About this file

SECTION 27 33 31.00 10

View the file

Other files for this federal contract opportunity

Other files attached to Devils Lake Flood Risk Management Phase 3 Embankments construction project, newest first.
File Type Posted
DL Phase 3 Revised abstract.pdf PDF
DL PHASE 3 BID ABSTRACT.pdf PDF
DEMO Table REV.pdf PDF
Devils Lake Phase 3 Amendment 0007 032511.pdf PDF
Devils Lake Phase 3 Amendment 0006 032411.pdf PDF
DLCEP3_REALESTATE_PART1.pdf PDF
DLCEP3_CD115.pdf PDF
DLCEP3_CS123.pdf PDF
DLCEP3_CU107.pdf PDF
DLCEP3_C604.pdf PDF
DLCEP3_CD116.pdf PDF
DLCEP3_CD115.pdf PDF
DLCEP3_CD120.pdf PDF
DLCEP3_REALESTATE_PART2.pdf PDF
DLCEP3_CD116.pdf PDF
DLCEP3_CD120 .pdf PDF
DEMO Table.pdf PDF
DLCEP3_C604.pdf PDF
DLCEP3_CS123.pdf PDF
Devils Lake Phase 3 Amendment 0005 032111.pdf PDF
Devils Lake Phase 3 Amendment 0004 031811.pdf PDF
Devils Lake Phase 3 Amendment 0003 031711.pdf PDF
11-B-0005_fullsize_amd3.pdf PDF
11-B-0005_halfsize_amd3.pdf PDF
11-B-0005_halfsize_amend2_part_a.pdf PDF
01 33 00 ENG 4288 REGISTER.pdf PDF
11-B-0005_halfsize_amend2_part_b.pdf PDF
11-B-0005_fullsize_amend2_part_a.pdf PDF
01 22 00 00 13.pdf PDF
11-B-0005 Amendment 0002.doc DOC document
35 73 13 PLACEMENT AND COMPACTION REQUIREMENTS FOR FILL.pdf PDF
35 73 13.pdf PDF
11-B-0005_fullsize_amend2_part_b.pdf PDF
Mar 8 site visit sign-in sheet.pdf PDF
Mar 1 site visit sign-in sheet.pdf PDF
Devils Lake Phase 3 Amendment 0001.doc DOC document
11-B-0005_DLCEP3_11x17_references.pdf PDF
11-B-0005_DLCEP3_11x17_part1b.pdf PDF
11-B-0005_DLCEP3_11x17_part3a.pdf PDF
11-B-0005_DLCEP3_11x17_part4.pdf PDF
11-B-0005_DLCEP3_11x17_part2.pdf PDF
11-B-0005_DLCEP3_11x17_part3b.pdf PDF
11-B-0005_DLCEP3_11x17_part1a.pdf PDF
Devils Lake Ph3 SolicitationW912ES-11-B-0005 FINAL .pdf PDF
11-B-0005_DLCEP3_22x34_part3b.pdf PDF
11-B-0005_DLCEP3_22x34_part1a.pdf PDF
11-B-0005_DLCEP3_22x34_part3a.pdf PDF
11-B-0005_DLCEP3_22x34_part2.pdf PDF
11-B-0005_DLCEP3_22x34_part1b.pdf PDF
11-B-0005_DLCEP3_22x34_part4.pdf PDF
Show all 50

Devils Lake Flood Risk Management Phase 3 Embankments construction project has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

devils Lake phase 3 DEVP3

SECTION 27 33 31.00 10

ONE-WAY FM RADIO DATA CONTROL SYSTEM

04/06

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 142 (2007) Recommended Practice for Grounding of Industrial and Commercial Power Systems

- IEEE Green Book

IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power Circuits

IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 780 (2011) Standard for the Installation of Lightning Protection Systems

1.2 SYSTEM DESCRIPTION

1.2.1 General

Provide a complete FM radio system consisting of transmitter, communication links, antenna system, radio switches, communication links surge protection, and power line surge protection. The system shall be compatible with the existing master radio system at Devils Lake.

1.2.2 Electrical Requirements

The equipment shall operate from an AC voltage source as shown, plus or minus 10 percent, at a frequency of 60 Hz, plus or minus 2 percent.

1.2.3 Power Line Surge Protection

Protect equipment connected to AC circuits from power line surges.

Equipment shall meet the requirements of IEEE C62.41.1 and IEEE C62.41.2.

Fuses shall not be used for surge protection.

1.2.4 Communications Links Surge Protection

Protect communications equipment against surges induced on any communications link. Cables and conductors which serve as communications links shall have surge protection circuits installed at each end. Furnish

SECTION 27 33 31.00 10 Page 1 protection at equipment and additional triple electrode gas surge protectors rated for the application on each circuit installed within 3 feet of the building cable entrance. Surge protection shall meet the requirements of NFPA 780 guidelines and specifications.

1.3 RADIO FREQUENCY COMMUNICATION EQUIPMENT (RFCE) SYSTEM

Design the antenna installations to maintain minimum field strength of 30 microvolts/meter at any point in the controlled area during transmission.

1.4 TECHNICAL DATA

Deliver the technical data specified herein in accordance with Contract Clauses, Special Contract Requirements, and the Contract Data Requirements List, DD Form 1423 which is attached and made a part of this Contract.

Data delivered shall be identified by reference to the particular specification paragraph against which it is furnished. Data shall be organized and delivered as follows:

1.4.1 Group I Technical Data Package

1.4.1.1 System Drawings

The data package shall include the following:

a. FM Radio System block diagram.

b. FM Radio System component installation and wiring diagrams.

c. FM Radio System physical layout and schematics.

d. Details of connections to power sources, including grounding.

e. Details of surge protection device installation.

f. Details of cable splicing and connector installations.

1.4.1.2 Equipment Data

A complete data package shall be delivered for all materials, including field and system equipment.

1.4.1.3 FM Transmission System Descriptions and Analyses

The Group I data package shall include complete system descriptions, analyses, and calculations used to configure required equipment.

Descriptions and calculations shall show how the equipment will operate as a system to meet the specified performance requirements.

1.4.1.4 RF Area Coverage Report

The Group I data package shall include an area coverage report incorporating a topographical map with coverage indicated. The following shall be shown on the map:

a. Location of the transmitter and antenna.

b. Location of the radio switch from the transmitting antenna.

SECTION 27 33 31.00 10 Page 2

c. Radials (straight line segments indicating direction, distance and difference in elevation) from the transmitting antenna to the radio switches described in b. above.

f. Attenuation (dB) between the transmitting antenna and the radio switches described in b. above. The system loss shall take into account the effect of terrain variables such as distance, antenna height, obstructions, and absorption losses.

1.4.2 Group V Technical Data Package

The Group V technical data package shall consist of the system documentation. The draft copy used during site testing shall be updated with any changes required prior to final delivery of the manuals. Each manual's contents shall be identified on the cover. The manuals shall include the names, addresses, and telephone numbers of each subcontractor installing equipment and systems and of the nearest service representative for each item of equipment and each system. The manuals shall have a table of contents and tab sheets. Tab sheets shall be placed at the beginning of each chapter or section and at the beginning of each appendix. The final copies, bound in hardback loose-leaf binders, shall be delivered within 30 days after completion of the endurance test, and shall include all modifications made during installation, checkout, and acceptance. Manuals delivered shall include:

a. Functional Design Manual: two copies.

b. Hardware Manual: two copies.

c. Operator's Manual: six copies.

d. Maintenance Manual: twocopies.

1.4.2.1 Functional Design Manual

The functional design manual shall identify the operational requirements for the radio control system and explain the theory of operation, design philosophy, and specific functions. A description of hardware functions, interfaces, and requirements shall be included for all system operating modes.

1.4.2.2 Hardware Manual

A manual describing equipment furnished, including:

a. General description and specifications.

b. Installation and checkout procedures.

c. Equipment electrical schematics and layout drawings.

d. Alignment and calibration procedures.

e. Manufacturer's repair parts list indicating sources of supply.

f. Interface definition.

SECTION 27 33 31.00 10 Page 3

1.4.2.3 Operator's Manual

The operator's manual shall fully explain procedures and instructions for operation of the system.

1.4.2.4 Maintenance Manual

The maintenance manual shall include descriptions of maintenance for all equipment including inspection, calibration, periodic preventative maintenance, fault diagnosis, and repair or replacement of defective components.

1.5 ENVIRONMENTAL REQUIREMENTS

Equipment to be utilized indoors shall be rated for continuous operation under ambient environmental conditions of 35 to 120 degrees F dry bulb and 10 to 95 percent relative humidity, noncondensing. All other equipment shall be rated for continuous operation under the ambient environmental temperature, pressure, humidity, and vibration conditions specified or normally encountered for the installed location.

PART 2 PRODUCTS

2.1 NAMEPLATES

Provide nameplates with unique identifiers engraved or stamped.

Permanently attach nameplates to enclosure panel doors and back plates.

For each field mounted piece of equipment attach a plastic or metal tag with equipment name and point identifier.

2.2 RADIO FREQUENCY COMMUNICATION EQUIPMENT (RFCE)

2.2.1 Contractor Furnished

RFCE shall be furnished and installed by the Contractor.

2.3 ANTENNA CABLING

Antenna cabling for 900 MHz shall be Times Microwave Systems LMR-400 for feedlines less than 50 Ft and Times Microwave Systems LMR-600 for feedlines more than 50 Ft, or government approved equal. Connections shall be N-Type with the exception of jumper connection from the radio (TNC) to the lightning arrestor (N-Type). All connectors shall be installed by qualified personnel with experience with radio telemetry equipment. Antenna Cable Jumpers shall be a manufactured cable set with factory installed ends.

Cable for jumper to be a minimum of RG-59. All connection points outside buildings shall be weather proofed using cold shrink kits as per manufacturer's instructions. Weatherproofing materials shall be designed to resist water and UV light.

2.4 GROUNDING KITS

Antenna cable to be grounded per manufacturer specifications but no less than immediately inside structure entrances and every 100' of cable thereafter. Grounding kits manufactured by the cable manufacturer, produced specifically for the cable being used shall be used. No third party grounding kits will be acceptable.

SECTION 27 33 31.00 10 Page 4

2.5 LIGHTNING PROTECTION

Lightning protection shall be supplied for each radio antenna and shall be field installed by Contractor, and grounded per manufacturer's instructions. Lightning protection device shall be Manufacturer/Model:

Polyphaser - IS-B50LN-C2, or government approved equal. Characteristics of the lightning protection shall be as follows:

Frequency Range (MHz): 125 - 1000.

RF Power (Watts): VHF 375, UHF 125.

Unit Impendence (Ohms): 50.

Throughput Energy (micro joules): less than or equal to 220.000.

Throughput Voltage (Volts): less than 700 Vpk.

Connectors: N Female Insertion Loss (dB): 0.1 dB.

Turn On Voltage (Volts): 600 V.

2.6 YAGI DIRECTIONAL ANTENNA

YAGI Directional Antenna shall be supplied and field installed per manufacturer's instructions by the Contractor. Antenna shall be mounted per manufacturers specifications using OEM mounting hardware supplied with antenna. The YAGI Directional Antenna shall shall be Manufacturer/Model: GE MDS Clearwave - 97-3194-A06, or government approved equal. Characteristics of the YAGI Directional Antenna shall be as follows:

Frequency (MHz): 450-470.

No. of Elements: 6 element.

Gain (dB): 10 dB.

Connector: Standard N Female.

Power rating: 150 Watts.

Front to Back Ratio: greater than or equal to 15 dB.

Wind Loading: 200 mpg wind, 110 mph with 0.5" radial ice.

2.7 LONG RANGE IP/ETHERNET AND SERIAL RADIO

Long Range IP/Ethernet and Serial Radio shall be supplied and installed per manufacturer's instructions by the Contractor. The Long Range IP/Ethernet and Serial Radio shall shall be Manufacturer/Model: GE MDS SD4 Series, or government approved equal. Characteristics of the Long Range IP/Ethernet and Serial Radio shall be as follows:

General;

Frequency: Configurable Operational Modes: Simplex, half-duplex Modulation: Digital, CPFSK Range: Up to 50 miles RF Data rate & Bandwidth: 9,600 & 19,200 bps @ 12.5 kHz Frequency Band: 450 - 512 MHz

Transmitter;

Frequency Stability: +/- 0.5 ppm Carrier Power: 0.1 to 5 Watts Programmable Carrier Power Accuracy: Normal +/- 1.5 dB Duty Cycle: Continuous Output Impedance: 50 Ohms

Receiver;

Type: Double Conversion Superheterodyne

SECTION 27 33 31.00 10 Page 5

Sensitivity: -112 dBm typical @ 1x10-6 BER Selectivity: greater than 10 dB

Interfaces;

Serial COM1: RS-232, DB-9 Serial COM2: RS-232, RS-485 DB-9 Ethernet: 10/100 BaseT, RJ 45 Antenna: TNC Female

Management;

MDS PulseNET NMS MDS Radio Configuration Software AES-128 Encryption Remote Diagnostics

Environmental;

Temperature: -40°C to +70°C (-40°F to +158°F) Humidity: 95% @ 40°C (104°F) non-condensing

Electrical;

Tx Current: 2.2A Typical at 5 Watts Rx Current: <125 mA Sleep Mode: 9 mA nominal Primary power: 10-30 Vdc

Mechanical;

Case: Rugged die-cast aluminum Dimensions: 1.5 H x 6.5 W x 4.625 D in Weight: 1.22 lbs DIN-rail mounting kit.

2.8 5 PORT ETHERNET SWITCH

5 Port Ethernet Switch shall be supplied and installed per manufacturer's instructions by the Contractor. The 5 Port Ethernet Switch shall shall be Manufacturer/Model: Sixnet - SLX-5MS-1, or government approved equal.

Characteristics of the Long Range IP/Ethernet and Serial Radio shall be as follows:

Performance;

Managed with 5 Ethernet ports Store & Forward wire-speed switching Automatic address learning, aging and migration.

Power Input;

10-30 VDC

Redundant input terminals

Environmental;

Operation temperature: -40 to 75°C Storage temperature: -40 to 85°C Humidity (non-condensing) 5 to 95% RH

Din Rail mounting

SECTION 27 33 31.00 10 Page 6

PART 3 EXECUTION

3.1 INSTALLATION

Install system components and appurtenances in accordance with the manufacturer's instructions and as shown. Provide necessary interconnections, services, and adjustments required for a complete and operable radio system. Grounding shall be in accordance with IEEE 142.

3.1.1 Antenna

Plug tubular radiator elements to prevent wind vibration fatigue. Vertical tubular elements shall have drain holes near the bottom. Outside connectors shall be snug, filled with silicone grease, and properly sealed with heat-shrink wrap suitable for ambient temperatures of minus 22 to 140 degrees F.

3.1.2 Interior Work

Install interior electrical work as specified in Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM and as shown.

3.1.3 Exterior Work

3.1.3.1 Underground

Except as otherwise specified, install underground electrical work as specified in Section 33 71 02.00 20 UNDERGROUND ELECTRICAL DISTRIBUTION and as shown.

a. Where direct burial cable will pass under sidewalks, roads, or other paved areas, the cable shall be placed in minimum 1 inch rigid galvanized steel conduit. Conduit may be installed by jacking or trenching, as approved. When direct burial cable is to be placed in heavy use areas other than paved areas and where the cable may be subject to damage from heavy equipment, the cable shall be placed in minimum 1 inch rigid PVC conduit schedule 80, buried a minimum of 42 inches below the surface.

b. Direct burial cable shall be placed below a minimum 3 inch wide plastic warning tape buried in the same trench or slot. The tape shall be 12 inches above the cable. The warning tape shall be continuously imprinted with the words "WARNING--COMMUNICATION CABLE BELOW" at not more than 4 foot intervals.

c. Transitions from underground cable to aerial cable shall be as specified for CONNECTIONS BETWEEN AERIAL AND UNDERGROUND SYSTEMS in Section 33 71 02.00 20 UNDERGROUND ELECTRICAL DISTRIBUTION.

d. Splices shall be installed in cable boxes. Sufficient cable shall be provided in each splicing location to properly rack and splice the cables, and to provide extra cable for additional splices. Proper strain relief shall be provided. Cable ends shall be protected at all times with end caps except during actual splicing. During the splicing operations, means shall be provided to protect the unspliced portions of the cable from the intrusion of moisture and other foreign matter.

e. For cable installed in ducts and conduit, a cable feeder guide shall be used between the cable reel and the face of the duct and

SECTION 27 33 31.00 10 Page 7 conduit to protect the cable and guide it into the duct and conduit as it is played off the reel. As the cable is played off the reel, it shall be inspected for jacket defects. Cable shall not be kinked or crushed during installation. A pulling eye shall be attached to the cable and used to pull the cable through the duct and conduit system.

Cable shall be hand fed and guided through each manhole. As the cable is played off the reel into the cable feeder guide, it shall be sufficiently lubricated with a type of lubricant recommended by the cable manufacturer. Where the cable is pulled through a manhole, additional lubricant shall be applied at intermediate manholes.

Dynamometers or load-cell instruments shall be used to ensure that the pulling line tension does not exceed the installation tension value specified by the cable manufacturer. The mechanical stress placed upon a cable during installation shall not be such that the cable is twisted or stretched.

3.1.4 Radio Control Switch (RCS)

Install RCS in accordance with manufacturer's guide and seal penetrations with rubber silicone sealant to preclude the entry of water.

3.1.5 Impulse Suppression Surge Arrester Grounding

Impulse suppression surge arresters shall be grounded. Ground resistance shall be not more than 10 ohms. Connections to earth shall be made in the same manner as for secondary neutral ground rod. The aerial portions of surge arrester and secondary neutral ground conductors shall be separate from and independent of each other but both grounds shall be bonded together below grade at the ground rods, or to the ground counterpoise, as applicable and the ground rods shall be spaced a minimum of 20 feet apart.

3.2 RADIO CONTROL SYSTEM TESTING

3.2.1 General

Demonstrate compliance of the one-way FM Radio Data Control System with the contract documents. Furnish personnel, equipment, instrumentation, and supplies necessary to perform site testing. Ensure that test personnel are regularly employed in the testing and calibration of radio control systems. Testing shall include the field tests and the performance verification tests. Field tests shall be conducted by the Contractor to determine the system is completely operational. Performance verification test shall be a demonstration to the Government to ensure proper operation of all the components and proper execution of the sequence of operation.

3.2.2 Test Plan

Submit and obtain approval of the field test plan and performance verification test plan for each phase of testing before beginning that phase of testing. Give to the Contracting Officer written notification of planned testing at least 30 days prior to test. Notification shall be accompanied by the proposed test procedures. In no case will the Contractor be allowed to start testing without written Government approval of field test plan and performance verification test plan.

3.2.3 Test Oversight

Tests are subject to oversight and approval by the Contracting Officer.

SECTION 27 33 31.00 10 Page 8

3.2.4 Test Reporting

Before scheduling the performance verification test, furnish field test documentation and written Certified Statement of Field Test Completion to the Contracting Officer for approval. The statement, certified by the radio control system provider, states that the installed system has been tested and is ready for the performance verification test. Do not start the performance verification test prior to receiving written permission from the Government. During and after completion of the Field Tests, and again after the Performance Verification Tests, identify, determine causes, replace, or repair equipment that fails to meet the specification, and submit a written report to the Government. Document all tests with detailed test results. Explain in detail the nature of each failure and corrective action taken. Provide a written report containing test documentation after the Field Tests and again after the Performance Verification Tests.

-- End of Section --

SECTION 27 33 31.00 10 Page 9

File details come from the government source that posted it. Updated .