This document appears to be a set of installation instructions for an internal halyard flagpole system. It provides detailed steps for assembling and installing the flagpole, winch, and cable components. Key details include:

The document contains instructions for properly setting the flagpole foundation, assembling the sectional pole, installing the winch and cable system, and properly hoisting the flag. It includes diagrams and illustrations to aid the installation process. These instructions are intended to be used in conjunction with a federal contract opportunity for the removal of an existing dump station and related site improvements at the Cross Lake Recreation Area.

The related federal contract opportunity is for the "Dump Station Removal & Area Improvement" project at the U.S. Army Corps of Engineers' Cross Lake Recreation Area in Crosslake, Minnesota. The scope of work includes removal of the existing dump station, installation of new concrete sidewalks and paver paths, construction of a new pergola with swing, installation of a bike rack, sprinkler system updates, and landscaping. The work is to be completed by June 27, 2025.

View the file

Other files for this federal contract opportunity

Other files attached to Dump Station Removal & Area Improvement, newest first.
File Type Posted
24Q0137 Amendment 2.pdf PDF
SOW Attachments 2.pdf PDF
24Q0137 Amendment.pdf PDF
Flag Pole Installation ec45ih.pdf PDF
24Q0137 Solicitation.pdf PDF
SOW Attachments.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTERNAL HALYARD FOUNDATION INSTALLATION INSTRUCTIONS

1. Dig foundation hole four to six times the butt diameter of the flagpole.

2. Set the foundation tube so that the top of the foundation tube is two inches above grade.

3. Plumb foundation tube and brace so that it will not move during the pouring of the concrete.

4. Pour concrete and trowel up even with top of foundation tube. Keep inside of foundation tube dry.

5.Laypoleonsawhorsesandunwrap.Forsectionalpolescheckbothendsforanyburrs.If
anyarefound,filethemoffandwipetheareasclean.LiquidSoapthejambsleeves.Align
thearrowsand/ornumbersoneachsectionandjambtogether.Numbersmustbeidentical
foraproperfit.

6. Turn to the next page for winch and cable assembly.

7.Screwballintotruckandtightenballsetscrew.Ballshouldbetightenedintotrucktightly
byturningstemofballwithwrench.Donottightenbyturningballproper.Balloptionalon
internalhalyardpoles.
8.Ifflashcollarisprovidedwithpole,slidecollaronfromthebottomofpoletoabovewinch
levelandattachflashcollarbytyingtothepolewithlinetoholdflashcollaruntilafter
erectionofpole.Thenremoveline,slidecollardown,caulkbetweenthecollarandthe
polewithwaterproofsealant(likeroofingcementofasphaltumsealant).
9.Erectpoleintofoundationtubeandcenterit.Turnsothattheaccessdoorisinthe
directiondesired.
10.Placewoodwedges(suppliedbyothers)betweenthepoleandthefoundationtubeand
plumbpole.
11.Packdrysandbetweenthepoleandfoundationtube.Leavetwoinchesvoidatthetop
andfillwithwaterproofsealanttokeepwateroutofthesand.

IMPORTANT:

Whenerectingsectionalflagpoles,neverplaceyourslingabovethejoint.Slingmustbe
positionedbelowthejoint,thuseliminatingthepossibilitythatthetwosectionscould
separateduringhoisting.

CAUTION

Extreme caution should be exercised when installing flagpoles near overhead power lines or in the vicinity of buries cables.

Rev. 8/2015 Page 1

ACCESSORY ASSEMBLY INSTRUCTIONS

1. For ease of assembly, the upper and lower cable assemblies have been pre-assembled at our factory.

2.Locatetruckwithfactoryinstalledcableassemblies(SeeIllustration#1).
3.Locatelowercableassembly;thiswillbethecableexitingfromthethreadedportionofthe
truck(SeeIllustration#1).
4.Usinganelectrical“FISHTAPE”feedlowercableassemblythroughthe1-1/2”threaded
holeatthetopoftheflagpole,pulllowercablethroughentirelengthofflagpole.
5.Awinchholewithaslottedkeywaywillbefoundabout4ft.abovegradefromthebottom
ofthepole.Usingextremecaution,reachintothishole,graspcableandpullabout4ft.of
cablethroughthishole(SeeIllustration#2).USE CAUTION, THE EDGES OF THIS HOLE

MAY BE SHARP!

6.Youshouldnowhaveallbutafewinchesofthelowercableassemblyinsideoftheflagpole,
oratthelowerendoftheflagpole.Ifthisisnotthecase,thenrepeatsteps1thru5.
7.Screwthetruckassemblyintothetopoftheflagpolesecurely.
8.Ifsteps1thru7havebeensatisfactorilycompleted,thenyouarenowreadytoinstallthe
WINCHASSEMBLY.
9.Locatethewinchassembly.Removethecylinderlockkeyswhicharetapedtothesideofthe
winchassembly.Removethehexdrivecountersunkstainlesssteelscrewfromtherearofthe
winch.Putkeysandscrewinasafelocation.Youwillhavetousetheminalaterstep.
10.Toremovethelockfromwinch,insertkey,turncounter-clockwiseandpulluntilthecylinder
comesout.
11.Locatecableretainingholeandcableretainingsetscrew(SeeIllustration#3).Withpainted
surfaceofwinchinlefthandandunpaintedsurfaceinyourrighthand,lookintowindow
ofwinch.Youwillseea1/8”holelocatedonrightsideofthewinchdrum.Thisisthecable

retaining hole.

12.Takelooseendofcablethatisprotrudingfromthewinchholeandinsertintothecable
retaininghole.Atthispointitisimportantnottoexposeanycableontheothersideofthe
drum(SeeIllustration#3).
13.Locatecrankhandle.Insertintorecessandpushinandturnclockwiseuntilcableretaining
setscrewisexposed.
14.Usingappropriatesize,alignwrenchandtightensetscrewsecurely(SeeIllustration#3).
15.Usingasquarekeywayasapathwayforthe1/8”cable,insertthecartridgeintothewinch
hole(SeeIllustration#4).
16.Locate1/2”holewhichisdirectlyoppositethewinchhole.Alignthisholewiththeholein
thecartridge,insertscrewandtightensecurely(SeeIllustration#5).
17.Withcartridgewinchproperlyinstalled,insertcrankintocranksocket.Pushinandturn
CLOCKWISEuntiltheuppercablestartstomovetowardthetopoftheflagpole.
18.Locatetherubbercoatedcounterweightandattachtemporarilytoopenchainlinkatloose

end of the upper cable.

Page 2Rev. 8/2015

ILLUSTRATION #1

Secure optional finial here

Lower Cable Assembly

Truck Assembly

Upper Cable Assembly

ILLUSTRATION #2

Use slotted keyway to pull cable assembly through

1/2 inch hex drive winch retaining screw

Insert winch into flagpole

Winch Drum

ILLUSTRATION #3

Cable retaining hole:

Insert cable here

Cable retaining set screw:

Secure cable with this

Weep hole

Lower cable assembly from threaded portion of truck

Note: No exposed cable

ILLUSTRATION #4

To unlock:

• Insert key.

• Turn counter-clockwise.

• Pull out cylinder.

To lock:

• Insert cylinder into recess.

• Turn clockwise until snug.

• Apply slight pulling pressure.

• Turn key about 1/2 turn counterclockwise to remove key.

ILLUSTRATION #5

Lower cable assembly

Lock recess and crank port

Winch Drum

1/2 inch hex drive winch retaining screw

Winch Window

ILLUSTRATION #6

Flag Snap

Flag Snap

Counterweight

Counterweight

Beaded Retainer Ring

Beaded Retainer Ring

Cable Stop Cable Stop

STANDARD FLAG

ARRANGEMENT

DELUXE FLAG

ARRANGEMENT

Copper Duplex Sleeve Copper Duplex Sleeve

Thimble Thimble

Stainless Steel Quick Link

Stainless Steel Quick Link

Stainless Steel Cable

Stainless Steel Cable

Safety Cable

Shock Spring

File details come from the government source that posted it. Updated .