W912EP-17-R-0008_Amendment_0003.pdf

PDF 28 MB Posted

Attached to
HERBERT HOOVER DIKE REHABILITATION PROJECT, REACH 1 CUTOFF WALL EXTENSION, PALM BEACH COUNTY, FLORIDA
Solicitation number
W912EP-17-R-0008
Issued by

About this file

Amendment 0003

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W32CS570057098

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Herbert Hoover Dike Rehabilitation Project, Reach 1 Cutoff Wall Extension, Palm Beach County, Florida

This Amendment is being issued for the follow ing:

See the attached SF30 Continuation page for details of this amendment.

The Proposal Due Date remains unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP-17-R-0008

X 9B. DATED (SEE ITEM 11)

18-Apr-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-May-2017

CODE

USA ENGINEER DISTRICT, JACKSONVILLE

CONTRACTING DIVISION

701 SAN MARCO BLVD

JACKSONVILLE FL 32207-8175

W912EP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SF 30 CONTINUATION SHEET

Herbert Hoover Dike Rehabilitation Project, Reach 1 Cutoff Wall Extension, Palm Beach County, Florida

W912EP-17-R-0008 2 Amendment 0003

SUMMARY OF CHANGES

Changes to Specifications:

Volume 1 of 2 – Contract Documents:

DELETE Section 00010A and REPLACE with the attached Section 00010A.

Volume 2 of 2 – Contract Specifications:

DELETE Section 00 31 32 and REPLACE with the attached Section 00 31 32.

DELETE Section 01 11 00 and REPLACE with the attached Section 01 11 00.

DELETE Section 01 22 00 and REPLACE with the attached Section 01 22 00.

DELETE Section 02 32 00 and REPLACE with the attached Section 02 32 00.

DELETE Section 02 32 10 and REPLACE with the attached Section 02 32 10.

DELETE Section 33 24 15 and REPLACE with the attached Section 33 24 15.

DELETE Section 35 41 00 and REPLACE with the attached Section 35 41 00.

DELETE Drawing No. C-13 and REPLACE with the attached Drawing No. C-13.

DELETE Drawing No. C-35 and REPLACE with the attached Drawing No. C-35.

Additional Documents:

Attached is the sign in sheet from the Site Visit.

(End of Summary of Changes)

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

HERBERT HOOVER DIKE REHABILITATION PROJECT

REACH 1 CUTOFF WALL EXTENSION

PALM BEACH COUNTY, FLORIDA

W912EP-17-R-0008 00010A-1 Amendment 0003

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

PHASE 1 (DEMONSTRATION SECTION, STATION 2569+00 TO STATION 2576+00)

0001 MOBILIZATION AND DEMOBILIZATION JOB $_______________

0002 WORK PLATFORM INSTALLATION

(ESTIMATED QUANTITY) 600 LINEAR FOOT $___________ $_______________

0003 WORK PLATFORM REMOVAL

(ESTIMATED QUANTITY) 600 LINEAR FOOT $___________ $_______________

0004 CUTOFF WALL (STA. 2570+00 TO STA. 2575+00)

(ESTIMATED QUANTITY) 29,000 SQUARE FOOT $___________ $_______________

0005 VERIFICATION CORING/TESTING

(ESTIMATED QUANTITY) 10 EACH $___________ $_______________

0006 STANDBY TIME 60 DAY $___________ $_______________

0007 CONTRACTING OFFICER'S FIELD OFFICE 47 MONTH $___________ $_______________

TOTAL PHASE 1 (LINE ITEMS 0001 THROUGH 0007) $_______________

PHASE 2 (STATION 2574+00 TO STATION 2698+00 AND STATION 2723+00 TO STATION 2908+00)

0008 MOBILIZATION AND DEMOBILIZATION JOB $_______________

0009 WORK PLATFORM INSTALLATION

(ESTIMATED QUANTITY) 30,700 LINEAR FOOT $___________ $_______________

0010 WORK PLATFORM REMOVAL

(ESTIMATED QUANTITY) 30,700 LINEAR FOOT $___________ $_______________

0011 CUTOFF WALL (STA. 2575+00 TO STA. 2697+00

AND STA. 2724+00 TO STA. 2907+00)

(ESTIMATED QUANTITY) 1,637,600 SQUARE FOOT $___________ $_______________

0012 VERIFICATION CORING/TESTING

(ESTIMATED QUANTITY) 123 EACH $___________ $_______________

0013 PIEZOMETERS JOB $_______________

0014 12" DIP REMOVAL JOB $_______________

0015 TRANSPORT STOCKPILE MATERIAL JOB $_______________

TOTAL PHASE 2 (LINE ITEMS 0008 THROUGH 0015) $_______________

TOTAL PHASES 1 AND 2 (LINE ITEMS 0001 THROUGH 0015) $_______________

SEE NEXT PAGE.

HERBERT HOOVER DIKE REHABILITATION PROJECT

REACH 1 CUTOFF WALL EXTENSION

PALM BEACH COUNTY, FLORIDA

W912EP-17-R-0008 00010A-2 Amendment 0003

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

PHASE 3 (STATION 2696+00 TO STATION 2725+00)

0016 WORK PLATFORM INSTALLATION

(ESTIMATED QUANTITY) 2,800 LINEAR FOOT $___________ $_______________

0017 WORK PLATFORM REMOVAL

(ESTIMATED QUANTITY) 2,800 LINEAR FOOT $___________ $_______________

0018 CUTOFF WALL (STA. 2697+00 TO STA. 2724+00)

(ESTIMATED QUANTITY) 150,320 SQUARE FOOT $___________ $_______________

0019 VERIFICATION CORING/TESTING

(ESTIMATED QUANTITY) 11 EACH $___________ $_______________

0020 PIEZOMETERS JOB $_______________

TOTAL PHASE 3 (LINE ITEMS 0016 THROUGH 0020) $_______________

TOTAL PHASES 1 THROUGH 3 (LINE ITEMS 0001 THROUGH 0020) $_______________

PHASE 4 (STATION 2566+00 TO STATION 2571+00)

0021 WORK PLATFORM INSTALLATION

(ESTIMATED QUANTITY) 400 LINEAR FOOT $___________ $_______________

0022 WORK PLATFORM REMOVAL

(ESTIMATED QUANTITY) 400 LINEAR FOOT $___________ $_______________

0023 CUTOFF WALL (STA. 2567+00 TO STA.2570+00)

(ESTIMATED QUANTITY) 17,400 SQUARE FOOT $___________ $_______________

0024 VERIFICATION CORING/TESTING

(ESTIMATED QUANTITY) 3 EACH $___________ $_______________

TOTAL PHASE 4 (LINE ITEMS 0021 THROUGH 0024) $_______________

TOTAL BID (LINE ITEMS 0001 THROUGH 0024) $_______________

SEE NOTES ON NEXT PAGE.

HERBERT HOOVER DIKE REHABILITATION PROJECT

REACH 1 CUTOFF WALL EXTENSION

PALM BEACH COUNTY, FLORIDA

W912EP-17-R-0008 00010A-3 Amendment 0003

NOTES: (1) SEE SECTION 00100 INSTRUCTIONS TO OFFERORS.

(2) OFFERORS MUST PRICE ALL LINE ITEMS.

(3) SEE CLAUSE "PREPRICING VARIATION IN ESTIMATED QUANTITY" PARAGRAPH 999.211-1 (SECTION 00800).

(4) THE STATIONS INDICATED FOR EACH PHASE INCLUDE THE CUTOFF WALL AND SUPPORTING FEATURES, SUCH AS THE WORK PLATFORM, WHICH MAY OVERLAP. STATIONS INDICATED IN THE "CUTOFF WALL" LINE ITEMS ARE

THE ACTUAL LIMITS OF CUTOFF WALL IN EACH PHASE.

(5) THE CONTRACTING OFFICER WILL ISSUE A SEPARATE NOTICE TO PROCEED (NTP) FOR EACH PHASE OF WORK.

HHD Rehabilitation Project, Reach 1 Cutoff Wall W912EP-17-R-0008 Extension, Palm Beach County, Florida

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

1.3.1.1 Phase 1

1.3.1.2 Phase 2

1.3.1.3 Phase 3

1.3.1.4 Phase 4

1.3.2 Order of Work

1.3.3 Location and Access

1.3.4 Safety Requirements

1.4 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

1.5 LIQUIDATED DAMAGES - CONSTRUCTION

1.6 PHYSICAL DATA

1.6.1 Physical Conditions

1.6.2 Weather and Water Stage Data

1.6.3 Contractor Investigation

1.6.4 Maritime Traffic

1.7 LAYOUT OF WORK

1.7.1 Established Project Control

1.7.2 Layout

1.7.3 Survey

1.8 DAMAGE TO WORK

1.9 EXISTING WORK

1.10 EXISTING UTILITIES

1.10.1 Under Ground Utility Location

1.10.2 Notification Prior to Excavation

1.10.3 Utilities at South Bay Boat Ramp

1.10.4 Utilities at Structure S-276

1.10.5 Piezometers

1.11 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)

1.11.1 Schedule of Monthly Anticipated Adverse Weather Delays

1.11.2 Contractor Responsibility

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 11 00 Page 1 Amendment 0003

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

GDR Section 00 31 32, Geotechnical Data Report For Herbert Hoover Dike Rehabilitation Project, Reach 1 Cutoff Wall Extension

EM 385-1-1 Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Temporary Turnout Plan ; G, RO

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

The work includes constructing 6.5 miles of cutoff walls in Reach 3 (Segments 1, 2, and 3) of the Herbert Hoover Dike (HHD) embankment from South Bay to Lake Harbor. Work is divided into phases as follows:

1.3.1.1 Phase 1

The limits of construction are from Station 2569+00 to Station 2576+00 to allow for construction and removal of the construction platform. Cutoff wall construction is from Station 2570+00 to Station 2575+00 (Demonstration Section).

1.3.1.2 Phase 2

The limits of construction are from Station 2574+00 to Station 2698+00 and Station 2723+00 to Station 2908+00 to allow for construction and removal of the construction platform. Cutoff wall construction is from Station 2575+00 to Station 2697+00 and Station 2724+00 to Station 2907+00.

SECTION 01 11 00 Page 2 Amendment 0003

1.3.1.3 Phase 3

The limits of construction are from Station 2696+00 to Station 2725+00 to allow for construction and removal of the construction platform. Cutoff wall construction is from Station 2697+00 to Station 2724+00.

1.3.1.4 Phase 4

The limits of construction are from Station 2566+00 to Station 2571+00 to allow for construction and removal of the construction platform. There is an adjacent Construction Contractor whose work begins at Station 2567+00 and proceeds north. This contract has been structured with Phasing such that adjacent work efforts (by others) are complete minimizing the potential for overlapping work efforts. Cutoff wall construction is from Station 2567+00 to Station 2570+00.

1.3.2 Order of Work

The Contractor will receive a separate Notice to Proceed (NTP) for each phase of work. The first NTP will be to construct a 500 linear feet cutoff wall demonstration section as shown (Phase 1). Once the demonstration section is accepted by the Government, NTP for Phase 2 will be issued. Subsequent NTPs may be issued prior to completion of Phase 2.

1.3.3 Location and Access

The project area is located on the south side of Lake Okeechobee between South Bay and Lake Harbor in Palm Beach County, Florida.

The Contractor's entrances are shown on the drawings and are shared by others. The Contractor shall comply with all language contained within the Rights of Entries obtained by the United States Army Corps of Engineers (USACE). The Contractor is responsible for obtaining and complying with all Federal, State, County, and any other jurisdictional agency, requirements for permits, criteria, and use. The South Bay Boat Ramp existing access ramps as shown shall not be used for construction.

For construction access, construct access ramps and turn-around to accommodate construction equipment and construction means and methods.

While working in or driving through the limits of the South Bay Boat Ramp (Station 2637+00 to Station 2647+00), the Contractor shall use flagmen to direct and coordinate all traffic movement within the limits of the South Bay Boat Ramp.

For access and traffic control along the crest of HHD, the Contractor may elect to design and construct temporary turnouts every 1000 feet along the embankment. If so elected, the Contractor must provide a design and submit a Temporary Turnout Plan for approval by the government prior to commencement of work. The plan shall comply with the requirement of Haul Road prescribed in Specification Section 01 50 02 Temporary Construction Facilities.

The Contractor may utilize area within the limits of construction as laydown areas. The limits of construction are shown. If the lakeside slope of the embankment is used, the lakeside slope will be subject to lake-stage, lake-surge and lake-waves which may inundate the lakeside slope, see specification section 00 33 50 .

SECTION 01 11 00 Page 3 Amendment 0003

1.3.4 Safety Requirements

See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1 .

1.4 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. Read this paragraph in conjunction with the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1.

b. In addition to the above, the following shall apply: The time for completion does not include establishment of grass. Grass shall be established not later than the time stated in the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1 plus the time stated for the establishment of grass as set forth in the paragraph SOD ESTABLISHMENT PERIOD of Section 32 92 23 SODDING.

1.5 LIQUIDATED DAMAGES - CONSTRUCTION

Refer to the Clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12) of Section 00700 CONTRACT CLAUSES in Volume 1.

1.6 PHYSICAL DATA

Read this paragraph in conjunction with the Clause PHYSICAL DATA (FAR 52.236-4) of Section 00700 CONTRACT CLAUSES in Volume 1.

1.6.1 Physical Conditions

The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and/or by core borings. When the indicated physical conditions are the result of site investigations by core borings, the core boring logs and laboratory data are in Section 00 31 32 GEOTECHNICAL DATA REPORT ( GDR) and the core boring locations are shown on the drawings. Also, see the GDR for instructions concerning availability of core borings for inspection.

1.6.2 Weather and Water Stage Data

See Section 00 33 50 WEATHER AND WATER STAGE DATA. It is the Contractor's responsibility to obtain information concerning wind and rain.

1.6.3 Contractor Investigation

Refer to the Clause SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (FAR 52.236-3) of Section 00700 CONTRACT CLAUSES in Volume 1.

1.6.4 Maritime Traffic

It is anticipated that there will be no impacts to maritime traffic.

1.7 LAYOUT OF WORK

Read this paragraph in conjunction with the Clause LAYOUT OF WORK (FAR 52.236-17) of Section 00700 CONTRACT CLAUSES in Volume 1.

SECTION 01 11 00 Page 4 Amendment 0003

1.7.1 Established Project Control

The Government has established monuments along the work site(s). Each monument is represented in the contract drawings by a Designation and in most cases, an alphanumeric Permanent Identifier (PID). Information concerning the location and elevations can be found within the Survey Notes on the plan sheets. The Survey Notes for each included field survey will cite a particular survey number, and specify the control used to conduct that survey. Additional information is included in the Survey Notes that must be duplicated if an attempt to recreate the subject survey is desired.

See Section 00 31 21 CONTROL MONUMENT DESCRIPTIONS.

1.7.2 Layout

From the monuments, control data and elevations established by the Government, the Contractor shall complete the layout of the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work.

1.7.3 Survey

The Contractor shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and material, and all labor as may be required in laying out any part of the work from the monuments, control data and elevations established by the Government. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks established by the Contracting Officer until authorized to remove them, and if such marks are destroyed by the Contractor or through his negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor.

The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.

1.8 DAMAGE TO WORK

The responsibility for damage to any part of the permanent work shall be as set forth in Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES in Volume 1. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to Clause CHANGES of Section 00700 CONTRACT CLAUSES in Volume 1 will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or lump sum prices. Except as herein provided, damage to all work (including temporary construction), SECTION 01 11 00 Page 5 Amendment 0003 utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.

1.9 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.10 EXISTING UTILITIES

1.10.1 Under Ground Utility Location

All underground utilities within the work limits must be positively identified in accordance with the American Society of Civil Engineers, Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data (latest edition). All underground utilities within the work limits must be positively identified by a private utility locating service and coordinated with the Government. Any utilities found which are not shown on the construction drawings must be brought to the Contracting Officer's attention prior to proceeding with construction.

The Contractor shall coordinate service disconnections of active utilities with the Contracting Officer at least 30 days prior to impacting the utility with construction activities and shall provide weekly progress updates until such time that the utility is taken out of service. The progress update shall include the date at which the active utility impacts construction such that there is no disruption to the Contractor's work and progress.

1.10.2 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work. Contact utility authority 15 days prior to excavating.

Contractor is responsible for marking all utilities not marked by utility authority.

1.10.3 Utilities at South Bay Boat Ramp

At the South Bay Boat Ramp there is an inactive 12 inch ductile iron pipe, raw waterline, crossing the cutoff wall alignment. The Contractor shall remove this pipe and appurtenant features from the embankment to the limits shown. Abandon any portion of pipe not removed in accordance with Section 02 41 00 DEMOLITION. The excavation shall be backfilled with compacted soil in accordance specification section 35 41 00 EMBANKMENT

CONSTRUCTION.

1.10.4 Utilities at Structure S-276

At Structure S-276 there are underground utilities buried approximately 3

SECTION 01 11 00 Page 6 Amendment 0003 feet deep. The Contractor shall coordinate through the Contracting Officer with Operations Division staff to de-energize and secure the utilities. The Contractor shall remove the wires from each (6 are expected) conduit, remove a section from each conduit as required to install cutoff wall beneath the conduits. Once the cutoff wall is installed, install the section of removed conduit and install the wires as they were prior to construction.

1.10.5 Piezometers

Protect existing piezometers during construction. Should an existing piezometer become damaged, the Contractor shall provide piezometer(s) in accordance with Section 02 32 10 SUBSURFACE DRILLING AND SAMPLING FOR PIEZOMETER INSTALLATION at no cost to the Government. Existing piezometers shown shall be automated in accordance with Section 33 24 15

VIBRATING WIRE PIEZOMETERS.

1.11 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)

This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Clause DEFAULT (FIXED-PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

1.11.1 Schedule of Monthly Anticipated Adverse Weather Delays

The schedule of monthly anticipated adverse weather delays is based upon National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location for a daily precipitation greater than or equal to

0.50 inches and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

See Section 00 33 50 WEATHER AND WATER STAGE DATA to obtain MONTHLY

ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON 5-DAY WORK WEEK.

1.11.2 Contractor Responsibility

Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily CQC report the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in Section 00 33 50 WEATHER AND WATER STAGE DATA (rounded to the nearest whole number), the Contracting Officer will convert any qualifying delays

SECTION 01 11 00 Page 7 Amendment 0003 to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Clause DEFAULT (FIXED PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 11 00 Page 8 Amendment 0003

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUMMARY

1.2 QUALITY CONTROL SYSTEM (QCS)

1.2.1 Definition

1.2.2 Instructions

1.3 SUBMITTALS

1.4 LUMP SUM PAYMENT ITEMS

1.4.1 Mobilization and Demobilization (Line Items 0001 and 0008)

1.4.2 Piezometers (Line Items 0013 and 0020)

1.4.3 12" DIP Removal (Line Item 0014)

1.4.4 Transport Stockpile Material (Line Item 0015)

1.5 UNIT PRICE PAYMENT ITEMS

1.5.1 Work Platform Installation (Line Items 0002, 0009, 0016 and

0021)

1.5.1.1 Payment

1.5.1.2 Measurement

1.5.1.3 Unit of Measure

1.5.2 Work Platform Removal (Line Items 0003, 0010, 0017 and 0022)

1.5.2.1 Payment

1.5.2.2 Measurement

1.5.2.3 Unit of Measure

1.5.3 Cutoff Wall (Line Items 0004, 0011, 0018 and 0023)

1.5.3.1 Payment

1.5.3.2 Measurement

1.5.3.3 Unit of Measure

1.5.4 Verification Coring/Testing (Line Items 0005, 0012, 0019 and

0024)

1.5.4.1 Payment

1.5.4.2 Measurement

1.5.4.3 Unit of Measure

1.5.5 Standby Time (Line Item 0006)

1.5.5.1 Payment

1.5.5.2 Unit of Measure

1.5.6 Contracting Officer's Field Office (Line Item 0007)

1.5.6.1 Payment

1.5.6.2 Measurement

1.5.6.3 Unit of Measure

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 PAYMENT PROCEDURES

3.1.1 Requesting Progress Payment

SECTION 01 22 00 Page 1 Amendment 0003

3.1.2 Options and Modification CLINS

SECTION 01 22 00 Page 2 Amendment 0003

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUMMARY

This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.

Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved. Unless there is a specific Line Item for administrative costs, such as Quality Control and Safety, allocate such costs proportionally across all Line Items.

1.2 QUALITY CONTROL SYSTEM (QCS)

1.2.1 Definition

The terms "Contract Line Item Number (CLIN)" and "Line Item" are interchangeable herein (e.g.: CLIN 0001 is Line Item 0001). The term "CLIN" is a contracting term used in the Quality Control System (QCS) payment data base.

1.2.2 Instructions

See Section 01 45 04 C0NTRACTOR QUALITY CONTROL for instructions on linking a CLIN to a schedule of values of pay activities and construction schedule, and in-depth payment procedure.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:

SD-01 Preconstruction Submittals

Schedule of Values ; G, RO

Provide a breakdown of lump sum items into proposed pay activities as part of the initial project schedule. Schedule of Values will become basis for CLIN and Pay Activity data in the QCS payment data base.

SECTION 01 22 00 Page 3 Amendment 0003

1.4 LUMP SUM PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

Progress payments for lump sum CLINs will be made in accordance with the Payments Under Fixed-Price Construction Contracts clause of Section 00700 CONTRACT CLAUSES in Volume 1. Submit a list of pay activities, (Schedule of Values) to breakdown bid for each lump sum CLIN. The Schedule of Values shall be submitted for Government approval with the baseline schedule submittal (see Section 01 32 01 PROJECT SCHEDULE). An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, the Contractor should take into account the amount reserved for contract payments when preparing the construction schedule.

1.4.1 Mobilization and Demobilization (Line Items 0001 and 0008)

Payment will be made for costs associated with or incidental to mobilization and demobilization and establishment of initial project management and coordination associated with each Notice to Proceed (NTP).

See Clause PAYMENT FOR MOBILIZATION AND DEMOBILIZATION of Section 00700 CONTRACT CLAUSES in Volume 1.

1.4.2 Piezometers (Line Items 0013 , and 0020 and 0025 )

Payment will be made for costs and materials associated with or incidental to the installation of automating existing piezometers.

1.4.3 12" DIP Removal (Line Item 0014)

Payment will be made for costs associated with or incidental to the removal of the 12" DIP, pipe valves, pump house and pilings. Also included are costs associated with or incidental to restoring the embankment, including surface treatments as related to the DIP and pump house removal.

1.4.4 Transport Stockpile Material (Line Item 0015)

Payment will be made for costs associated with or incidental to transport of stockpile material as shown on the drawings. Also included are costs associated with or incidental to restoring the embankment, including surface treatments as related to stockpile removal.

1.5 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE and described below. The unit price and payment made for each

SECTION 01 22 00 Page 4 Amendment 0003 item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

Each Unit Price CLIN may be a single pay activity item or may be broken down into pay activities with smaller quantities equal to CLIN total.

Contract unit price multiplied by agreed quantity is full compensation.

1.5.1 Work Platform Installation (Line Items 0002, 0009, 0016 and 0021)

1.5.1.1 Payment

Payment will be made for costs associated with or incidental to borrow, transportation, placement, maintenance of earthen construction platforms.

Payment under this line item includes but is not limited to geotextile, sod as required to stabilize the platform side slope; erosion control measures and erosion control monitoring.

1.5.1.2 Measurement

Work platform installation will be measured for payment by the length placed and maintained.

1.5.1.3 Unit of Measure

Linear foot.

1.5.2 Work Platform Removal (Line Items 0003, 0010, 0017 and 0022)

1.5.2.1 Payment

Payment will be made for costs associated with or incidental to removal, transportation, and disposal of earthen construction platforms after completion of cutoff wall construction. Payment under this line item includes but is not limited to removal and disposal of geotextile and any other material used to stabilize the platform side slope. Payment under this line item includes site restoration of the embankment to pre-existing lines and grades to include embankment fill, topsoil, sod, sod establishment, and noise control. Pre-existing lines and grades will be indicated on drawings within each work limit from surveys obtained by the Government.

1.5.2.2 Measurement

Work platform removal will be measured for payment by the length removed, including satisfactory restoration of the site.

1.5.2.3 Unit of Measure

Linear foot.

1.5.3 Cutoff Wall (Line Items 0004, 0011, 0018 and 0023)

1.5.3.1 Payment

Payment will be made for costs associated with or incidental to placement of the cutoff wall.

SECTION 01 22 00 Page 5 Amendment 0003

1.5.3.2 Measurement

Cutoff wall will be measured for payment by the area satisfactorily placed.

1.5.3.3 Unit of Measure

Square foot.

1.5.4 Verification Coring/Testing (Line Items 0005, 0012, 0019 and 0024)

1.5.4.1 Payment

Payment will be made for costs associated with or incidental to verification drilling and testing.

1.5.4.2 Measurement

Verification coring and testing will be measured for payment by the number of cores taken and tested.

1.5.4.3 Unit of Measure

Each.

1.5.5 Standby Time (Line Item 0006)

1.5.5.1 Payment

Standby time will be paid for each calendar day as exercised by the Contracting Officer. Standby time shall be associated with and incidental to the verification testing and acceptance for the Demonstration Section.

1.5.5.2 Unit of Measure

Day.

1.5.6 Contracting Officer's Field Office (Line Item 0007)

1.5.6.1 Payment

Payment will be made for costs associated with or incidental to providing, maintaining, and final disposition of the Contracting Officer's field office including all costs for rent and provision of all services indicated in Section 01 52 10 CONTRACTING OFFICER'S FIELD OFFICE. Costs for such provision and maintenance of the Contractor's own field office and other facilities will not be paid for under this line item.

1.5.6.2 Measurement

The basis for payment will be the amount of time that the Contracting Officer's field office is available to the Government within the duration of the contract.

1.5.6.3 Unit of Measure

Month.

SECTION 01 22 00 Page 6 Amendment 0003

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 PAYMENT PROCEDURES

Upon receiving initial Resident Management System import file, go to "Pay Activities" and establish a link between bid breakdown schedule of values of "Pay Activities" to contract CLINs using "Schedule Activities" data entry page.

3.1.1 Requesting Progress Payment

For progress payments, ensure "Activity Schedule", "Feature Schedule", submittal register, and punchlists are all up to date. Use "Progress Payments" to "request Activity Earnings" for both "Activity Earnings" data entry page and "Other Earning". Provide hard copies of supporting invoices and quantity measurements to support all requested earnings.

Ensure that sum of payment activities do not exceed contract award CLIN funding amounts, or "unbalanced" CLINs error will prevent processing the payment.

3.1.2 Options and Modification CLINS

When additional work is added by modification, existing CLINs funding amounts must be updated, or new CLINs for modification will be created.

If contract has option CLINs not yet awarded, option CLINs will appear as zero dollar CLINs until option is awarded by modification. No payment may be requested for Options or Modification CLINs until contract modification has been funded and signed.

SECTION 01 22 00 Page 7 Amendment 0003

SECTION TABLE OF CONTENTS

DIVISION 02 - EXISTING CONDITIONS

SECTION 02 32 00

VERIFICATION DRILLING AND PERMEABILITY TESTING OF IN-PLACE CUTOFF WALL

PART 1 GENERAL

1.1 REFERENCES

1.2 SYSTEM DESCRIPTION

1.2.1 Core Drilling

1.2.2 In-situ Permeability Testing

1.3 SUBMITTALS

1.4 SEQUENCING AND SCHEDULING

1.5 QUALIFICATIONS

1.5.1 Driller

1.5.2 Borehole Logger

1.5.3 Hydrogeologist

1.5.4 Borehole Camera Specialist

PART 2 PRODUCTS

2.1 CORE BOXES

2.2 LABELS

2.3 BOREHOLE CAMERAS

2.3.1 First Borehole Camera

2.3.2 Second Borehole Camera

2.4 Electronic Water Level Gauge (Pressure Troll)

PART 3 EXECUTION

3.1 EQUIPMENT AND SUPPLIES

3.1.1 Core Drilling

3.1.2 In-Situ Permeability Testing

3.2 CORE DRILLING

3.2.1 Procedure

3.2.2 Casing Installation

3.2.3 Drilling Deviation Measurements

3.2.4 Arrangement of Core

3.2.5 Preservation of Core

3.2.6 Labeling, Marking and Packing Core

3.2.7 Selection of Test Samples

3.2.7.1 Compressive Strength Testing

3.2.7.2 Laboratory Permeability Testing

3.2.8 Disposition of Core

3.3 IN-SITU PERMEABILITY TESTING

3.3.1 Test Coordination and Documentation

3.3.2 Permeability Testing

3.3.3 Stage 1 Falling Head Test for Cutoff Wall

3.3.4 Stage 2 Water Pump Test/Rising Head Recovery for Cutoff Wall

3.4 DISPOSITION OF BOREHOLES WITH APPROVED TESTS

3.5 ABANDONED AND SUPPLEMENTAL VERIFICATION BORINGS

SECTION 02 32 00 Page 1 Amendment 0003

3.6 DECOMMISSIONING

3.7 RECORDS

3.7.1 360-degree Video Recording

3.7.2 Vertical Video Recording

3.8 FIGURE 1 - REPORT OF FALLING HEAD PERMEABILITY TEST

SECTION 02 32 00 Page 2 Amendment 0003

SECTION 02 32 00

VERIFICATION DRILLING AND PERMEABILITY TESTING

OF IN-PLACE CUTOFF WALL

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C511 Standard for Mixing Rooms, Moist Cabinets, Moist Rooms, and Water Storage. Tanks Used in the Testing of Hydraulic Cements and Concretes.

ASTM D2113 (2008) Rock Core Drilling and Sampling of Rock for Site Investigation

ASTM D2166 (2006) Standard Test Method for Unconfined Compressive Strength of Cohesive Soil

ASTM D5084 (2010) Measurement of Hydraulic Conductivity of Saturated Porous Materials Using a Flexible Wall Permeameter

1.2 SYSTEM DESCRIPTION

The Contractor shall provide verification drilling and sampling (verification borings) of the completed cutoff wall to determine the continuity, homogeneity, in-situ permeability of the cutoff wall, and to obtain samples of sufficient quality for required laboratory testing. This is to be accomplished by means of core drilling and permeability testing.

The equipment and techniques to be used shall be submitted in the Drilling Plan .

Verification borings shall be drilled at depths and locations directed by the Contracting Officer. Laboratory testing of wet grab samples will supplement the testing from verification borings. Permeability tests shall be performed in-situ for each open hole. Borehole Camera surveys of the entire verification boring shall be performed concurrently with the rising head stage of tests on constructed cutoff wall. For use in determining the in-situ permeability of the cutoff wall, groundwater level monitoring wells shall be installed adjacent to each verification boring for monitoring external groundwater levels.

1.2.1 Core Drilling

Drilling of cores shall be by any approved standard and accepted method of rotary core drilling ( ASTM D2113) that will provide continuous and complete cores of the required diameter over the entire depth of the

SECTION 02 32 00 Page 3 Amendment 0003 constructed cutoff wall. The method used shall provide excellent recovery of cores from the cutoff wall with potential sand lenses and unmixed zones, and not cause damage to the cutoff wall.

1.2.2 In-situ Permeability Testing

In-situ permeability testing is the process of introducing water into or extracting water out of the cutoff wall through verification borings for the purpose of determining the in-situ permeability of the cutoff wall.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Drilling Plan ; G, DO

Prior to starting work, the Contractor shall submit a plan for drilling, sampling, testing, and safety. The plan shall include, but not be limited to; the proposed method of drilling and sampling including a description of the sampling and testing tools that will be used, a listing of any subcontractors to include a description of how the subcontractors are to be used and a description of all methods and procedures to be utilized to ensure a safe operation and to protect the environment. The plan shall also include installation methods, type, location, and tip elevation of water level monitoring wells. This submittal shall also include a statement of the prior experience, in the type of work described in these specifications, of the Borehole Logger(s) and Driller(s) designated to perform the work specified herein. No work shall be performed until this plan has been approved and no deviation from the approved plan will be permitted without prior approval by the Contracting Officer. Coordinate the Drilling Plan with Section 01 57 50 DRILLING PROGRAM PLAN.

Verification Boring Reports ; G, DO

The Contractor shall submit for each complete verification boring, legible copies of verification boring reports in accordance with paragraph RECORDS below.

In-Situ Permeability Testing Plan ; G, DO

The Contractor shall submit a plan for in-situ permeability testing. The plan shall include, but not be limited to; a description of all methods and procedures for performing the in-situ permeability testing, data reduction, equations, all assumptions used to determine the permeability of the cutoff wall, manufacturer's data specification sheets for all equipment and materials to be used, and calibration certificates less than 60 days old from the start of testing on all pressure gauges and flow meters used during the in-situ testing.

Include/describe in this plan the following:

SECTION 02 32 00 Page 4 Amendment 0003

a) Proposed methods and procedures for performing in-situ permeability testing. Include the proposed form used to document time and water level readings and other data pertinent to permeability testing.

b) Procedures for collecting and analyzing all flow rate-time-water level data from the falling head tests (Stage 1), which will be used to calculate the in-situ permeability of the cutoff wall above the groundwater table.

c) Procedures for collecting and analyzing all flow rate-time-water level data from the Stage 2 rising head recovery test, which will be used to calculate the in-situ permeability of the cutoff wall below the groundwater table.

d) The in-hole submersible pump size, geometry, characteristic curves, and manufacturer's operating manuals for the Stage 2 phase of testing of the cutoff wall. The selected pumping equipment shall eliminate any electromagnetic influence that could affect the resolution of the borehole camera.

e) Sketches detailing how all equipment (pump, camera, and pressure troll) will be simultaneously inserted into the borehole for observing the quality of the in-situ cutoff wall under external water pressure during Stage 2 testing.

f) Details of how the water level will be kept low enough during Stage 2 testing to accommodate a full borehole camera survey in a dry hole.

BOREHOLE CAMERAS; G, DO

Provide manufacturer's data specification sheets and operating manuals for the borehole camera(s) to be used for the borehole surveys described in PRODUCTS below. Indicate in the submittal the capabilities of the encoder to provide date and time stamps on the video.

Electronic Water Level Gauge (Pressure Troll) ; G, DO

Provide manufacturer's data specification sheets and operating manuals for the electronic water level gauge (pressure troll) as described in PRODUCTS below.

Casing Installation Plan ; G, DO

Submit a plan detailing the installation process for the required continuous steel or PVC casing that connects the top of the work platform to the top of the cutoff wall for QC testing. This plan shall indicate the methodology for casing installation, size and length of casing, and the means of providing a watertight seal between the casing and top of the cutoff wall as described in paragraph CASING INSTALLATION below. The casing size provided shall be large enough to accommodate all testing and inspection equipment. If steel casing is used, the Contractor shall ensure that the appropriate camera type and/or precautions are taken to eliminate interference with downhole cameras.

SECTION 02 32 00 Page 5 Amendment 0003

SD-06 Test Reports

Core Disposal Notification

Notify the Contracting Officer 30 calendar days prior to disposal of cores as required in subparagraph "Disposition of Core" in paragraph CORE DRILLING below.

1.4 SEQUENCING AND SCHEDULING

Acceptance of a segment of cutoff wall will not be approved until the verification drilling and testing is performed and the performance requirements are satisfied. Cutoff wall construction shall not extend greater than 9000 linear feet beyond the closest accepted verification boring. The Contractor shall plan activities accordingly.

a. The location of verification borings at each cutoff wall location shall be determined by the Contracting Officer. Verification boring locations will be determined within ten (10) days after placement of cutoff wall.

b. Verification borings may be added or deleted as required by the Contracting Officer. For bidding purposes, assume at least one verification borings will be performed every 250 linear feet (LF) of cutoff wall constructed. One verification boring will be required at each connection to existing cutoff wall for record only. A minimum of ten (10) verification borings shall be performed in the Demonstration Section.

c. Additional verification borings that exceed the quantity above will be paid at the unit rate.

1.5 QUALIFICATIONS

1.5.1 Driller

The driller shall have experience using cutoff wall drilling equipment similar to the equipment to be used for this contract. The experience shall include a minimum of 2 projects of depths greater than 60 feet and a minimum length of 1000 feet using equipment similar to that being used for this contract.

1.5.2 Borehole Logger

Provide a qualified Borehole Logger, either a Geologist or Geotechnical Engineer, licensed in the any state, if not signing and sealing the report, experienced in subsurface exploration to oversee all drilling, sampling, and in-situ testing operations. A State of Florida license is required only if the individual is signing and stamping the documents.

This individual shall also be responsible for the preparation of all samples for delivery.

The presence of a Government representative or the keeping of separate drilling records by the Contracting Officer shall not relieve the Contractor of the responsibility for the work specified in this specification.

SECTION 02 32 00 Page 6 Amendment 0003

1.5.3 Hydrogeologist

The Hydrogeologist shall be an individual who has had experience with at least 5 projects of cutoff wall or bottom seal construction requiring in-place permeability testing using the methods proposed for this contract. A qualified geologist or geotechnical engineer can also serve as the Hydrogeologist.

1.5.4 Borehole Camera Specialist

Provide a qualified Borehole Camera Specialist with applicable demonstrated experience on at least 3 projects (performed within 5 years of NTP) in the operation and maintenance of borehole cameras and field operated video recording equipment.

PART 2 PRODUCTS

2.1 CORE BOXES

Longitudinally partitioned, hinged top, core boxes shall be used for all cores.

2.2 LABELS

Core boxes shall be identified by permanent marker or stenciled labels.

The information on this label shall contain the following:

PROJECT: HERBERT HOOVER DIKE REHABILITATION, REACH 1 CUTOFF WALL

EXTENSION PROJECT

HOLE NO.: STATION __________

CORE DEPTH: __________ to __________

BOX NO.: __________

TOTAL NUMBER OF BOXES FOR THE HOLE: __________

2.3 BOREHOLE CAMERAS

Two types of borehole cameras are required:

2.3.1 First Borehole Camera

The first borehole camera is for making a 360 degree log of the verification boring. The camera shall meet the following minimum requirements:

TYPE: Digital Optical Borehole Televiewer.

FRAME RATE: 20HZ.

EXPOSURE: 6.

LIGHTING: 10.

RESOLUTION: 900 pixels.

LOGGING SPEED: 2.9 feet/minute.

SECTION 02 32 00 Page 7 Amendment 0003

2.3.2 Second Borehole Camera

The second borehole…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .