- Marine Corps Support Facility – Blount Island, Maintenance Dredging 38-Foot Project Duval County, Florida
- Solicitation number
- W912EP21B0005
About this file
This is a solicitation notice for maintenance dredging services. The project involves dredging at the Marine Corps Support Facility - Blount Island in Duval County, Florida from Station 0+00 to Station 56+09.1 to a depth of 38 feet plus two feet of allowable overdepth, with dredged material to be placed at the Dayson Island Disposal Area. Additional services include bird and turbidity monitoring, standby time, and partnering regroup. The pre-bid conference will be held on June 18, 2021 and bids are due by July 7, 2021. This is a small business set-aside acquisition under NAICS Code 237990 with a magnitude between $1,000,000 and $5,000,000. Interested vendors must register at beta.Sam.gov to receive any amendments to the solicitation that will be issued electronically on or around June 7, 2021.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Marine Corps Support Facility - Blount Island, Maintenance Dredging 38-Foot Project Duval County, Florida
1. See SF30 Continuation Sheet for Amendment Details
2. Receipt of Bids remains unchanged (07 July 2021) All other conditions remain the same.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 49
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP21B0005
X 9B. DATED (SEE ITEM 11)
07-Jun-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Jun-2021
CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SF 30 CONTINUATION SHEET
Marine Corps Support Facility – Blount Island, Maintenance Dredging, 38-Foot Project, Duval County, Florida
W912EP21B0005 2 Amendment 0003
SUMMARY OF CHANGES
1. SPECIFICATIONS:
Text changes have been updated with additions noted by underlined text (green in PDF) and deletions noted by line/cross-outs (red in PDF). These text changes pertain only to changes made by this amendment.
DELETE SF 1442 and REPLACE with the attached revised SF 1442.
DELETE Section 00800 and REPLACE with the attached revised Section 00800.
DELETE Section 00010A and REPLACE with the attached revised Section 00010A.
DELETE Section 01 11 00 and REPLACE with the attached revised Section 01 11 00.
DELETE Section 01 22 00 and REPLACE with the attached revised Section 01 22 00.
DELETE Section 01 57 20 and REPLACE with the attached revised Section 01 57 20.
2. DRAWINGS: No change to drawings.
(End of Summary of Changes)
MARINE CORPS SUPPORT FACILITY - BLOUNT ISLAND, MAINTENANCE DREDGING 38-FOOT PROJECT, DUVAL COUNTY, FLORIDA
DESCRIPTION OF WORK: REFER TO SECTION 01 11 00 FOR COMPLETE PROJECT DESCRIPTION
DRAWINGS: SEE DFARS CLAUSE 252.236-7001, SECTION 00700.
MAGNITUDE OF CONSTRUCTION IS BETWEEN $1,000,000 AND $5,000,000.
THIS IS A SMALL BUSINESS SET-ASIDE.
NAICS CODE FOR THIS PROJECT IS 237990 AND THE SIZE STANDARD IS $30 MILLION.
**BLOCK 11 - SEE SECTION 00700, FAR CLAUSE 52.211-10 FOR PERIOD OF PERFORMANCE
BID OPENING WILL BE HELD VIRTUALLY VIA WEBEX. UTILIZE THE LINK AND CALL-IN INFORMATION PROVIDED BELOW:
https://usace.w ebex.com/meet/frederick.l.cooper
Audio Teleconference: 1-844-800-2712. Access Code: 1997545390.
YOU MUST BE REGISTERED IN THE SYSTEM FOR AWARD MANAGMENT (SAM) TO RECEIVE AN AWARD FROM THIS
SOLICITATION. THE SAME WEBSITE IS LOCATED AT WWW.SAM.GOV
X
FREDERICK L COOPER 904-232-1186
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-Jun-2021
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______60 calendar days and complete it w ithin ________150 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section 00700
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A.
local time ______________07 Jul 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USA ENGINEER DISTRICT, JACKSONVILLE
CONTRACTING DIVISION
701 SAN MARCO BLVD
JACKSONVILLE FL 32207-8175
W912EP
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
Sealed offers in original and ____1______ copies to perform the w ork required are due at the place specif ied in Item 8 by __0_2_:_0_0 _A__M__ (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912EP21B0005 195
https://usace1.webex.com/meet/frederick.l.cooper
2:00 PM
k3ctcflc Cross-Out k3ctcflc Cross-Out
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
SECTION 00010A
LINE ITEMS AND PRICING SCHEDULE
MARINE CORPS SUPPORT FACILITY - BLOUNT ISLAND
MAINTENANCE DREDGING, 38-FOOT PROJECT
DUVAL COUNTY, FLORIDA
LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL
0001 MOBILIZATION AND DEMOBILIZATION JOB $_______________
0002 EXCAVATION, UNCLASSIFIED
STATION 0+00 TO STATION 56+09.1
(ESTIMATED QUANTITIES, SEE NOTE 1) 150,000 CUBIC YARD $___________ $_______________
0003 TURBIDITY AND DISPOSAL MONITORING JOB $_______________
0004 MARINE ANIMAL OBSERVER
(MECHANICAL DREDGING ONLY) JOB $_______________
0005 BIRD MONITORING JOB $_______________
0006 STURGEON PROTECTED SPECIES OBSERVER
(CUTTERHEAD DREDGING ONLY) 14 DAY $_______________
0006 0007 STANDBY TIME (SEE NOTE 3) 24 HOUR $___________ $_______________
0007 0008 PARTNERING REGROUP 1 EACH $___________ $_______________
TOTAL BID (LINE ITEMS 0001 THROUGH 0007 0008) $_______________
NOTES: (1) THE TOTAL QUANTITY SHOWN FOR EACH EXCAVATION CLIN INCLUDES REQUIRED DEPTH, ALLOWABLE OVERDEPTH, AND SHOALING ESTIMATED TO OCCUR BETWEEN THE DATES OF SURVEYS SHOWN ON THE DRAWINGS AND ACTUAL DREDGING. THE CONTRACTOR SHALL NOT PERFORM WORK IN EXCESS OF THE TOTAL ESTIMATED QUANTITY GIVEN FOR EACH LINE ITEM WITHOUT PRIOR APPROVAL OF THE CONTRACTING OFFICER. THE CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER AT LEAST ONE WEEK PRIOR TO THE ANTICIPATED DATE THAT THE ESTIMATED QUANTITY
MAY BE EXCEEDED.
(2) OFFERS MUST PRICE ALL ITEMS. SEE SECTION 00100 INSTRUCTIONS TO OFFERORS.
(3) STANDBY TIME IS DEFINED AS WHEN THE DREDGE PLANT IS NOT IN OPERATION AT THE DIRECTION OF THE CONTRACTING OFFICER. STANDBY TIME SHALL BE UTILIZED ONLY DUE TO ENDANGERED SPECIES CONCERNS, DIFFERING SITE CONDITIONS, SECURITY OPERATIONS OR OTHER CONDITIONS AS DETERMINED BY THE CONTRACTING OFFICER. REQUIREMENTS FOR WORK STOPPAGES, DELAYS OR OTHER IMPACTS ASSOCIATED WITH COMPLIANCE WITH SECTION 01 57 20 ENVIRONMENTAL PROTECTION ARE NOT PAID FOR UNDER THIS LINE ITEM. STANDBY TIME IS NOT AFFORDED FOR DELAYS CAUSED BY ADVERSE WEATHER CONDITIONS. PAYMENT WILL ONLY BE MADE FOR ACTUAL STANDBY TIME REQUIRED BY THE CONTRACTING
OFFICER. SEE SECTION 01 22 00 MEASUREMENT AND PAYMENT.
W912EP21B0005 00010A-1 Amendment 0003
Section 00800 - SPECIAL REQUIREMENTS
UAI 5152.231-9000 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR 2013)
As prescribed in 5131.100-70, insert the following clause:
EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE
(a) This special contract requirement does not apply to terminations. See 52.249-5000, Basis for Termination
Settlement Proposals, and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region III. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the small purchase threshold, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing
Proposal Cover Sheet.
(End of special contract requirement)
52.223-1 BIOBASED PRODUCT CERTIFICATION (MAY 2012)
As required by the Farm Security and Rural Investment Act of 2002 and the Energy Policy Act of 2005 (7 U.S.C.
8102(c)(3)), the offeror certifies, by signing this offer, that biobased products (within categories of products listed by the United States Department of Agriculture in 7 CFR part 3201, subpart B) to be used or delivered in the performance of the contract, other than biobased products that are not purchased by the offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements.
(End of provision)
W912EP21B0005 1 Amendment 0003
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (FEB 2021)
(a) "Hazardous material", as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).
(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Material Safety
Data Sheet submitted under this contract.
Material (if none, insert None) Identification No.
(c) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.
(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a Material Safety
Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with
Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items.
Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered nonresponsible and ineligible for award.
(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.
(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the
Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.
(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.
(h) The Government's rights in data furnished under this contract with respect to hazardous material are as follows:
(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to--
(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;
(ii) Obtain medical treatment for those affected by the material; and
(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.
(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this
W912EP21B0005 2 Amendment 0003 clause, in precedence over any other clause of this contract providing for rights in data.
(3) The Government is not precluded from using similar or identical data acquired from other sources.
(End of clause)
UNAUTHORIZED INSTRUCTIONS FROM GOVERNMENT OR OTHER PERSONNEL
The Contractor shall not accept any instructions issued by any person, employed by the Government or otherwise, other than the Contracting Officer or the Contracting Officer's Representative (COR) acting within the limits of the
COR’s authority. See the Contracting Officer's Representative clause of this contract.
(End of paragraph number 999.201-4002)
NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM SYSTEM – SPECIAL STANDARD OF
RESPONSIBILITY
(a) The National Dredging Quality Management Program System (NDQMPS) is an automated dredge contract monitoring system comprised of both Contractor provided hardware, Contractor provided software, and software developed by the Army Corps of Engineers (the Corps). This NDQMPS was formerly known as the Silent Inspector.
The Corps developed the NDQMPS as a low cost, repeatable, impartial system for automated dredge/scow monitoring. The NDQMPS consists of three major components: the Dredge Specific System (DSS), the Ship Server, and the Shore Server. The DSS collects and displays various dredge sensor data for the dredge crew to monitor dredge progress and quality control. The other major task of the DSS is to send data to the Ship Server. Most dredging Contractors already have a computer system and sensors onboard for control or positioning that can be used as the DSS. The dredging Contractor supplies and owns the DSS and all associated sensors. The Ship Server acts as the dredge-based data archive and report creation center by storing the data from the DSS and performing automated review of the data. The Ship Server can produce many different reports including dredge location history, volume history, and operational status. Additional information about NDQMPS can be found at https://dqm.usace.army.mil/.
(b) As authorized by FAR 9.104-2, Contracting Officers may establish special standards of responsibility when necessary. The Contracting Officer has determined that use of the NDQMPS is necessary for work performed by hopper dredge or scows. Therefore, in order to be considered responsible for performing this contract, the Offeror must establish after contract award but prior to notice to proceed that any hopper dredge or scow to be used in performance of this contract has been outfitted with the NDQMPS and the system has been certified by the National
Dredging Quality Management Program System Support Center within the last year. Certification requires meeting the requirements of Section 35 20 23: DREDGING of the contract specifications. Questions regarding certification should be addressed to the NDQMPS support team in Mobile District on the contact form at the web site, or by calling 877-840-8024.
(c) Each solicitation shall contain the current standard NDQMPS requirements in addition to special requirements for the project. These special requirements may include penalties for non-performance and data upload schedules.
(End of paragraph)
W912EP21B0005 3 Amendment 0003
SEAGOING BARGE ACT – SPECIAL STANDARD OF RESPONSIBILITY
The Seagoing Barge Rules (46 USC 2101 et seq.) apply to this project. The contractor, upon the request of the
Contracting Officer, shall be required to submit evidence of U.S. Coast Guard certification. Failure to produce the certificate within the requested time may be cause for determining the offeror non-responsible.
(End of paragraph number)
STANDARD OF RESPONSIBILITY FOR DREDGING CONTRACTOR
After bid opening, in addition to other information the Contracting Officer may require, the apparent low bidder shall provide a listing of all current contracts and a listing of all U.S. Army Corps of Engineers contracts completed within the past two years. For each of these contracts the bidder shall provide: the plant involved; responsible individual’s name (project manager); QC and safety professional’s names; and accident rates, descriptions, and causes. The bidder shall describe corrective actions taken in response to previous accidents and shall address the specific actions planned for this project to preclude similar accidents.
(End of paragraph)
VARIATION IN ESTIMATED QUANTITY -- DREDGING
(a) Read this paragraph in conjunction with the Variation in Estimated Quantity clause of this contract. This paragraph only applies to line items for excavation.
(b) The estimated quantities contained in the excavation line item(s) of this contract include material from both the required dredging prism and an area of allowable overdepth. The Contractor is not required to excavate the material in the area of allowable overdepth. However, as a precondition for requesting an equitable adjustment in the event the actual quantity is less than 85 percent of the estimated quantity, the Contractor shall have excavated 100 percent of the available material in the required prism and at least 75 percent of the available material in the area of allowable overdepth.
(End of paragraph number)
OBTAINING INFORMATION REGARDING THIS SOLICITATION
Read this paragraph in conjunction with FAR 52.214-6, Explanation To Prospective Bidders, which is located in this Section 00100. Verbal requests for information must be directed to the person whose name appears in item 9 of the SF 1442. Collect calls cannot be accepted. Written requests for explanations must be sent to the person identified in item 9 of the SF 1442 and may be sent via facsimile to 904-232-2748. Inquiries and requests that are directed to any other person may not be relayed to the proper person and, therefore, may not be answered.
(End of paragraph number 999.214-4000)
BIDDER'S CHECKLIST -- CONSTRUCTION/DREDGING CONTRACTS
The following list should be used by bidders to avoid irregularities that have occurred in past bids.
1. Have amendments to the Invitation been acknowledged on the bid form in the spaces provided? If not, acknowledgment must be made by separate letter or telegram prior to opening of bids.
2. Have prices been inserted for all bid items of the Bidding Schedule?
3. Do prices inserted include subcontractors' and suppliers' quotations, indirect costs, and profit?
4. Does the total bid amount include the costs of obtaining performance and payment bonds?
5. Have all prices and computations been checked?
6. Is the bid submitted on the latest bid schedule?
7. Have changes been made to the Bidding Schedule if required by amendment?
8. Are decimal points in the bid prices in the proper places?
9. Have you checked for transposition of figures in prices inserted on the Bidding Schedule?
10. Is the bid form signed, and if so, is the bid form signed by a person legally authorized to bind the bidder? Is the
W912EP21B0005 4 Amendment 0003 bidder's address included?
11. If the bid is signed by an agent, is legal evidence of agent's authority to sign included with the bid?
12. If a bid guarantee is required, does your bid guarantee comply with the Bid Guarantee clause of the solicitation?
If the bid guarantee is in the form of a bid bond is it on Standard Form 24? If your bid guarantee does not firmly bind you (and your sureties, if applicable) to the United States of America, YOUR BID WILL BE CONSIDERED
NONRESPONSIVE.
13. If the bid guarantee is in the form of a bid bond, is it completely and properly executed, dated not later than the bid opening date, signed by Principal and Surety, corporate certificates executed, and all as contained in
"Instructions" on Standard Form 24? Power of Attorney is also required to accompany the bond. Is the penal sum marked in? If an individual surety (or sureties) is (are) guaranteeing the bid bond, have the requirements of the
Pledges Of Assets clause of this solicitation been satisfied and are the supporting documents included with the bond?
14. Have the appropriate boxes been checked in all paragraphs of the Representations And Certifications (Section
00101)?
15. Have all representations and certifications been submitted with the bid?
16. If required by the Invitation, is literature, data, catalogs, etc., specified by the Invitation included with the bid?
17. Have requirements of the Late Submissions, Modifications And Withdrawals Of Bids provision of this solicitation been met?
CAUTION: BIDS THAT ARE QUALIFIED BY THE BIDDER MAY BE CONSIDERED NONRESPONSIVE.
ELECTRONIC BIDS
The offeror’s bid shall be submitted electronically, as described below. The use of hyperlinks in the bid is prohibited.
The offeror’s bid must be received no later than 2:00 PM, local time12 August 2021 07 July 2021.
NOTE: The only authorized transmission method of bids in response to the subject solicitation is electronically via
SAFE online submission. No other transmission methods (Email, Facsimile, Regular mail, Hand carried, etc.) will be accepted.
The Offeror’s bid must be received by the Government no later than the date/time specified in the solicitation and cited above. Offerors shall submit their bid using the following link:
https://safe.apps.mil/
Please submit bids utilizing the link above to Contract Specialist, Frederick Cooper at
Frederick.L.Cooper@usace.army.mil and Contracting Officer, Claurice Dingle at
Claurice.M.Dingle@usace.army.mil.
Instructions for submitting electronic bids:
In an effort to reduce paperwork and cost, all bids shall be submitted electronically through the SAFE site. You are limited to five (5) maximum files per upload (total size cannot exceed 2GB). If you have a large number of files, it is recommended that you combine or ZIP your files before uploading to the SAFE site. Offerors may use compression utility software such as WinZip or PKZip to reduce file size and facilitate transmission.
Request for upload code:
Offerors must email Contract Specialist Frederick Cooper at Frederick.L.Cooper@usace.army.mil and Contracting
Officer, Claurice Dingle at Claurice.M.Dingle@usace.army.mil no later than five (5) working days prior to the bid due date to receive a request code which will allow for file uploads via the SAFE site. Offerors that fail to email for request a code five (5) working days before bid submission date may not be able to receive a request code in time to upload their submission.
File Description:
To ensure your submission is received and processed appropriately, it is important that interested parties
W912EP21B0005 5 Amendment 0003 mailto:Frederick.L.Cooper@usace.army.mil mailto:Claurice.M.Dingle@usace.army.mil mailto:Frederick.L.Cooper@usace.army.mil mailto:Claurice.M.Dingle@usace.army.mil k3ctcflc Cross-Out
CAREFULLY ensure their electronic files adhere to the following naming convention. Each file name shall begin with the solicitation number, followed by the word “RESPONSE”, followed by your firm’s name and finally a brief file description.
EXAMPLES:
(1) “W912HP20R0020 RESPONSE Firm name Volume I.pdf”
(2) “W912HP20R0020 RESPONSE Firm name Volume II .pdf
Upload Completion & Deadline.
Interested parties shall submit responses no later than the date cited above. The time & date of bid receipt will be the upload completion / delivery time & date recorded within Safe. Offerors should time their upload effort with prudence by not waiting until the last few minutes— this will allow for unexpected delays in the transmittal process.
Submissions after the deadline may be emailed to Contract Specialist Frederick Cooper
(Frederick.L.Cooper@usace.army.mil) and Contracting Officer Claurice Dingle
(Claurice.M.Dingle@usace.army.mil), but be advised they will be considered late and as such will be processed in accordance with FAR 15.208.
Submission shall be in Adobe PDF format.
Instructions to follow on the SAFE Website:
1. Once at the SAFE website, select the “Drop-off” icon. This allows users without a CAC or users whose computer is not configured to read a CAC the option to access the SAFE site as a guest.
2. After selecting the “Click Here” link you will be prompted to add your personal information, file information, recipient (Government representative) information and email settings
3. When completing your file information for transmittal via the SAFE website, you will be required to enter the email address for all recipients for this solicitation, the recipients are the Contract Specialist and the
Contracting Officer. The Contract Specialist for this solicitation is Frederick Cooper
:Frederick.L.Cooper@usace.army.mil and the Contracting Officer is Claurice Dingle:
Claurice.M.Dingle@usace.army.mil. The E-Mail address of the Government Employee who initiated the request code will be automatically entered. The Bidder must enter the E-Mail address for both the
Contracting Officer and Specialist. The Bidder can enter an additional E-Mail address if desired. After entering the email address, click the ADD button to add the person(s) email to the “Recipients List” of your response. When your bid is submitted, a notification will be sent to the recipients you added.
NOTE: Do NOT send the SAFE site packages to group email accounts.
Even if you successfully upload your bid to the SAFE site, notification will not be sent to the government recipients until you verify your email address. Entering an incorrect email may result in the rejection of your submission for lateness. An Offeror can confirm proper submission by the ‘Drop-Off Completed” screen which generates based on proper file submission.
NOTE: It has been reported that documents may more quickly upload into the SAFE website when using the Firefox web browser. The Government cannot verify that this is true and offers no guarantee that Offerors will have more success utilizing any particular browser.
Receipt of Submission:
For the purposes of establishing whether a bid submission is considered timely, the Government considers the date and time the submission is completely uploaded into the SAFE website. For bids larger than the 2GB capacity of the SAFE website and require multiple submissions, the Government will consider the date and time the last submission is completely uploaded into the SAFE website. Do not assume that electronic communication is instantaneous. It can take several minutes or even hours in some cases.
W912EP21B0005 6 Amendment 0003 mailto:Frederick.L.Cooper@usace.army.mil mailto:Claurice.M.Dingle@usace.army.mil
The Government will not be responsible for submissions delivered to any location or to anyone other than those designated to receive bids. Offerors are responsible for ensuring that bids are submitted so as to reach the designated recipient. Offerors are responsible for allowing sufficient time for the bid to be received in accordance with the instructions provided.
(End of provision)
NOTIFICATION TO UNSUCCESSFUL BIDDERS
In accordance with FAR 14.409-1, unsuccessful bidders will be notified, in writing or electronically within 3 days of contract award, that their bid was not accepted. Award synopsis as well as the Bid Abstract will be posted to the
Federal Business Opportunities website at www.fbo.gov. If a bid is rejected for any reason other than price, the unsuccessful bidder will receive written notification stating the reason for rejection of the bid.
(End of paragraph)
U.S. ARMY CORPS OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1
This paragraph applies to contracts and purchase orders that require the contractor to comply with EM 385-1-1
(e.g., contracts that include the Accident Prevention clause at FAR 52.236-13 and/or other safety provisions). EM
385-1-1 and its changes are available at https://www.usace.army.mil/Missions/Safety-and-Occupational-Health/.
The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the date the solicitation for this contract/purchase order was issued.
(End of paragraph)
DREDGING SAFETY MANAGEMENT PROGRAM
The Contractor shall comply with the provisions of EM 385-1-1. If the Contractor is a currently accepted participant in the Dredging Contractors of America (DCA)/United States Army Corps of Engineers (USACE)
Dredging Safety Management Program (DSMP), as determined by the DCA/USACE Joint Committee, and holds a current valid Certificate of Compliance for both the Contractor Program and the dredge(s) to be used to perform the work required under this contract, the Contractor may, in lieu of submitting an Accident Prevention Plan: (i) upon request, make available for review the Contractor’s current Safety Management System (SMS) documentation, (ii) submit to the Contracting Officer the current valid Company Certificate of Compliance for its SMS, (iii) submit the current dredge(s) Certificate of Compliance based on third party audit, and (iv) submit for review and acceptance, site-specific addenda to the SMS as specified in the solicitation.
(End of Paragraph)
TERMINATION FOR DEFAULT FOR FAILURE TO PROVIDE ACCEPTABLE PERFORMANCE AND
PAYMENT BONDS
If the successful offeror, upon acceptance of its offer by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bonds within 2 workdays after receipt of the notice of award by the offeror, the Contracting Officer may terminate the contract for default.
(End of paragraph number)
W912EP21B0005 7 Amendment 0003 http://www.fbo.gov/ http://www.usace.army.mil/Missions/Safety-and-Occupational-Health/
CONSTRUCTION CONTRACTOR PERFORMANCE EVALUATIONS
In accordance with the provisions of Subpart 36.201 (Evaluation of Contractor Performance) of the Federal
Acquisition Regulation (FAR), construction contractors’ performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in
Engineering and Construction Bulletin 2014-13 to fulfill this FAR requirement. For construction contracts awarded at $650,000.00 or more, the USACE will evaluate contractor's performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 60 days. The evaluation will be transferred to the Past Performance
Information Retrieval System (PPIRS) within 15 calendar days after issuance. However, it will remain with
“Pending” status in PPIRS until the government official closes the form in CPARS. Contractors may access their own evaluations in PPIRS by registering as a user and obtaining specific software, called PKI certification, which is installed on the user's computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The average cost per certificate is about $100 - $120 per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about CPARS, PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.gov. If the
Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.
(End of Paragraph)
NOTICE TO MARINERS -- CONSTRUCTION CONTRACTS
Should the Contractor, during operations, encounter any objects on the channel bottom which could be a hazard to navigation, the Contractor shall immediately notify the Contracting Officer as to the location of said object and shall provide any other pertinent information necessary for the Contracting Officer to prepare and issue a Notice to
Mariners.
(End of paragraph number)
(S-102) CONTRACTOR SUPPLY and USE OF ELECTRONIC SOFTWARE FOR PROCESSING DAVIS-
BACON ACT CERTIFIED LABOR PAYROLLS
The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE WITH DAVIS-BACON AND RELATED ACT REGULATIONS.
If the contractor elects to use an electronic Davis-Bacon payroll processing system, then the contractor shall be responsible for obtaining and providing for all access, licenses and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon and related Act regulations. When the contractor uses an
W912EP21B0005 8 Amendment 0003 http://www.cpars.gov/ electronic Davis-Bacon payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic Davis-Bacon payroll system, then the contractor shall obtain and provide electronic system access to the Government, as required to comply with the
Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.
The contractor’s provision and use of an electronic payroll processing system shall meet the following basic functional criteria; commercially available; compliant with appropriate Davis-Bacon Act payroll provisions in the
FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records
(format at https://rms.usace.army.mil/Home/Guides) for export in an Excel spreadsheet to be imported into the contractor’s Quality Control System (QCS) version of Resident Management System (RMS), that in turn shall export payroll data to the Government’s Resident Management System (RMS); demonstrated security of data and data entry rights; ability to produce contractor-certified electronic versions of weekly payroll data; ability to identify erroneous entries and track the data/time of all versions of the certified Davis-Bacon payrolls submitted to the government over the life of the contract; capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Davis-Bacon payroll processing system shall be provided to the Government during contract closeout.
All contractor-incurred costs related to the contractor’s provision and use of an electronic payroll processing service shall be included in the contractor’s price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this contract.
(End of paragraph)
ENGLISH SPEAKING REPRESENTATIVE
At all times when any performance of the work at any site is being conducted by any employee of the Contractor or his subcontractors, the Contractor shall have a representative present at each site who has the capability of receiving instructions in the English language, fluently speaking the English language and explaining the work operations to persons performing the work in the language that those performing the work are capable of understanding. The
Contracting Officer shall have the right to determine whether the proposed representative has sufficient technical and bilingual capabilities, and the Contractor shall immediately replace any individual not acceptable to the
Contracting Officer.
(End of paragraph)
W912EP21B0005 9 Amendment 0003
Marine Corps Support Facility - Blount Island Maintenance Dredging, 38-Foot Project
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Project Locations
1.2.3 Safety Requirements
1.3 SUBMITTALS
1.4 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.5 LIQUIDATED DAMAGES - CONSTRUCTION
1.6 PHYSICAL DATA
1.6.1 Physical Conditions
1.6.2 Weather, Water Stage and Tide Data
1.6.3 Contractor Investigation
1.6.4 Maritime Traffic
1.6.5 Obstruction of Channel
1.6.6 Hydrographic Surveys
1.7 CONTRACTOR ACCESS AND USE OF PREMISES
1.7.1 MARINE CORPS SUPPORT FACILITY - BLOUNT ISLAND (MCSF-BI) ENTRY
CONTROL REGULATIONS
1.7.1.1 Access
1.7.1.2 No Smoking Policy
1.7.1.3 Cell Phone Usage
1.7.1.4 Security Requirements
1.8 PHOTOGRAPY
1.9 LAYOUT OF WORK
1.9.1 Established Project Control
1.9.2 Layout
1.9.3 Survey
1.10 DAMAGE TO WORK
1.11 EXISTING WORK
1.12 ENTRY CONTROL PROCEDURES APPENDIX
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1 W912EP21B0005 Amendment 0003
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
GDR SECTION 00 31 32, Geotechnical Data Report for U.S. Marine Corps Support Facility - Blount Island, Maintenance Dredging, 38-Foot Project, Duval County, Florida
EM 385-1-1 Safety and Health Requirements Manual
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
Project work consists of maintenance dredging at the Marine Corps Support Facility - Blount Island (MCSF-BI) from Station 0+00 to Station 56+09.1 with a 38-foot required Mean Lower Low Water (MLLW) maintenance depth plus two feet of allowable overdepth throughout as shown on the drawings. The placement location of the dredged material will be Dayson Island Disposal Area (D/A-D) as shown on the drawings. Additional work also includes bird environmental monitoring, turbidity and disposal monitoring, standby time, and partnering regroup.
1.2.2 Project Locations
MCSF-BI is located approximately 15 miles northeast of downtown Jacksonville, Florida and nine miles west of the mouth of the St. Johns River. Blount Island is bordered to the north by St. Johns River and Fulton Cutoff Channel to the south.
1.2.3 Safety Requirements
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1 .
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
SECTION 01 11 00 Page 2
List of Contact Personnel
1.4 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
Read this paragraph in conjunction with the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.5 LIQUIDATED DAMAGES - CONSTRUCTION
Refer to the Clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6 PHYSICAL DATA
Read this paragraph in conjunction with the Clause PHYSICAL DATA (FAR 52.236-4) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6.1 Physical Conditions
The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and/or by core borings. When the indicated physical conditions are the result of site investigations by core borings, the core boring logs and laboratory data are in Geotechnical Data Reports ( GDR) and the core boring locations are shown on the drawings. Also, see the GDR for instructions concerning availability of core borings for inspection.
1.6.2 Weather, Water Stage and Tide Data
See Section 00 33 50 WEATHER, WATER STAGE AND TIDE DATA for applicable data links and information to where the Contractor can ascertain the weather conditions that could be encountered at the project location. The information provided does not preclude the Contractor from assessing and scheduling for adverse weather.
1.6.3 Contractor Investigation
Refer to the Clause SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (FAR 52.236-3) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6.4 Maritime Traffic
Marine Traffic in the project area consists of Naval, commercial, pleasure, and small recreational vessels of all types and sizes which can be accommodated by existing depths.
1.6.5 Obstruction of Channel
The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of any vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon completion of the work, promptly remove the
SECTION 01 11 00 Page 3 plant, including ranges, buoys, piles, and other marks placed by him under the contract in navigable waters or on shore.
1.6.6 Hydrographic Surveys
Hydrographic surveys are provided on the ehydro web site:
https://www.arcgis.com/apps/opsdashboard/index.html#/4b8f2ba307684cf597617bf1b6d2f85d Survey numbers are indicated on the drawings.
1.7 CONTRACTOR ACCESS AND USE OF PREMISES
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
It should be recognized the requirements for security and base access varies between bases as well as between various locations within individual bases. It is incumbent on the Contractor to ascertain the current security and base access requirements appropriate to the project location and incorporate the cost, if any, for compliance to said requirements into Contractor's proposal. Lack of knowledge of current requirements does not constitute a basis for an adjustment to the contract.
Ensure that Contractor personnel employed on the activity become familiar with and obey activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless cleared by the Contracting Officer.
1.7.1 MARINE CORPS SUPPORT FACILITY - BLOUNT ISLAND (MCSF-BI) ENTRY
CONTROL REGULATIONS
1.7.1.1 Access
Marine Corps Support Facility Blount Island (MCSF-BI) has transitioned to the Defense Biometric Identification System (DBIDS). DBIDS is the Marine Corps Enterprise Access Control Solution that meets the USMC-mandated vetting requirements. The DBIDS credential/pass is no cost to the those requiring access to MCSF-BI for official business.
All contractors and vendors require sponsorship to come aboard MCSF-BI.
Before being granted access aboard MCSF-BI,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .