This document contains a solicitation for a construction project and an amendment to that solicitation. The U.S. Army Corps of Engineers Walla Walla District is seeking to replace aging electrical equipment at the Lower Monumental Navigation Lock in Washington. Key project elements include replacing medium and low voltage switchgear, transformers, motor controls, feeders, cable trays, and installing new control systems and HMI screens. An extended outage window of 5-9 weeks will be provided. The pre-proposal site visit date was changed in the amendment. The solicitation will utilize a best value tradeoff source selection method and result in a firm fixed price construction contract valued between $5-10 million. Proposals are due approximately 30 days after posting to sam.gov in April 2022. The NAICS code is 238210 and the small business size standard is $16.5 million.

View the file

Other files for this federal contract opportunity

Other files attached to Lower Monumental Navigation Lock Power and Controls Upgrade, newest first.
File Type Posted
Amendment 0005 W912EF22R0002.pdf PDF
Amendment 0005 TechSpecs.pdf PDF
W912EF22R0002_Site Visit Sign-In Sheet.pdf PDF
Amendment 0004 Supplemental Drawings.pdf PDF
Amendment 0004 TechSpecs.pdf PDF
Amendment 0004 Plans.pdf PDF
Amendment 0004 W912EF22R0002.pdf PDF
Amendment 0003 W912EF22R0002.pdf PDF
Amendment 0002 W912EF22R0002.pdf PDF
Brand Name Determination SEL Equip W912EF22R0002 Redacted.pdf PDF
Site Visit Info W912EF22R0002.pdf PDF
Solicitation W912EF22R0002.pdf PDF
Plans W912EF22R0002 LMA Navlock Power Controls Upgrade.pdf PDF
Tech Specs W912EF22R0002 LMA Navlock Power Controls Upgrade.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912EF22R0002, Low er Monumental Navigation Lock Pow er and Controls Upgrade

The solicitation is amended as follow s:

The site visit date is changed from 11 May 2022 at 10:00 a.m. Pacif ic Time to 18 May 2022 at 10:00 a.m. Pacif ic Time.

See Continuation Page for details.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-May-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912EF22R0002

X 9B. DATED (SEE ITEM 11)

28-Apr-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-May-2022

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

DAVID C BOONE 201 N. THIRD AVENUE

WALLA WALLA WA 99362-1876

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF22R0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

18 May 2022 at 10:00 a.m. Pacific Time

(c) Participants will meet at--

Lower Monumental Lock and Dam 5520 Devils Canyon Road Kahlotus, WA 99335

There will be only one site visit offered. Offerors planning to attend must register for the site by sending an email to: david.c.boone@usace.army.mil and Leanne.R.Walling@usace.army.mil

Firms must register no later than the day before the site visit.

Site visit attendees must provide the following information in the email:

(1) Solicitation Number

(2) Project Title

(3) Name of individual(s) attending

(4) Name of company being represented

(5) Phone number of company

(6) Are all individuals U.S. Citizens?

If not, please refer to ACCESS FOR FOREIGN NATIONALS in Section 00 73 00

Each individual must have picture identification on his/her person while at the project site. There can be no substitutions of one individual for another. If an individual arrives at the site visit without having called ahead of time and/or without picture identification, that individual may not be allowed on the project.

Participants of scheduled site visit must abide by the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, latest version) in accordance with Section 5, “Personal Protective and Safety Equipment.” It is the responsibility of the participants to wear personal protective and safety equipment as required by this regulation.

Failure to comply could result in denial of access to site visit location.

The latest version of EM 385-1-1 is available online at:

http://www.usace.army.mil/SafetyandOccupationalHealth.aspx

All attendees must follow federal, state, and local guidelines for the mitigation of COVID 19 when attending this

W912EF22R0002

site visit. Please ensure all attendees have PPE with them in order to comply with COVID 19 mitigation measures.

The ACCESS FOR FOREIGN NATIONALS requirement in Section 00 73 00 applies to site visits as well as to performance of the work.

Site Visit Guidelines:

Government staff will read the script (Description of the project).

The Government will not be answering any questions during the walkthrough. Potential offerors will be allowed to take equipment specific pictures and measurements of equipment that is along the predetermined pathway only.

Once site visit is complete, contractor attendees will be escorted back to the Visitor Center and the site visit walkthrough is complete.

To ensure consistent information is shared among all potential offerors, all questions must be submitted through the ProjNet bidder inquiry process outlined in the solicitation.

(End of provision)

(End of Summary of Changes)