This amendment modifies a solicitation for the Lower Monumental Navigation Lock Power and Controls Upgrade project. The U.S. Army Corps of Engineers Walla Walla District will replace aging electrical equipment and controls at the Lower Monumental Lock and Dam in Franklin County, Washington. Key changes include extending the response deadline to June 21, 2022, revising site restrictions and outage windows, and updating the wage determination. Offerors must provide construction services including demolition and installation of new medium and low voltage switchgear, motor controls, transformers, feeders, and an HMI system. The work must be completed during an extended outage from January 15 to March 29, 2024 to minimize river traffic impacts. The solicitation will result in a single firm fixed-price construction contract with performance and payment bonds required. The estimated value is between $5-10 million.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0005 TechSpecs.pdf | ||
| W912EF22R0002_Site Visit Sign-In Sheet.pdf | ||
| Amendment 0004 Supplemental Drawings.pdf | ||
| Amendment 0004 TechSpecs.pdf | ||
| Amendment 0004 Plans.pdf | ||
| Amendment 0004 W912EF22R0002.pdf | ||
| Amendment 0003 W912EF22R0002.pdf | ||
| Amendment 0002 W912EF22R0002.pdf | ||
| Amendment 0001 W912EF22R0002.pdf | ||
| Brand Name Determination SEL Equip W912EF22R0002 Redacted.pdf | ||
| Site Visit Info W912EF22R0002.pdf | ||
| Solicitation W912EF22R0002.pdf | ||
| Plans W912EF22R0002 LMA Navlock Power Controls Upgrade.pdf | ||
| Tech Specs W912EF22R0002 LMA Navlock Power Controls Upgrade.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912EF22R0002, Low er Monumental Navigation Lock Pow er and Controls Upgrade
The solicitation is amended as follow s:
See Continuation Page for details.
1. CONTRACT ID CODE PAGE OF PAGES
1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Jun-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EF22R0002
X 9B. DATED (SEE ITEM 11)
28-Apr-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Jun-2022
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
DAVID C BOONE 201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF22R0002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0005
Summary of changes for Amend-0005 Lower Monumental Navigation Lock Power and Controls Upgrade
1) Revised the following Specifications:
a) SECTION 01 14 00.10 28 PROJECT SITE RESTRICTIONS
i) Revised paragraph 1.3 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS.
(1) Renumbered subparagraphs.
See revised specifications for details.
2) Revised the following Clause:
a) 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
See Yellow Highlights.
3) The required response date/time has changed from 20-Jun-2022 03:00 PM to 21-Jun-2022 03:00 PM.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 20-Jun-2022 03:00 PM to 21-Jun-2022 03:00 PM.
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to
a) Commence work under this contract within 10 calendar days after the date the Contractor receives the Notice to Proceed (NTP),
b) prosecute the work diligently, and
c) complete the entire work ready for use not later than the dates listed below.
WORK WINDOWS:
Navigation Lock Pre-Outage Work Window: 0600 1 December 2023, through 1700 14 January 2024.
Navigation Lock Outage Work Window: 0600 15 January 2024, through 1700 29 March 2024.
See SECTION 01 14 00.10 28 PROJECT SITE RESTRICTIONS, paragraph SITE CONDITIONS AND OPERATIONAL RESTRICTIONS for additional information and restrictions.
1. The Contractor shall complete all work for the Navigation Lock Power and Controls Upgrade by no later than 29 March 2024.
2. The Navigation Lock must remain in service at all times during the Navigation Lock Pre-Outage Work
Window.
3. Government support is limited between 20 December and 2 January, annually. Support from Lower
Monumental staff is unavailable during this time unless approved in writing by the Contracting Officer.
4. All work requiring the Navigation Lock to be out of service must occur during the Navigation Lock Outage Work Window.
5. The Contractor shall complete final cleanup and demobilization by not later than 15 calendar days after completion of work in (1) above.
6. The Contractor shall complete the final, approved submission of the following by not later than 30 calendar days after completion of work in (1) above.
a) O&M manuals.
b) As-Built drawings.
c) Shop Drawings.
d) Record Drawings.
e) Spare Parts submission
The completion date is based on the assumption that the successful offeror will receive the NTP by 25 August 2022.
The completion date will be extended by the number of calendar days after the above date that the Contractor receives the NTP, except to the extent that the delay in issuance of the NTP results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of clause)
SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS
The following have been modified:
WAGE DETERMINATION
General Decision Number: WA20220069 05/20/2022
Superseded General Decision Number: WA20210069
State: Washington
Construction Type: Heavy including water and sewer line construction
County: Franklin County in Washington.
HEAVY CONSTRUCTION PROJECTS (including sewer/water construction).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $15.00 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2022. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $11.25 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2022. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at https://www.dol.gov/agencies/whd/government-contracts.
Modification Number Publication Date 0 01/07/2022 1 02/18/2022 2 02/25/2022 3 05/20/2022
* CARP0059-009 06/01/2021
Rates Fringes
CARPENTER (Including Form Work)............................$ 38.87 17.84
MILLWRIGHT.......................$ 50.68 20.14
PILEDRIVERMAN....................$ 40.17 17.84
ZONE PAY:
ZONE 1 0-45 MILES FREE
ZONE 2 45-100 MILES $4.00/PER HOUR
ZONE 3 OVER 100 MILES $6.00/PER HOUR
DISPATCH POINTS:
PASCO (515 N. Neel Street) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
SPOKANE (127 E. AUGUSTA AVE.) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
WENATCHEE (27 N. CHELAN) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
COEUR D' ALENE (1839 N. GOVERNMENT WAY) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
MOSCOW (302 N. JACKSON) or Main Post Office of established residence of employee (Whichever is closest to the worksite).
ELEC0112-014 06/01/2021
Rates Fringes
ELECTRICIAN......................$ 50.00 22.93
ENGI0370-022 07/01/2019
Rates Fringes
POWER EQUIPMENT OPERATOR
GROUP 1.....................$ 28.46 17.25
GROUP 2.....................$ 28.78 17.25
GROUP 3.....................$ 29.39 17.25
GROUP 4.....................$ 29.55 17.25
GROUP 5.....................$ 29.71 17.25
GROUP 6.....................$ 29.99 17.25
GROUP 7.....................$ 30.26 17.25
GROUP 8.....................$ 31.36 17.25
ZONE DIFFERENTIAL (Add to Zone 1 rate): Zone 2 - $2.00
Zone 1: Within 45 mile radius of Spokane, Pasco, Washington;
Lewiston, Idaho
Zone 2: Outside 45 mile radius of Spokane, Pasco, Washington; Lewiston, Idaho
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Rollers, all types on subgrade, including seal and chip coatings; Drill Assistant; Crane Oiler
GROUP 2: Fork Lift; Broom/Sweeper
GROUP 3: Bulldozer (up to D-6 or equivalent); Boring Machine
GROUP 4: Oiler; Drill (churn, core, calyx or diamond);
Loaders (overhead & front-end, under 4 yds. R/T)
GROUP 5: Backhoe (Under 45,000 gw); Trackhoe/Excavator (under 3/4 yd.); Drilling equipment (8 unch bit and over) (robbins, reverse circulation and similar); Piledriver;
Grade Checker; Boom Truck (Under 25 tons)
GROUP 6: Asphalt Roller; Backhoe (45,000 gw and over to 110,000 gw); Trackhoe/Excavator (3/4 yd. to 3 yd.), Bulldozer, 834 R/T & similar; Mechanic; Paver; Scraper;
Screed; Loader Operator (front-end & overhead, 4 yds. incl.
8 yds.)
GROUP 7: Backhoe (Over 110,000); Trackhoe/Excavator (3 yds & over); Grader/Blade; Loaders (overhead & front-end, over 8 yds. to 10 yds.)
GROUP 8: Loaders (overhead and front-end, 10 yards and over)
BOOM PAY: (All Cranes, Including Tower) 180 ft to 250 ft $ .50 over scale Over 250 ft $ .80 over scale
NOTE:
In computing the length of the boom on Tower Cranes, they shall be measured from the base of the Tower to the point of the boom.
HAZMAT:
Anyone working on HAZMAT jobs, working with supplied air shall receive $1.00 an hour above classification.
IRON0014-012 01/03/2022
Rates Fringes
IRONWORKER (Ornamental, Reinforcing and Structural)......$ 36.19 30.70
LABO0238-014 06/01/2020
Rates Fringes
LABORER: Mason Tender - Brick...$ 29.06 13.65
LABO0238-015 06/01/2021
Rates Fringes
LABORER (Pasco)
GROUP 1.....................$ 27.34 14.50
GROUP 2.....................$ 29.44 14.50
GROUP 3.....................$ 29.71 14.50
GROUP 4.....................$ 31.32 13.00
Zone Differential (Add to Zone 1 rates): Zone 2 - $2.00
BASE POINTS: Spokane, Pasco, Lewiston
Zone 1: 0-45 radius miles from the main post office.
Zone 2: 45 radius miles and over from the main post office
LABORERS CLASSIFICATIONS
GROUP 1: Flagger
GROUP 2: Common or General Laborer; Form-Stripping
GROUP 3: Mason Tender-Cement/Concrete
GROUP 4: Grade Checker; High Scaler; Handheld Drill
PAIN0005-003 07/01/2020
Rates Fringes
PAINTER (Brush, Roller, and Spray.)..........................$ 25.19 13.20
PLAS0072-008 06/01/2020
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 31.30 15.53
Zone Differential (Add to Zone 1 rates): Zone 2 - $2.00
BASE POINTS: Spokane, Pasco, Lewiston, Wenatchee
Zone 1: 0 - 45 radius miles from the main post office
Zone 2: 45 radius miles from the main post office
TEAM0690-005 01/01/2019
Rates Fringes
Truck drivers: (ANYONE
WORKING ON HAZMAT JOBS SEE
FOOTNOTE A BELOW)
ZONE 1:PASCO ZONE CENTER
GROUP 4....................$ 29.13 17.40
GROUP 5....................$ 29.24 17.40
GROUP 6....................$ 29.24 17.40
Zone Differential (Add to Zone 1 rate: Zone 1 + $2.00)
BASE POINTS: Spokane, Moses Lake, Pasco, Lewiston
Zone 1: 0-45 radius miles from the main post office Zone 2: Outside a 45 mile radius from the main post office
TRUCK DRIVERS CLASSIFICATIONS
GROUP 4: Water Truck (0-8,000 gallons)
GROUP 5: Semi-Trailer Truck
GROUP 6: Water Truck (8,001-14,000 Gallons)
FOOTNOTE A - Anyone working on a HAZMAT job, where HAZMAT cerfification is required, shall be compensated as a premium, in addition to the classification working in as follows:
LEVEL C-D: - $.50 PER HOUR - This level may use an air purifying respirator or additional protective clothing.
LEVEL A-B: - $1.00 PER HOUR - Uses supplied air in conjunction with a chemical splash suit or fully encapsulated suit with a self-contained breathing apparatus.
Employees shall be paid Hazmat pay in increments of four(4) and eight(8) hours.
* SUWA2009-060 08/07/2009
Rates Fringes
CARPENTER, Excludes Form Work....$ 23.54 4.99
LABORER: Landscape & Irrigation.......................$ 12.27 ** 2.73
LABORER: Pipelayer..............$ 19.28 0.00
OPERATOR: Asphalt Plant.........$ 34.14 0.68
OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 10.63 ** 0.00
OPERATOR: Crane.................$ 23.42 5.54
OPERATOR: Power Shovel..........$ 25.12 7.83
TRUCK DRIVER, Includes Dump Truck............................$ 27.67 0.00
TRUCK DRIVER: Flatbed Truck.....$ 22.74 6.29
TRUCK DRIVER: Lowboy Truck......$ 22.89 5.72
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($15.00) or 13658 ($11.25). Please see the Note at the top of the wage determination for more information.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
(End of Summary of Changes)
File details come from the government source that posted it. Updated .