A22.SOW_REFERENCE_10__Pre-Service_Survey_Report_2.23.2018.pdf
PDF 311 KB Posted
- Attached to
- Rice Lake Pump Repairs & MCC Evaluation Federal contract opportunity
- Solicitation number
- W912EK19T0038
About this file
SOW reference 10
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLOW-TECHNICS, INC.
Evaluation Report
For
U.S. Army Corps of Engineers
Rice Lake Habitat
Banner, IL
Submitted by:
FLOW – TECHNICS, INC.
Frankfort, IL.
PHONE: 815-277-2600
FAX: 815-534-5311
2/23/2018
Pre-Service Survey
On Wednesday, February 21, 2018, Flow-Technics’ Service Technicians located to Rice
Lake Wildlife Habitat in Banner, Illinois to document the site conditions of the property, junction box electrical connections and electrical conductors within the pumps discharge tube.
Evaluation
All power leads to stator are megging grounded.
Power lines from junction box back to building are megging 200+ @ 1000V.
Connection chamber probe meggs at 200+ @ 200V.
Stator Housing probe megs 10 megs @ 200V.
Seal Chamber probe megs 100 megs @ 200V.
Pump cables were pulled and showed no visible signs of damage. The pump was pulled out of the tube and no obstruction was seen in the propeller area. The pump was set by the road due to rising river level. The connection chamber was opened and looked good.
On Thursday, February 22, 2018 the pump was prepared for transport to the evaluation facility.
The pump was delivered to the evaluation facility on Thursday, February 22, 2018 and will be torn down and evaluated the week of February 26, 2018 upon the approval of the
Army Corp. of Engineers.
File details come from the government source that posted it.