Abstract of Bids.pdf
PDF 91 KB Posted
- Attached to
- Below Piggott Seepage Remediation Federal contract opportunity
- Solicitation number
- W912EQ20B0003
About this file
This abstract of bids summarizes the offers received in response to a solicitation for a channel cleanout and seepage berm construction project on the St. Francis River in Clay County, Arkansas. The solicitation was issued by the U.S. Army Corps of Engineers Memphis District as a HUBZone small business set-aside. Five contractors submitted bids by the July 28, 2020 deadline ranging from $10.7 million to $24.4 million. The government estimate was $16.3 million. The scope of work includes clearing debris from 44,060 linear feet of channel, constructing 36,426 linear feet of interior drainage, establishing turf, installing environmental protections, and other related work. Line items cover mobilization, demolition, excavation, culverts, stone products, and other construction activities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment-0004.pdf | ||
| Drawing-Plans Vol 2- Amendment 3.pdf | ||
| Solicitation Amendment-0003.pdf | ||
| Drawing-Plans Vol 1- Amendment 3.pdf | ||
| Drawing-Plans Vol 2-Amended.pdf | ||
| Performance Specifications-Amended.pdf | ||
| Solicitation Amendment-0002.pdf | ||
| Solicitation Amendment-0001.pdf | ||
| Drawing-Plans Vol 1-Amended.pdf | ||
| Drawing-Plans -Vol 1.pdf | ||
| Solicitation.pdf | ||
| Drawing-Plans 3.pdf | ||
| Drawing-Plans 2.pdf | ||
| Drawing-Plans 1.pdf | ||
| Specifications.pdf | ||
| Solicitation.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNOFFICIAL ABSTRACT
I certify that I have read all offers received in response to this solicitation and all offers have been recorded on this abstract Sequoria Wilson, Bid Opening Officer
UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED UNIT EXTENDED
NO. DESCRIPTION QTY U/M PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
0001 MOBILIZATION AND DEMOBILIZATION 1 JA XXX $271,748.00 XXX 686,000.00$ XXX 718,609.00$ XXX 935,000.00$ XXX 1,000,000.00$
0002 ENVIRONMENTAL PROTECTION 1 JA XXX $7,486.00 XXX 37,000.00$ XXX 43,319.00$ XXX 11,000.00$ XXX 20,000.00$
0003 STORM WATER POLLUTION PREVENTION
0003AA WRITE AND AMEND SWPPP 1 JA XXX 3,542.00$ XXX 5,300.00$ XXX 55,696.00$ XXX 17,000.00$ XXX 5,500.00$
0003AB TEMPORARY ENVIRONMENTAL SEEDING 1 JA XXX 199,729.00$ XXX 26,285.00$ XXX 92,827.00$ XXX 260,000.00$ XXX 100,000.00$
0003AC EROSION CONTROL BERM 100,600 LF 0.56$ 56,336.00$ 2.12$ 213,272.00$ 2.75$ 276,650.00$ 1.50$ 150,900.00$ 2.00$ 201,200.00$
0003AD SILT FENCE 11,270 LF 2.04$ 22,990.80$ 3.17$ 35,725.90$ 4.68$ 52,743.60$ 3.00$ 33,810.00$ 2.15$ 24,230.50$
0003AE CONSTRUCTION ENTRANCE/EXIT 2 EA 3,333.00$ 6,666.00$ 2,640.00$ 5,280.00$ 3,713.00$ 7,426.00$ 3,500.00$ 7,000.00$ 3,000.00$ 6,000.00$
0003AF CHECK DAM 28 EA 915.54$ 25,635.12$ 607.00$ 16,996.00$ 897.32$ 25,124.96$ 3,000.00$ 84,000.00$ 1,500.00$ 42,000.00$
0004 DEMOLITION
0004AA STRUCTURAL DEMOLITION 1 JA XXX 16,990.00$ XXX 31,600.00$ XXX 71,786.60$ XXX 80,000.00$ XXX 46,000.00$
0004AB PIPE AND WELL ABANDONMENT 1 JA XXX 23,023.00$ XXX 21,100.00$ XXX 12,978.52$ XXX 90,000.00$ XXX 135,000.00$
0004AC CANOPY REMOVAL 1 JA XXX 4,064.00$ XXX 10,600.00$ XXX 29,704.80$ XXX 50,000.00$ XXX 24,000.00$
0004AD DEMOLITION, ALL OTHER ITEMS 1 JA XXX 48,381.00$ XXX 26,300.00$ XXX 49,462.49$ XXX 30,000.00$ XXX 315,000.00$
0004AE HAZARDOUS SUBSTANCE TESTING 1 JA XXX 3,653.00$ XXX 5,300.00$ XXX 11,139.30$ XXX 6,000.00$ XXX 6,500.00$
0005 TRAFFIC CONTROL AND SIGNAGE 1 JA XXX 86,566.00$ XXX 80,000.00$ XXX 33,417.90$ XXX 300,000.00$ XXX 125,000.00$
0006 HAUL ROADS AND LOW WATER CROSSING
0006AA HAUL ROAD #1 1 EA 47,420.00$ 47,420.00$ 26,500.00$ 26,500.00$ 111,393.00$ 111,393.00$ 250,000.00$ 250,000.00$ 35,000.00$ 35,000.00$
0006AB HAUL ROAD #2 1 EA 80,714.00$ 80,714.00$ 26,500.00$ 26,500.00$ 99,016.00$ 99,016.00$ 140,000.00$ 140,000.00$ 150,000.00$ 150,000.00$
0006AC HAUL ROAD #3 1 EA 16,651.00$ 16,651.00$ 26,500.00$ 26,500.00$ 55,552.93$ 55,552.93$ 80,000.00$ 80,000.00$ 90,000.00$ 90,000.00$
0006AD HAUL ROAD #4 1 EA 14,962.00$ 14,962.00$ 26,500.00$ 26,500.00$ 86,639.00$ 86,639.00$ 50,000.00$ 50,000.00$ 60,000.00$ 60,000.00$
0007 GEOTEXTILE, NON-WOVEN 75,300 SY 1.82$ 137,046.00$ 3.17$ 238,701.00$ 4.33$ 326,049.00$ 4.75$ 357,675.00$ 1.15$ 86,595.00$
0008 CLEARING-CHANNEL BANK 285 HL 882.36$ 251,472.60$ 2,322.00$ 661,770.00$ 1,237.70$ 352,744.50$ 1,650.00$ 470,250.00$ 1,800.00$ 513,000.00$
0009 CLEARING AND GRUBBING-BERM 240 AC 472.41$ 113,378.40$ 845.00$ 202,800.00$ 3,805.93$ 913,423.20$ 3,600.00$ 864,000.00$ 1,050.00$ 252,000.00$
0010 CHANNEL CLEANOUT EXCAVATION 355,228 CY 2.97$ 1,055,027.16$ 3.17$ 1,126,072.76$ 7.43$ 2,639,344.04$ 12.00$ 4,262,736.00$ 2.92$ 1,037,265.76$
0011 EXCAVATION 77,100 CY 2.94$ 226,674.00$ 3.17$ 244,407.00$ 3.40$ 262,140.00$ 3.00$ 231,300.00$ 2.75$ 212,025.00$
0012 SEMI-COMPACTED FILL 764,500 CY 5.44$ 4,158,880.00$ 10.19$ 7,790,255.00$ 7.43$ 5,680,235.00$ 10.00$ 7,645,000.00$ 9.12$ 6,972,240.00$
0013 CORRUGATED METAL PIPE (CMP) CULVERT
0013AA 24" CMP CULVERT 92 LF 66.95$ 6,159.40$ 36.95$ 3,399.40$ 99.00$ 9,108.00$ 350.00$ 32,200.00$ 231.00$ 21,252.00$
0013AB 30" CMP CULVERT 59 LF 85.03$ 5,016.77$ 42.20$ 2,489.80$ 123.77$ 7,302.43$ 400.00$ 23,600.00$ 213.00$ 12,567.00$
0014 24" STEEL PIPE CULVERT 528 LF 238.99$ 126,186.72$ 36.95$ 19,509.60$ 142.33$ 75,150.24$ 850.00$ 448,800.00$ 361.00$ 190,608.00$
0015 SEEDING-CHANNEL BANK 129 AC 1,431.12$ 184,614.48$ 2,650.00$ 341,850.00$ 3,101.00$ 400,029.00$ 6,000.00$ 774,000.00$ 950.00$ 122,550.00$
0016 ESTABLISHMENT OF TURF-BERM 240 AC 2,693.95$ 646,548.00$ 2,650.00$ 636,000.00$ 3,683.10$ 883,944.00$ 6,000.00$ 1,440,000.00$ 950.00$ 228,000.00$
0017 STONE PRODUCTS
0017AA AGGREGATE SURFACE COURSE 19,200 TN 31.85$ 611,520.00$ 44.30$ 850,560.00$ 37.13$ 712,896.00$ 65.00$ 1,248,000.00$ 28.00$ 537,600.00$
0017AB COARSE AGGREGATE, SIZE #1 21,670 TN 35.88$ 777,519.60$ 44.30$ 959,981.00$ 34.38$ 745,014.60$ 75.00$ 1,625,250.00$ 30.15$ 653,350.50$
0017AC COARSE AGGREGATE, SIZE #57 13,240 TN 35.56$ 470,814.40$ 44.30$ 586,532.00$ 34.05$ 450,822.00$ 80.00$ 1,059,200.00$ 30.15$ 399,186.00$
OPTION 1
0018 ASBESTOS ABATEMENT 1 JA XXX 38,210.00$ XXX 10,500.00$ XXX 37,131.00$ XXX 5,000.00$ XXX 19,000.00$
0019 LEAD ABATEMENT 1 JA XXX 5,320.00$ XXX 21,000.00$ XXX 30,942.50$ XXX 5,000.00$ XXX 9,200.00$
OPTION 2
0020 MOBILIZATION AND DEMOBILIZATION 1 JA XXX 6,040.00$ XXX 155,000.00$ XXX 59,348.00$ XXX 25,000.00$ XXX 50,000.00$
0021 ENVIRONMENTAL PROTECTION 1 JA XXX 6,160.00$ XXX 5,100.00$ XXX 15,000.00$ XXX 1,500.00$ XXX 2,000.00$
0022 STORM WATER POLLUTION PREVENTION
0022AA WRITE AND AMEND SWPPP 1 JA XXX 2,660.00$ XXX 3,100.00$ XXX 19,500.00$ XXX 2,300.00$ XXX 2,000.00$
0022AB TEMPORARY ENVIRONMENTAL SEEDING 1 JA XXX 53,980.00$ XXX 26,000.00$ XXX 14,852.40$ XXX 35,000.00$ XXX 20,000.00$
0022AC EROSION CONTROL BERM 7,600 LF 0.56$ 4,256.00$ 2.12$ 16,112.00$ 2.36$ 17,936.00$ 1.00$ 7,600.00$ 2.00$ 15,200.00$
0022AD SILT FENCE 100 LF 2.04$ 204.00$ 3.17$ 317.00$ 4.40$ 440.00$ 2.00$ 200.00$ 2.50$ 250.00$
0022AE CHECK DAM 7 EA 915.57$ 6,408.99$ 600.00$ 4,200.00$ 928.27$ 6,497.89$ 3,000.00$ 21,000.00$ 2,000.00$ 14,000.00$
0023 DEMOLITION, ALL OTHER ITEMS 1 JA XXX 1,420.00$ XXX 10,100.00$ XXX 0.00 XXX 20,000.00$ XXX 16,000.00$
0024 GEOTEXTILE, NON-WOVEN 5,000 SY 1.82$ 9,100.00$ 3.17$ 15,850.00$ 4.12$ 20,600.00$ 3.25$ 16,250.00$ 1.15$ 5,750.00$
0025 CLEARING AND GRUBBING-BERM 50 AC 472.40$ 23,620.00$ 820.00$ 41,000.00$ 3,616.56$ 180,828.00$ 2,500.00$ 125,000.00$ 1,050.00$ 52,500.00$
0026 EXCAVATION 17,900 CY 2.98$ 53,342.00$ 3.15$ 56,385.00$ 3.23$ 57,817.00$ 1.50$ 26,850.00$ 3.00$ 53,700.00$
0027 SEMI-COMPACTED FILL 119,500 CY 5.16$ 616,620.00$ 6.30$ 752,850.00$ 7.40$ 884,300.00$ 5.00$ 597,500.00$ 9.50$ 1,135,250.00$
0028 STEEL PIPE CULVERT
0028AA 24" STEEL PIPE CULVERT 132 LF 239.00$ 31,548.00$ 29.55$ 3,900.60$ 136.15$ 17,971.80$ 850.00$ 112,200.00$ 570.00$ 75,240.00$
0028AB 30" STEEL PIPE CULVERT 36 LF 302.53$ 10,891.08$ 37.99$ 1,367.64$ 160.90$ 5,792.40$ 850.00$ 30,600.00$ 780.00$ 28,080.00$
0029 ESTABLISHMENT OF TURF-BERM 50 AC 2,693.94$ 134,697.00$ 2,650.00$ 132,500.00$ 3,527.45$ 176,372.50$ 3,800.00$ 190,000.00$ 950.00$ 47,500.00$
0030 STONE PRODUCTS -$
0030AA COARSE AGGREGATE, SIZE #1 1,430 TN 35.88$ 51,308.40$ 44.30$ 63,349.00$ 32.68$ 46,732.40$ 50.00$ 71,500.00$ 32.00$ 45,760.00$
0030AB COARSE AGGREGATE, SIZE #57 860 TN 35.56$ 30,581.60$ 44.30$ 38,098.00$ 32.33$ 27,803.80$ 55.00$ 47,300.00$ 32.00$ 27,520.00$
15,242,619.76$
41%
BIDDER #4
PONTCHARTRAIN PARTNERS, LLC
739 S. CLARK ST
NEW ORLEANS, LA 70119
UNOFFICIAL ABSTRACT
US ARMY, CORPS OF ENGINEERS - MEMPHIS DISTRICT ABSTRACT OF BIDS
SMALL BUSINESS DETERMINATION:HUBZONE SET-ASIDE
BIDDER #3
INVITATION NO.: W912EQ-20-B-0003
GOVT. ESTIMATE BIDDER #1 BIDDER #2
7120 REDWOOD BLVD, SUITE A 643 CHALAN SAN ANTONIO, STE 114
ODIN CONSTRUCTION
HICKMAN, KY 42050
HAROLD COFFEY CONSTRUCTION
P.O. BOX 300
TITLE: BELOW PIGGOTT & BELOW HWY 90
VARIATION FROM GOVT. EST.----------------------------------------------------------------->> 51% 57% 126%
GRAND TOTAL ITEMS 0001 THRU 0018 $10,793,781.52 16,911,553.80$ 24,396,521.00$ 16,327,815.70$
BID OPENING DATE AND TIME: 07/28/2020 AT 1:30 PM COST
MEMPHIS
DISTRICT
ENGINEERING
NUMBER OF AMENDMENTS: 4
BASE CONTRACT: (STA 2+13 TO 341+71)
AAC-AMORIENT CONTRACTING
TAMUNING, GUAM 96913 NOVATO, CA 94945
CEMVM 967 (REV. JAN 00)
ABSTRACT OF BIDS
File details come from the government source that posted it. Updated .