W32CS570880307

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Kissimmee River Restoration Project, S-69 Weir and Canal Backfill, Highlands and Okeechobee Counties, Florida

This amendment is being issued to:

1. Revise Volume 1 of 2, Section 00010A, Line Items and Pricing Schedule. See Page 2 of SF 30, Summary of Changes.

The proposal due date remains unchanged. All other conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Jul-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP-17-R-0018

X 9B. DATED (SEE ITEM 11)

21-Jun-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Jul-2017

CODE

USA ENGINEER DISTRICT, JACKSONVILLE

CONTRACTING DIVISION

701 SAN MARCO BLVD

JACKSONVILLE FL 32207-8175

W912EP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EP-17-R-0018

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

SF 30 CONTINUATION SHEET

Kissimmee River Restoration Project, S-69 Weir and Canal Backfill, Highlands & Okeechobee Counties, FLORIDA Amendment 0006

SUMMARY OF CHANGES

Changes to Specifications:

Volume 1 of 2 – Technical Specifications:

DELETE Section 00010A and REPLACE with the attached revised Section 00010A

(End of Summary of Changes)

KISSIMMEE RIVER RESTORATION PROJECT, S-69 WEIR AND CANAL BACKFILL

Okeechobee and Highlands Counties, Florida

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

0001 MOBILIZATION AND PREPARATORY WORK 1 JOB $_______________

0002 CLEARING AND GRUBBING 1 JOB $_______________

0003 ENVIRONMENTAL MONITORING 1 JOB $_______________

0004 TURBIDITY MONITORING 1 JOB $_______________

0005 SODDING 1 JOB $_______________

0006 LANDSCAPE 1 JOB $_______________

0007 SHELL-ROCK 1 JOB $_______________

0008 VIBRATION MONITORING - PRECONSTRUCTION SURVEY 1 JOB $_______________

0009 VIBRATION MONITORING - IMPLEMENTATION 1 JOB $_______________

0010 STEEL SHEET PILE 1 JOB $_______________

0011 CONCRETE ACCESS ROAD 1 JOB $_______________

0012 SAFETY BARRIERS, NAVIGATION AND 1 JOB $_______________

NO TRESPASSING SIGNS

0013 CONSTRUCTION OF PHASE 1 - BYPASS CONSTRUCTION 1 JOB $_______________

0014 REMOVAL/BACKFILLING OF PHASE 1- BYPASS CONSTRUCTION 1 JOB $_______________

0015 EXCAVATION AND SELECT FILL OF THE C-38 CANAL PLUG 1 JOB $_______________

PHASE 2 - CONSTRUCTION

0016 EXCAVATION AND CANAL BACKFILL 1,241,000 CUBIC YARD $_____________ $_______________ OF C-38 CANAL AND TRIBUTARIES (Estimate Quantity)

0017 EAST TIE-BACK LEVEE (Estimate Quantity) 20,700 CUBIC YARD $_____________ $_______________

0018 WEST TIE-BACK LEVEE (Estimate Quantity) 13,000 CUBIC YARD $_____________ $_______________

0019 FDOT DITCH LINER (Estimate Quantity) 3,800 SQUARE YARD $_____________ $_______________

0020 R 700 RIP RAP (Estimate Quantity) 3,700 SQUARE YARD $_____________ $_______________

0021 R 60 150 RIP RAP (Estimate Quantity) 3,700 SQUARE YARD $_____________ $_______________

0022 BEDDING STONE ON SUMP (Estimate Quantity) 4,100 SQUARE YARD $_____________ $_______________

0023 R 1500 RIP RAP (Estimate Quantity) 2,900 SQUARE YARD $_____________ $_______________

$_______________TOTAL (LINE ITEMS 0001 THROUGH 0023)

W912EP-17-R-0018 SECTION 00010A-1 Amendment 0006

KISSIMMEE RIVER RESTORATION PROJECT, S-69 WEIR AND CANAL BACKFILL

Okeechobee and Highlands Counties, Florida

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

NOTES: (1) ESTIMATED QUANTITIES FOR LINE ITEMS 0016 TO 0023, DO NOT INCLUDE TOLERANCES

(SEE SECTION 01 22 00). OFFERORS ARE RESPONSIBLE FOR CONSIDERING THE COST OF TOLERANCES THEY

REQUIRE, AND INCLUDE THESE COSTS IN THE UNIT PRICES FOR THE QUANTITIES INDICATED IN THESE LINE ITEMS.

(2) Actual Quantities for Line Items 0016 to 0023 may vary. See Clause 52.211-18 "Variation in Estimated Quantity" (Section 00700).

(3) All specification references to "Lump Sum" shall apply to line items indicating "JOB" as the unit (Line Items 0001 to 0015).

(4) Digital Terrain Models (DTM) and requisite raw data in XLM format are available for informational purposes only.

The Government assumes no responsibility for any apparent errors that may be present in the DTM or raw data;

nor does the Government assume responsibility for any conclusions or interpretations made by the Contractor based on the provided DTM or raw data. The DTM and raw data are available in compressed (zip) format for download by offerors with the solicitation on the Federal Business Opportunities (www.fbo.gov) web site.

The available information may include DTM surfaces for the existing site grades, excavation grades, and finished grades. The excavation DTM may not fully define surfaces related to temporary cuts required for site features such as stormwater management and erosion control components. Further, the excavation DTM may not reflect embankment foundation details such as soil benching. The finished DTM may not fully define surfaces related to site features such as storm water management and erosion control components. Further, the finished grade

DTM may not reflect embankment penetrations, internal embankment components such as seepage collection systems, nor embankment slope protection.

W912EP-17-R-0018 SECTION 00010A-2 Amendment 0004

Changes to Specifications: