting Officer for approval.

3.3 SCHEDULING

3.3.1 General

Schedule and execute the work, incorporating the necessary requirements set forth in these specifications. Develop and submit a schedule in accordance with Section 01 32 01.00 10 PROJECT SCHEDULE and CONTRACT

CLAUSE: 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS.

3.3.2 Notification

Inform the Government in writing, at the pre-construction conference, as to which hours of the day and days of the week for which work will be performed. Notify the Government at least 24 hours before work is to be conducted on overtime, in multiple shifts, on weekends, or on Federal Government holidays. Overtime and Holiday work requests must be approved by the Contacting Officer.

3.3.3 Government Operations

Do not interfere with normal lock and dam operations. Government personnel will not accept deliveries, phone calls, or mail or deliver messages for the Contractor.

3.3.4 Lock and Dam Operations

Contractor only has access to the lock during the navigation season. For NON-NAVIGATION SEASONS see 01 14 00.00 13 WORK RESTRICTIONS.

When accomplishing Government contracted work, the Contractor may request and receive priority lockage in either upbound or downbound directions. If a commercial tow boat is already arrived at the upstream and downstream arrival points, this is considered officially on approach to the lock and traffic cannot be requested to stop. For this case, the Contractor can no longer request priority lockage ahead of the commercial tow. If a commercial passenger vessel has requested priority lockage, the Contractor may not request priority lockage ahead of them, but must request priority

04/30/25 SECTION 01 00 00.00 13 Page 5 lockage next after the commercial passenger vessel.

Contractor may request lock stoppage up to 3 hours to accommodate contract work and requests for this action are required to be approved and planned by the Government.

Contractor may request scheduled navigational channel closures to accommodate contract work schedules and requests for this action are required to be approved and planned by the Contracting Officer. The Government may deny requests for navigational channel closures.

3.3.5 Notification of U.S. Coast Guard Prior to Beginning of Work and Completion of Work

At least two weeks prior to beginning work and expected channel closures, the Contractor shall notify the U.S. Coast Guard, Sector Upper Mississippi River, at sumrwaterways@uscg.mil . A copy of the Coast Guard Notifications shall be provided to the Contracting Officer. Also, within one week after the work is complete, the U.S. Coast Guard shall be notified at the same email address. The telephone number for the U.S. Coast Guard is (314) 269-2332

3.3.6 Dredging Operations

The Government has a commitment to maintain a 9 foot navigation channel.

If the Government decides there is risk of towboat grounding, the Contractor's schedule must be adjusted to allow for dredging by others at the area(s) of concern.

3.4 Local Emergency Responders

If the LD7 area is utilized by the Contractor, after Notice To Proceed (NTP) and prior to mobilization, the Contractor must coordinate and schedule a safety walk-through with LD7 staff and local emergency medical services (EMS) that respond to LD7 when 911 is dialed.

For this meeting, provide a minimum of 7 calendar days advance notification to the Contracting Officer.

3.5 OTHER CONTRACTS

The Government may undertake, award, or have other on-going contracts and work in the area of this project. The Contractor must coordinate their work with the other Contractors to prevent delays to this project and interferences with those contracts. The Contractor must expect minor delays and rescheduling due to these other contracts and work.

Coordination must be through the Contracting Officer. The other contracts and work in the area of this project are listed below. These contracts will be considered in accordance to CONTRACT CLAUSE: 52.236-8 OTHER

CONTRACTS.

3.5.1 List other contracts

The other contracts and work in the area of this project includes, but not limited to, those listed below.

Mechanical Unloading IDIQ, Contract No. W912ES22D0010 was awarded to Legacy Corporation of IL.: with base year in 2023 and option years through the 2024-2025 navigation seasons. This contract or a similar

04/30/25 SECTION 01 00 00.00 13 Page 6 contract are anticipated to be in effect during the entire length of the construction project.

Mechanical Dredging IDIQ, Contract No. W912ES24D0008 was awarded to LS Marine, Inc.: with base year in 2024 and option years through the 2025-2028 navigation seasons. This contract or a similar contract are anticipated to be in effect during the entire length of the construction project.

Miter Gates for Lock and Dam 7 are scheduled for installation during the 2025 navigation season. USACE will generally have floating plants and equipment staged at Lock and Dam 7 for approximately 2 weeks preceding installation through 1 week after installation. The miter gate installation will require four (4) scheduled 12 hour closures during which time the lock will be closed to all navigation. In addition to the scheduled lock closures, there is potential for additional closures should any problems arise during miter gate installation.

Recent miter gate installations and associated lock closures in St Paul district occurred 0700-1900 on consecutive Tuesdays and Thursdays. Exact closure dates and times for the Lock and Dam 7 miter gate installation have not yet been determined, but will be communicated with as much advance notice as possible to minimize impacts to navigation.

Lock and Dam No. 7 Mooring Cell and Dolphin will be awarded in a future contract.

Lock and Dam No. 7 End Cell will be awarded in a future contract.

3.6 OTHER WORK

The Contractor must contact the other local units of Government for work they may have going on in the area and coordinate work and schedules to prevent any delays in this contract.

-- End of Section --

04/30/25 SECTION 01 00 00.00 13 Page 7

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.2.3 Sequence of Work

1.3 EXISTING WORK

1.4 LOCATION OF UNDERGROUND UTILITIES

1.4.1 Notification Prior to Excavation

PART 2 PRODUCTS

PART 3 EXECUTION

04/30/25 SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes modifying the existing weir (notching), constructing a new rock weir structure, and incidental related work in accordance with contract drawings and specifications.

1.2.2 Location

The work is located at Lock and Dam No. 7. The exact location is shown on the plans.

1.2.3 Sequence of Work

Work must generally proceed from downstream terminus (STA D 11+15.47) to upstream terminus (STA 2+72.54) such that the three notches are completed first.

1.3 EXISTING WORK

Alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.4 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Verify existing utility locations indicated on contract drawings, within area of work.

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 7 days prior to starting excavation work.

04/30/25 SECTION 01 11 00 Page 2

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

04/30/25 SECTION 01 11 00 Page 3

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00.00 13

WORK RESTRICTIONS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 GROUNDS AND ROADWAYS

1.3.1 Parking

1.3.2 Staging Areas

1.3.3 Lock and Dam No. 7 Site Access

1.3.4 Loading Dock and River Access

1.3.5 High Water

1.3.6 Snow Removal

1.4 WORKING HOURS

1.5 BLASTING

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION

3.1 EXISTING UTILITIES

3.1.1 General

3.1.2 Buried Utilities

3.1.3 Interruption of Services

3.1.4 Minnesota One Call Excavation Notice System

3.2 PROTECTION OF TREES

3.2.1 Restoration of Damaged Trees

3.3 CONTRACTOR PROPOSED BORROW AND DISPOSAL AREAS

3.4 EAGLE NEST EXCLUSION ZONE RESTRICTIONS

3.4.1 Required Bald and Golden Eagle Protection Act Avoidance

Measures

3.5 DEFINED NON-NAVIGATION SEASONS

3.6 FLOATING PLANT

3.6.1 Equipment and Personnel

3.6.2 Navigable Waters

3.6.3 Sewage and Bilge Water Disposal

ATTACHMENTS:

LD7 Truck and Crane Capacities at the Loading Dock

Capacity Chart Examples

04/30/25 SECTION 01 14 00.00 13 Page 1

SECTION 01 14 00.00 13

WORK RESTRICTIONS

PART 1 GENERAL

1.1 REFERENCES

CODE OF FEDERAL REGULATIONS

46 CFR Chapter 1 Sub Q (2024) Equipment, Constructions, and Materials: Specifications and Approval

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Interruption Of Services

1.3 GROUNDS AND ROADWAYS

1.3.1 Parking

Parking is permitted only in the Contractor's staging area. No parking or staging will be allowed on the grass. Coordinate Contractor parking with the Contracting Officer.

1.3.2 Staging Areas

At Lock and Dam No. 7 (LD7) there are optional on-land staging areas shown on the plans. This area will be completely shutdown to public access for the duration of the time the Contractor is mobilized onsite.

The area around the helicopter pad must remain open for the duration of the contract period. Nondestructive use of the indicated areas on drawings is available for storage, parking, staging of contract materials, placement of the Contractor's job trailer, and portable toilet.

The gravel area west of the loading dock may be used for heavy equipment and rock storage. Maintain drainage of the existing drainage channel.

All electrical power to job trailers, land based equipment, and floating plant equipment must be supplied and paid for by the Contractor.

The LD7 Truck and Crane Capacities at the Loading Dock and Capacity Chart Examples are provided as an attachments.

1.3.3 Lock and Dam No. 7 Site Access

The lock staff and Contractors generally use a tandem lock system on the

04/30/25 SECTION 01 14 00.00 13 Page 2 outer security gate to establish and maintain shared access to LD7 and lockdown afterhours. One side of the gate must be left open during daytime work hours Monday-Friday to allow for site package, mail, garbage, and fuel deliveries as well as official Government visitors to the site.

1.3.4 Loading Dock and River Access

The loading dock, and the lane through the parking lot accessing the loading dock, may be used by the Contractor and will be a shared use area with the Government and other Contractors. The shared lane through the parking lot must remain clear of equipment and materials. The loading dock area and/or the parking lot must be cleared within 24 hours if given notice from the Government.

If the Contractor chooses to use the loading dock at LD7 for river access, provide the Government a 30 day notice for approval by Contracting Officer before intended use. The Government will provide a 100ft wide channel 9ft deep to the loading dock.

The LD7 loading dock and river access will be utilized by multiple Contractors and the Government. Coordination with the Contracting Officer will be required.

1.3.5 High Water

Using historic data, the tailwater elevation of 636 feet (mean sea level, vertical datum NAV 88, Geoid 18) occurs when the flow is approximately 70,000 cfs. At this elevation, the water overtops the loading dock. To prevent damage to the loading dock, it will not be available for use once overtopped with water.

In the event of high water affecting the parking lot and gravel areas, the Contractor is responsible to move equipment and material to higher ground as water comes up during flooding or moved to the Contractor's procured alternate storage area at no expense to the Government.

The Contractor is responsible to determine when action is necessary and monitor river flow rates reported on the following website:

https://www.mvp-wc.usace.army.mil/. Contractor must include U.S. Army Corps of Engineers calculated flow information on all Contractor Quality Control daily reports.

The Contractor may use this working river flow rate for scheduling work.

The Contractor is encouraged to investigate the site prior to beginning work to determine if the work can be completed at varying river conditions. Per FAR Clause 52.242-14 Suspension of Work, the Contracting Officer may suspend in-river work if river conditions become a high risk safety hazard. If work is suspended due to flooding, the Contractor may request a time extension per FAR Clause 52.249-10 Default (Fixed-Price Construction)

1.3.6 Snow Removal

The Contractor is responsible for snow removal in the Contractor's access, work, and parking areas, and when using the loading dock.

1.4 WORKING HOURS

The Contractor will generally be restricted to working between the hours

04/30/25 SECTION 01 14 00.00 13 Page 3 of 7:00 am and 5:00 pm Monday through Friday, excluding federal holidays, unless work outside these standard work hours and workdays are approved by the Contracting Officer. If the Contractor wishes to work outside the standard work hours and workdays listed above, the Contractor must submit a written request to the Contracting Officer at least three days in advance.

1.5 BLASTING

Blasting will not be permitted at the project site.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION

3.1 EXISTING UTILITIES

3.1.1 General

The Contractor must coordinate all utility relocation requirements and make payment to the utility companies for all services, fees, and permits required to relocate and reestablish service. The Contractor is responsible for all costs related to protecting existing utilities.

3.1.2 Buried Utilities

Utilities are not known to exist on site. However, prior to commencing excavation, the Contractor must accurately locate all such installations.

The Contracting Officer must immediately be notified if the Contractor damages any existing utility lines not intended to be removed. Repair of damaged utilities shall be in accordance with CLAUSE 52.236-9 PROTECTION

OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS.

3.1.3 Interruption of Services

Utility services must not be interrupted except for brief periods to facilitate cut-ins. The Contractor shall provide temporary service and shall relocate existing utilities as required to construct the work shown and insure uninterrupted service. If interruption of services is unavoidable, the Contractor shall request approval in writing at least 15 calendar days prior to the proposed interruption. This submittal shall fully describe all details of proposed interruption and the reasons why alternatives are not feasible. Information contained in the submittal shall include, but not be limited to, utilities being affected, duration of outage, and any sketches required to support the submittal. The Contractor must further coordinate with the owner of the utility and notify affected consumers at least 10 calendar days in advance of interruption of services. The Contracting Officer will not in general approve proposals which require interruption of services for more than 4 continuous hours.

3.1.4 Minnesota One Call Excavation Notice System

For contract work performed within the State of Minnesota, the Contractor must meet the requirements of Minnesota Statutes, Chapter 216D "Excavation Notice System." The Gopher State One Call notification center telephone numbers are:

04/30/25 SECTION 01 14 00.00 13 Page 4

Twin Cities Metro Area (651) 454-0002 Outstate (800) 252-1166

3.2 PROTECTION OF TREES

Do not operate equipment in vegetated areas outside the work limits.

Measures for tree protection are located in Section 01 57 20.00 13 Environmental Protection.

3.2.1 Restoration of Damaged Trees

Any existing tree designated to be protected that is damaged by the Contractor's operations must be replaced. Trees will be considered damaged if the critical root zone in cohesive soils is compacted, if there are significant wounds that could contribute to rot, or if distress (evident by reduced growth or other observations of distress documented by a forester) is observed prior to closing the contract. Trees must be replaced in kind on a caliper inch per caliper inch basis (DBH) (e.g. one 6-inch red oak must be replaced with two 3-inch red oaks, three 2-inch red oaks, or six 1-inch red oaks). Replacement tree size and location will be determined and staked by the Contracting Officer. Repair by pruning, aeration, soil conditioning, or other recommendation from a qualified forester will be considered by the Contracting Officer for substitution for replacement.

3.3 CONTRACTOR PROPOSED BORROW AND DISPOSAL AREAS

Any borrow and/or disposal sites proposed by the Contractor that are not already identified by the Government as approved for this project are subject to approval by the Contracting Officer. This approval process may require the Government to prepare an environmental assessment at no cost to the Contractor. This may require additional review time and may result in additional requirements to offset environmental effects associated with the use of the site. Proposed sites which involve the excavation or placement of material within a cultural site, wetland, wooded area, floodplain, or other environmentally sensitive area will not be approved.

3.4 EAGLE NEST EXCLUSION ZONE RESTRICTIONS

Active eagle nests may be present in the project area. Prior to the start of the construction season, the Government will conduct eagle nest surveys for the project area with assistance from the U.S. Fish and Wildlife Service. If a nest or nests are determined to be active within the project area the Contracting Officer will notify the Contractor.

3.4.1 Required Bald and Golden Eagle Protection Act Avoidance Measures

If nests at nearby locations are determined to be active or if additional active nests are identified within the project area, the Contractor will notify the Contracting Officer.

Contractor's activities near any active eagle nest must comply with the avoidance measures of the Bald and Golden Eagle Protection Act (16 U.S.C.

668-668c) as follows:

(1) Maintain a buffer, identified as the eagle nest exclusion zone, of at least 660 feet (200 meters) between project construction activities and any active nest.

04/30/25 SECTION 01 14 00.00 13 Page 5

(2) Restrict all project construction activities within 660 feet of any identified active eagle nest to outside the nesting season (i.e., outside nesting season is from mid-July through mid-January in the Midwest). The Government will determine when nesting activity has ended (i.e., eaglets have fledged) and will notify the Contractor.

Upon notification, the Contractor may immediately proceed with construction activities within the eagle nest exclusion zone.

(3) Maintain established landscape buffers that screen the activity from eagle nests.

3.5 DEFINED NON-NAVIGATION SEASONS

Contractor only has access to the lock during the navigation season.

Locks will be closed and opened to navigation as follows: Historically, navigation is closed during the months of Dec, Jan & Feb. Opening in the spring has been typically between 1 to 15 March. For scheduling and planning purposes, assume the Locks will be closed to navigation from 10 December to 10 March.

3.6 FLOATING PLANT

3.6.1 Equipment and Personnel

Floating plant and personnel must comply with the applicable U.S. Coast Guard regulations and licensing requirements. Floating plant equipment must meet the applicable requirements of 46 CFR Chapter 1 Sub Q .

The Contractor may moor barges and floating plant equipment along the west edge of the LD7 downstream guide wall, but is responsible to move their equipment elsewhere at the Contractors expense in the event that the guide wall is overtopped with flood water. This area is shown on the drawings.

The Contractor may moor floating plant equipment at the loading dock when not coordinating shared use with the Government or other Government Contractors as outlined above.

3.6.2 Navigable Waters

Floating vessels operating on the Mississippi River and its tributaries must be operated in accordance with Title 33 Chapter II Part 207, 207.300 "Ohio River, Mississippi River above Cairo, Ill., and their tributaries;

use, administration, and navigation."

3.6.3 Sewage and Bilge Water Disposal

The Contractor's methods for disposal of sanitary sewage, and bilge water accumulated aboard floating plant, must meet applicable local, State, and Federal requirements.

Attachments:

LD7 Truck and Crane Capacities at the Loading Dock, 1-page

Capacity Chart Examples, 1 page

04/30/25 SECTION 01 14 00.00 13 Page 6

Lock and Dam #7 Truck & Crane Capacities at the Loading Dock

Examples for use of the Capacity Chart

1. Water Level at EL 632.00

a) Read across to Max Truck Weight curve Read down to find allowable truck gross weight of 75.5 tons if situated along dock edge

2. Water Level at EL 632.00

a) Read across to Crane Along Edge curve Read down to find allowable crane gross weight of 81 tons if situated along dock edge

3. Water Level at EL 632.00

a) Read across to Crane 10 feet away from edge Read down to find allowable crane gross weight of 132.5 tons if situated 10 feet from dock edge

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 REFERENCES

1.2 COMPENSATION

1.3 APPROVAL OF MATERIALS OR ALTERNATES

1.4 QUANTITY SURVEYS

1.5 MEASUREMENT BY WEIGHT

1.5.1 Truckload or Railcar

1.5.2 Barge Load

1.5.2.1 Barge Data, Sketch, and Calculations

1.6 REMEASUREMENT

1.7 MEASUREMENT UNITS

1.8 SUBMITTALS

1.9 JOB PAYMENT ITEMS

1.9.1 BONDS (Performance and Payment)

1.9.1.1 Payment

1.9.1.2 Unit of Measure

1.10 UNIT PRICE PAYMENT ITEMS

1.10.1 EXCAVATED MATERIAL

1.10.1.1 Payment

1.10.1.2 Measurement

1.10.1.3 Unit of Measure

1.10.2 RIPRAP

1.10.2.1 Payment

1.10.2.2 Measurement

1.10.2.3 Unit of Measure

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

04/30/25 SECTION 01 22 00.00 10 Page 1

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)

NIST HB 44 (2024) Specifications, Tolerances, and Other Technical Requirements for Weighing and Measuring Devices

1.2 COMPENSATION

The payment provided for in the contract must constitute full compensation for furnishing all materials and for performing all work under the contract in a complete and acceptable manner. The contract work must include providing bonds (performance and payment), plant, equipment, tools, supplies, labor, supervision, incidental materials, quality control, environmental protection, meeting safety requirements, and performing all work required for which separate payment is not otherwise provided. Compensation for all work shown, specified, or essential to completion of the project (whether or not the specific material or operation is indicated) must be included in the bid price. The payment provided for in the contract includes compensation for all risk, loss, damage, and expense arising out of the nature of the work or its prosecution, subject to conditions of the contract. Payment for each contract line item will constitute full compensation for furnishing the materials and constructing the work complete in place as specified.

All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, must be included in the item most closely associated with the work involved. It is the responsibility of the Contractor to conform bid pricing in accordance with FAR 52.214-19(d) and 52.232-5, ensuring pricing is not materially unbalanced and that the prices presented for each line item or subline item accurately reflects the work effort associated with those items, inclusive of overhead costs.

1.3 APPROVAL OF MATERIALS OR ALTERNATES

Requests for approval of materials and products, or substitutes thereof, will not be considered prior to award of the contract.

1.4 QUANTITY SURVEYS

Provide quantity surveys for bulk materials measured by volume or weight, unless an alternate method of measurement is specified. Quantity surveys

04/30/25 SECTION 01 22 00.00 10 Page 2 are specified in Section 01 71 23.05 13 CONTRACTOR SURVEYS.

1.5 MEASUREMENT BY WEIGHT

Stone will be measured for payment by the ton as determined by barge displacement, certified railroad weights, where direct placement into structure(s) is practicable, or by weighing by the truckload on approved scales meeting the truckload requirements.

1.5.1 Truckload or Railcar

Bulk materials paid for by weight will be measured by weighing each truck load or rail car on an approved scale before being placed in the work.

Scales must be of sufficient length to permit simultaneous weighing of all axle loads and must be sensitive to a change in load of 0.2 percent throughout the range of the scale. The scale's accuracy must conform to the applicable requirements of NIST HB 44 and must be certified by a scale servicing company or by an inspector of the State Inspection Bureau. Each load must be accompanied by a delivery ticket certified by the weighmaster. Delivery tickets must be collected by the Contractor, and copies thereof must be furnished to the Contracting Officer. As a minimum, each ticket must contain the following information:

(1) Date and time.

(2) Vehicle or car number.

(3) Gross weight.

(4) Vehicle or car tare weight.

(5) Net weight.

(6) Job total for material weighed.

(7) Signature of weighmaster.

(8) Signature of Contractor's receiver.

1.5.2 Barge Load

Measurement by barge may be acceptable only if the rock is loaded onto barges at any location other than the Lock and Dam No. 7 (LD7) loading dock.

If material is delivered by barge, stone will be measured for payment by weight determined by barge displacement. Furnish the Contracting Officer a barge displacement table not less than 10 work days prior to unloading the stone from any barge. Submit each table showing the name and/or number of the barge owner, the name of the fabricator, and the certification and date of certification of the person or firm preparing the table. Furnish with the barge displacement tables a drawing or sketch of each barge, dimensioned in sufficient detail to permit checking of the tables. Show, as a minimum, the length, width, depth of the barge, and dimensions of the rake or rakes. A person or firm customarily performing this function other than the Contractor must certify the accuracy of each such table. Submit each table containing, in parallel columns, the freeboard of the barge in feet and tenths from zero to the full depth of the barge and the corresponding gross displacement to the nearest ton. Mark each barge suitably with three displacement gaging locations on each side near each end of the barge and two amidships on opposite sides. Mark each gaging location by a line perpendicular to the edge of the barge, 4 inches wide and 1 foot long, on both the deck and side of the barge and two amid ship on opposite sides. Provide barges with rakes that have the displacement gaging lines placed at each corner of the box section between the rakes.

If a barge has a box end or ends, place the gaging locations approximately

04/30/25 SECTION 01 22 00.00 10 Page 3

4 feet from the box end(s). The freeboard will be measured at the six gaging locations and the displacement determined by the use of "STANDARD BARGE TABLES" from the average of these measurements. The displacement will be determined before and after being unloaded and the difference between these values is the quantity delivered.

Load barges so that the readings taken at the gaging locations do not vary more than 1.5 feet fore and aft and do not vary more than 0.5 feet port to starboard. If such is not the case, trim the carrier by shifting the stone until this limit is reached, before the measurement will be accepted.

Determine the draft from the average of all six readings weighting the readings of the middle gage at double those of the end gages. (G1 + G2 + 2xG3 + 2xG4 + G5 + G6) divided by 8 = average draft. Ensure all carriers used in transporting stone are free of leaks such as would render accurate gauging difficult. Provide facilities for inspecting the hold of each carrier to determine whether leakage is occurring. Provide each carrier with adequate pumping facilities, and if water is found to be accumulating in the hold, pump the carrier dry before each gaging, both before and after unloading. Lightening by pumping or by transfer of crew or supplies will not be permitted while stone is being transferred. Leave rejected stone and unacceptable material aboard the barge until after the final readings are taken.

1.5.2.1 Barge Data, Sketch, and Calculations

Submit the gaging table data, stone hauling vessel information, gaging tables, and a copy of the barge data and table calculations used for the preparation of the tables in accordance with the barge load paragraphs above.

1.6 REMEASUREMENT

Where a loss of material due to stockpiling, rehandling, or hauling is possible, the Contracting Officer will have the discretion to require remeasurement prior to placement at no additional cost to the Government.

1.7 MEASUREMENT UNITS

When materials are measured in units other than the measurement units specified as the basis of payment, the measured quantities must be converted to the specified unit of measure. Factors for conversions from one basis or unit of measurement to another must be approved by the Contracting Officer.

1.8 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following must be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Delivery Ticket

Submit certified delivery tickets.

Barge Data, Sketch, and Calculations; G

04/30/25 SECTION 01 22 00.00 10 Page 4

1.9 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the bid schedule and described below.

The job price and payment made for each item listed must constitute full compensation for performing all work required for which separate payment is not otherwise provided.

1.9.1 BONDS (Performance and Payment)

1.9.1.1 Payment

Payment will be made for Performance and Payment Bonds required by this contract in accordance with FAR 52.232-5 paragraph (g).

1.9.1.2 Unit of Measure

Unit of measure: job.

1.10 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract for which contract unit price payments must be made are listed in the bid schedule and described below.

The unit price and payment made for each item listed must constitute full compensation for performing all work required for each of the unit price items.

1.10.1 EXCAVATED MATERIAL

1.10.1.1 Payment

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for excavation of the excavated material at the project location as shown and specified. Items of work include, but not limited to excavation, loading/unloading, disposal of unsatisfactory excavated material, and placement of excavated material into the weir as shown and specified.

1.10.1.2 Measurement

Measure excavated material for payment by the cubic yard (CY). Determine quantities using the Quantity Survey of the material. Volume must be determined by the amount of material removed from the construction area;

that is the difference between the pre-excavation and post-excavation surveys, after all material has been removed according to plans, specifications and permits. Excavation outside the neat lines and tolerances will not be measured for payment unless authorized by the Contracting Officer.

Additionally, surveys based on requirements of Paragraph SURVEYS FOR VERIFICATION OF DESIGN SECTION as specified in Section 01 71 23.05 13 CONTRACTOR SURVEYS are required to determine if excavation and placement are within the neat lines.

1.10.1.3 Unit of Measure

Unit of measure: cubic yard.

04/30/25 SECTION 01 22 00.00 10 Page 5

1.10.2 RIPRAP

1.10.2.1 Payment

Payment will be made for delivering and furnishing all materials, equipment and labor and performing all operations necessary for providing and placing riprap as shown and specified in accordance with contract terms and conditions.

1.10.2.2 Measurement

Measure riprap for payment by the Net Ton (TN) (2,000 pounds avoirdupois) in accordance with paragraph 1.7 MEASUREMENT BY WEIGHT in this section.

Surveys based on requirements of Paragraph SURVEYS FOR VERIFICATION OF DESIGN SECTION as specified in Section 01 71 23.05 13 CONTRACTOR SURVEYS are required to determine if placement is within the neat lines and tolerances. Payment will be made only for rock placed within the specified tolerances. All rock permitted by the Contracting Officer to remain outside the tolerances specified must be deducted from the payment quantity. The excess volume must be deducted from the payment quantity at the rate of 1.5 tons per cubic yard, regardless of actual weight per cubic yard.

1.10.2.3 Unit of Measure

Unit of measure: Net Ton.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --.

04/30/25 SECTION 01 22 00.00 10 Page 6

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

2.1.2.2 Other Than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Scheduling Expectations Kickoff Meeting(SEKO)

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Cost Loading of Submittals

3.2.3 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Procurement Activities

3.3.4 Mandatory Activities

3.3.5 Government Activities

3.3.6 Standard Activity Coding Dictionary

3.3.6.1 Workers Per Day (WRKP)

3.3.6.2 Responsibility Code (RESP)

3.3.6.3 Work Area Code (AREA)

3.3.6.4 Mod of Claim No. Coding (MODF)

3.3.6.5 Bid Item Coding (BIDI)

3.3.6.6 Phase of Work Coding (PHAS)

3.3.6.7 Category of Work Coding (CATW)

3.3.6.8 Feature of Work Coding (FOW)

3.3.7 Contract Milestones and Constraints

3.3.7.1 Project Start Date Milestone and Constraint

3.3.7.2 End Project Finish Milestone and Constraint

3.3.7.3 Interim Completion Dates and Constraints

3.3.7.3.1 Start Phase

3.3.7.3.2 End Phase

3.3.8 Adverse Weather

3.3.9 Calendars

3.3.10 Open Ended Logic

04/30/25 SECTION 01 32 01.00 10 Page 1

3.3.11 Default Progress Data Disallowed

3.3.12 Out-of-Sequence Progress

3.3.13 Added and Deleted Activities

3.3.14 Original Durations

3.3.15 Leads, Lags, and Start to Finish Relationships

3.3.16 Retained Logic

3.3.17 Percent Complete

3.3.18 Remaining Duration

3.3.19 Cost Loading of Closeout Activities

3.3.19.1 As-Built Drawings

3.3.20 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Initial Project Schedule Submission

3.4.2 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Electronic Scheduling Data

3.5.2 Narrative Report

3.5.3 Schedule Reports

3.5.3.1 Activity Report

3.5.3.2 Logic Report

3.5.3.3 Total Float Report

3.5.3.4 Earnings Report by CLIN

3.5.3.5 Scheduling and Leveling Report

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

3.5.4.2 Project Milestone Dates

3.5.4.3 Critical Path

3.5.4.4 Grouping and Sorting

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUESTS FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Changes That Do Not Cause Delay

3.8.3 Time Impact Analysis (Prospective Analysis)

3.8.4 Forensic Schedule Analysis (Retrospective Analysis)

3.8.5 Fragmentary Network (Fragnet)

3.8.6 Time Extension

3.8.7 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 TRANSFER OF SCHEDULE DATA INTO RESIDENT MANAGEMENT SYSTEM

3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS

04/30/25 SECTION 01 32 01.00 10 Page 2

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

Association for the Advancement of Cost Engineering International

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

AACE 84R-13 (2015) Planning and Accounting for Adverse Weather

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 67-17 (2017) Schedule Delay Analysis

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (2017) Administration -- Project Schedules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules for projects of similar size and complexity to this contract, using Primavera P6.

Representative must have a comprehensive knowledge of critical path method

04/30/25 SECTION 01 32 01.00 10 Page 3

(CPM)scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of…