02_TL_5.4.8_Earth_Bond_Testing.pdf

PDF 11 MB Posted

Attached to
Facilities Maintenance Services at Fort McCoy, WI
Solicitation number
W912ES-17-R-0002
Issued by

About this file

02 TL 5.4.8

View the file

Other files

File Type Posted
Amendment_3_.pdf PDF
02_TL_54_PM_Task_and_Freq_Chart_(18_Nov_16).xls XLS spreadsheet
Equipment_List_12-1-16.xlsx XLSX spreadsheet
BUILDING_LIST___21NOV16.xlsx XLSX spreadsheet
Amendment_2_.pdf PDF
01_TE_1.4.3_Workload_Data_(14_Nov_16).xlsx XLSX spreadsheet
01_TE_3-1_GFE_(29JAN2016).xlsx XLSX spreadsheet
02_TL_5_4_PM_Task_and_Freq_Chart_.xls XLS spreadsheet
Amendment_1_.pdf PDF
Site_Visit_Sign_In_Sheet_.pdf PDF
02_TL_5.4.4_Fire_Supp_(Dry_Pipe)_(18_FEB_16).xlsx XLSX spreadsheet
02_TL_4.7_WI_SALES_TAX_EXEMPT_FORM_.pdf PDF
02_TL_5.4.9_Cathodic_Protection_Testing.pdf PDF
02_TL_5.3.18b__Facility_Deactivation_(16AUG16).docx DOCX document
01_TE_3.2_GFF_(Post_B2108_Renovation).xlsx XLSX spreadsheet
MCC_Form_451.xlsx XLSX spreadsheet
00_PRS_Schedule_(7SEP16).xlsx XLSX spreadsheet
02_TL_5.4.1_Fire_Supp_(Ansul-Chemical).xlsx XLSX spreadsheet
Questionnaire_Attachment_.pdf PDF
01_CBA_FMC_2014-2017.pdf PDF
02_TL_5.4.5_Fire_Alarm_System.docx DOCX document
01_TE_1.4.3_Workload_Data_(31OCT16)_.xlsx XLSX spreadsheet
01_TE_3.2__GFF_(27_Oct_16).doc DOC document
02_TL_5.3.17Generator_Log_9-20-2016.xlsx XLSX spreadsheet
02_TL_1.2_3rd_Qtr_FY16.xlsx XLSX spreadsheet
02_TL_5.5_Ice_Melt_Report.xls XLS spreadsheet
Solicitation_.pdf PDF
01_TE_1.6.5_PRS_Description_FM_(18_Jul_16).doc DOC document
02_TL_5.4_PM_Task_and_Freq_Chart_(27_Oct_16).xls XLS spreadsheet
02_TL_5.4.6_Elevators_and_Lifts_(13_JUL_16).xlsx XLSX spreadsheet
02_TL_5.4.7_Water_System.pdf PDF
AR_420_1.pdf PDF
01_TE_3.3_GFP_Automation_(6SEP16).xlsx XLSX spreadsheet
01_TE_1.3_DSL_FM_(27_Oct_16).xlsx XLSX spreadsheet
FAC_MAINT_SCA-CBA_Employees.xlsx XLSX spreadsheet
01_TE_1.4.3_Workload_Table_(24_OCT_16).xls XLS spreadsheet
02_TL_5.4.2_Fire_Supp_(Kitchen_Hood_Cleaning).docx DOCX document
02_TL_1.6.12_HVAC_Qualifier.pdf PDF
02_TL_1.6_DD254_Contract_Security_Class_Spec.pdf PDF
02_TL_5.3.5_Facility_Standards.docx DOCX document
02_TL_5.3.18a_Facility_Activation_(16AUG16).docx DOCX document
02_TL_4.5b_Gen_tank_insp_Form_372.xlsx XLSX spreadsheet
02_TL_4.5a_TR-WM-118.pdf PDF
02_TL_5.4.3_Fire_Supp_(Wet_Pipe)_(13_JUL_16).xlsx XLSX spreadsheet
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bond & Earth Testing –

Site:

Date: __________ Condition: __________ Testing Criteria: Per NFPA70B, TM5-684 - Ground Resistance ≤25.0 Ω, Bond Testing DA PAM 385-64 ≤1.0Ω Floor – TB 385-4 min 1 megohm/kilovolt Test Equipment: __________

Room 301 Ground Point:

Use a high-resistance measuring instrument.

Connect one electrode of the measuring instrument to the facility ground.

Connect the other electrode to a five-pound weight that has a contact surface of five square inches of good conducting material.

Attach a non-conductive strap or handle to the block.

Apply voltage Pull the block along all points of the floor or work surface under test to verify that the complete surface meets the minimum resistance requirement of one megohm per kilovolt.

Building Ground Resistance:

Locate and test one of the exterior grounding rods around the exterior of the building near the control tower.

Test Results:

Room 301: ____Pass _____ Fail

Ground Resistance: ____________

Notes:

Bond & Earth Testing -

Site: AP-01 Description of Site: Building 6050 Aircraft Maintenance Hanger Date: _________ Condition: ___________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω, Bond Testing DA PAM 385-64 ≤1.0Ω Test Equipment: ____________

6-1 Ω

6-2 Ω

6-3 Ω

6-4 Ω

6-5 Ω

6-7 Ω

6-8 Ω

6-9 Ω

6-10 Ω

10-Building Ground Ω

Ground Resistance: __________ Ω

Pass/Fail _______

Site: ASP-03 Description of Site:

Date: __________ Weather Conditions: _____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: ________________

REF PT-1 REF PT-2 REF PT-3 REF PT-4 REF PT-5 REF PT-6

Ground Resistance: N/A

ASP-03 Interior Bonding Points

Site: ASP-04 Description of Site:

Date: ___________ Weather Conditions: _____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: ______________

REF PT-1 REF PT-2 REF PT-3 REF PT-4 REF PT-5 REF PT-6 REF PT-7 REF PT-8

ASP-04 Front View

Site: ASP-07 Description of Site:

Date: ____________ Weather Conditions: _____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: _______________

1-2

Ground Resistance: ____________ Ω

Site: ASP-09 Description of Site:

Date: ____________ Weather Conditions: _________________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Reference Point-1

Reference Point-2

Reference Point-3

Reference Point-4

Reference Point-5

Reference Point-6

Reference Point-7

Reference Point-8

ASP-09 Front View

Site: ASP-13 Description of Site:

Date: ____________ Weather Conditions: _______________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: ___________________

Ground Wire-1 Ground Wire-2 Ground Wire-3 Ground Wire-4 Ground Wire-5 Ground Wire-6 Ground Wire-7 Ground Wire-8

Ground Resistance: _________ Ω

ASP-13 Front View

Site: ASP-14 Description of Site:

Date: ____________ Weather Conditions: ________________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

1-2 1-3 1-4 1-5 1-6 1-7 1-8

Ground Resistance: _______ Ω

ASP-14 Front View

Site: ASP-15 Description of Site:

Date: __________ Weather Conditions: _____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Ground Wire-

Ground Wire-

Ground Wire-

Ground Wire-

Ground Wire-

Ground Wire-

Ground Wire-

Ground Wire-

Ground Wire-

Ground Resistance: ________ Ω

ASP-15 Front View

Site: ASP-16 Description of Site:

Date: _________ Weather Conditions: _______________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: _____________________

Door Hinge-1 Door Hinge-2 Door Hinge-3 Door Hinge-4 Door Hinge-5 Door Hinge-6 Door Hinge-7 Door Hinge-8 Door Hinge-9 Door Hinge-

Ground Resistance: _______ Ω

ASP-16 Front View

Site: CF-03 Description of Site:

Date: _______________ Weather Conditions: _______________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

1-2 1-3 of Site:

Condition: __________ Testing Criteria: Per NFPA70B, TM5-684 - Ground Resistance ≤25.0 Ω, Bond Testing DA PAM 385-64 ≤1.0Ω Floor – TB 385-4 min 1 megohm/kilovolt Test Equipment: __________

Room 145 Floor:

Use a high-resistance measuring instrument.

Connect one electrode of the measuring instrument to the facility ground.

Connect the other electrode to a five-pound weight that has a contact surface of five square inches of good conducting material.

Attach a non-conductive strap or handle to the block.

Apply voltage Pull the block along all points of the floor or work surface under test to verify that the complete surface meets the minimum resistance requirement of one megohm per kilovolt.

Building Ground Resistance:

Locate and test one of the exterior grounding rods around the exterior of the building.

Room 145: ____Pass _____ Fail

Ground Resistance: ____________

Site: AP-03 Description of Site:

Date: _________ Weather Conditions: ____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

NFPA 407 - <25 Ω

Bond Testing DA PAM 385-64 ≤1.0Ω.

Test Results

Ground Resistance (Point A-GROUND): DISP1_________ DISP2_________ DISP3__________ DISP4__________

Notes:

DISP1 DISP1 DISP1 DISP2 DISP2 DISP2 DISP3 DISP3 DISP3 DISP4 DISP4 DISP4

A-B B-C D-E A-B B-C D-E A-B B-C D-E A-B B-C D-E

Site: AP-05 Description of Site: U-Fuel Tank Date: __________ Weather Conditions: ____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Ground Resistance: __________

Note:

Site: ASP-01 Description of Site:

Date: __________ Weather Conditions: ____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: ___________

1-2 1-3 1-4 1-5 1-6 1-7 1-8 1-9 1-10 1-11 1-12

Ground Resistance: _______

ASP-01 Front View

Site: ASP-03 Description of Site:

Date: ____________ Weather Conditions: ______________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: _________________

1-2 1-3 1-4

Ground Resistance: __________________

Site: ASP-05 Description of Site:

Date: ____________ Weather Conditions: _____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Ground Resistance: ______ Ω

Site: ASP-06 Description of Site:

Date: _____________ Weather Conditions: _____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: _____________

1-2 1-3 1-4 1-5

Site: ASP-08 Description of Site:

Date: ___________ Weather Conditions: ________________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: __________________

Site: ASP-10 Description of Site:

Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

ASP-10 Front View

Site: ASP-12 Description of Site:

Date: ____________ Weather Conditions: ______________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: ____________________

Ground Wire-1 Ground Wire-2 Ground Wire-3 Ground Wire-4 Ground Wire-5 Ground Wire-6 Ground Wire-7 Ground Wire-8

ASP-11 Front View

Site: ASP-12 Description of Site:

Date: _____________ Weather Conditions: ________________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: _________________

Ground Resistance: ________ Ω

ASP-12 Front View

Site: AP-02 Description of Site: Building 6050 Tanker Points Date: ___________ Weather Conditions: ________________________ Testing Criteria: Per NFPA 780 – Ground Resistance ≤25.0 Ω, Ground Resistance:

1 2 3 4 5 6 N/A

Note:

Site: CF-01 Description of Site:

Date: __________ Weather Conditions: ______________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Bond Testing DA PAM 385-64 ≤1.0Ω Test Equipment: ______________

Test Results:

Ground Resistance (10 – Ground): _______ Ω

Ground Resistance (19 - Ground): _______ Ω

Ground Resistance (31 - Ground): _______ Ω

Notes:

1-2 1-3 4-5 4-6 7-8 7-9 11-10 11- 12 16-17 16-18 19-20 19-21 22-23

22-24 22-19 19-16 7-4 4-1 25-26 27-28 29-30 31-32 21-6 26-27 30-31 28-29

Site: CF-02 Description of Site:

Date: ____________ Weather Conditions: ____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

1-2 1-3 4-5 4-6

Site: SPC-01 Description of Site: Building #6250 Date: _______________ Weather Conditions: ______________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Ground Resistance: ___________ Ω

Site: AP‐04

Description of Site: Building 6058

Weather Conditions: ____________

R ‐ Reference point connected to building steel near Point 1 Test Results (ohms):

R‐1 R‐2 R‐3 R‐4 R‐5 R‐6 R‐7 R‐8 R‐9 R‐10 R‐11 R‐12 R‐13 R‐14 R‐15 R‐16 R‐17 R‐18

NA NA NA NA NA NA

Site: AP-06 Description of Site:

Date: ___________ Weather Condition: _____________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

NFPA 407 - <25 Ω

Building ground-

Building ground-

Building ground-

Building ground-

Building ground-

Building ground-

Building ground-

Building ground-

Building ground-

Ground Resistance: ________

Site: ASP-02 Description of Site:

Date: ___________ Weather Conditions: _________________ Testing Criteria: Per NFPA 780 - Ground Resistance ≤25.0 Ω

Test Equipment: __________________

Door Hinge-1 Door Hinge-2 Door Hinge-3 Door Hinge-4 Door Hinge-5 Door Hinge-6 Door Hinge-7 Door Hinge-8 Door Hinge-9 Door Hinge-

Ground Resistance: ______ Ω

ASP-02 Front View

02 TL 5-2.10 Earth Bond 29_Testing Report - Building 6058 Control Tower
02 TL 5-2.10 Earth Bond 1_01 Airport 6050
02 TL 5-2.10 Earth Bond 10_03 Testing Report - ASP 9005 Inside
02 TL 5-2.10 Earth Bond 11_04 Testing Report - ASP 9004
02 TL 5-2.10 Earth Bond 13_07 Testing Report - ASP 9016
02 TL 5-2.10 Earth Bond 15_09 Testing Report - ASP 9011
02 TL 5-2.10 Earth Bond 19_13 Testing Report - ASP 9013
02 TL 5-2.10 Earth Bond 20_14 Testing Report - ASP 9026
02 TL 5-2.10 Earth Bond 21_15 Testing Report - ASP 9014
02 TL 5-2.10 Earth Bond 22_16 Testing Report - ASP 9007
02 TL 5-2.10 Earth Bond 25_03 Testing Report - Tank Farm Area
02 TL 5-2.10 Earth Bond 26_01 Testing Report - NDB
02 TL 5-2.10 Earth Bond 28_Testing Report - Building 200
02 TL 5-2.10 Earth Bond 3_03 Testing Report - Airport 6050 Refueling
02 TL 5-2.10 Earth Bond 5_05 Testing Report - Airport 6058 UFuel
02 TL 5-2.10 Earth Bond 7_01 Testing Report - ASP 9003
02 TL 5-2.10 Earth Bond 9_03 Testing Report - ASP 9005 Outside
02 TL 5-2.10 Earth Bond 11_05 Testing Report - ASP 9015
02 TL 5-2.10 Earth Bond 12_06 Testing Report - ASP 9018
02 TL 5-2.10 Earth Bond 14_08 Testing Report - ASP 9017
02 TL 5-2.10 Earth Bond 16_10 Testing Report - ASP 9024
02 TL 5-2.10 Earth Bond 17_11 Testing Report - ASP 9012
02 TL 5-2.10 Earth Bond 18_12 Testing Report - ASP 9025
02 TL 5-2.10 Earth Bond 2_02 Report - Airport 6050 Tanker
02 TL 5-2.10 Earth Bond 23_01 Testing Report - Fuel Dispensing Area
02 TL 5-2.10 Earth Bond 24_02 Testing Report - Track Vehicle Refuling
02 TL 5-2.10 Earth Bond 27_01 Testing Report - SPC 6250
02 TL 5-2.10 Earth Bond 4_04 Testing Report - Airport 6058-Hanger
02 TL 5-2.10 Earth Bond 6_06 Testing Report - Airport 6010
02 TL 5-2.10 Earth Bond 8_02 Testing Report - ASP 9006

File details come from the government source that posted it. Updated .