A22.SOW_REFERENCE_13_Installation_and_Testing_Report_6.27.2018.pdf
PDF 1 MB Posted
- Attached to
- Rice Lake Pump Repairs & MCC Evaluation Federal contract opportunity
- Solicitation number
- W912EK19T0038
About this file
SOW reference 13
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLOW-TECHNICS, INC.
Installation (Item 2) and
Testing (Item 3) Report
For
U.S. Army Corps of Engineers
Rice Lake Habitat
Banner, IL
Submitted by:
FLOW – TECHNICS, INC.
Frankfort, IL.
PHONE: 815-277-2600
FAX: 815-534-5311
6/27/2018
Delivery:
On June 19, 2018 pump was loaded onto flatbed for delivery to Banner, IL.
Pump offloaded and transferred to pump deck.
On June 20, 2018 pump was wired for dry test and installed.
Dry Test Power Readings:
Dry Test Noise Reading:
Dry Test Vibe Reading:
Installation:
Pump set into tube.
Pump and cables were installed and also the tube cover.
Testing:
On June 21, 2018 wet test was performed.
Start of wet test power reading: Start of wet test noise reading:
Start of wet test vibe reading:
30 minutes into wet test power reading: 30 minutes into wet test noise reading:
30 minutes into wet test vibe reading:
End of wet test power reading (1hr): End of wet test noise reading (1hr):
End of wet test vibe reading (1hr):
On June 25, 2018 flow testing was performed by the U.S. Army Corp. of Engineers.
See below for location of flow sensor.
River level was 14.5” above pump deck. Discharge creek water level was 43.5” below discharge structure top wall.
Tube drawing:
U.S. Army Corp. of Engineers took flow readings for 5 minutes. Their readings averaged out to be 62,506.875 gpm.