Amendment 0002 Tech Specs.pdf
PDF 58 KB Posted
- Attached to
- Mill Creek Low Flow Radial Arm Gate Repair
- Solicitation number
- W912EF21B0012
About this file
This document provides details for a construction solicitation for repairs to radial arm gates at Mill Creek Low Flow Diversion Dam. Work includes concrete excavation, installation of self-regulating electric heating cables, concrete repair, abrasive blasting and coating of hydraulic steel structures, removal and replacement of grease lubricated bearings, and fabrication and installation of a radial gate control panel with a PLC control system to automate gate position based on forebay water level. Safety training and oversight requirements include development of an accident prevention plan, activity hazard analyses, and on-site safety personnel. The solicitation will be issued as a small business set-aside IFB by the U.S. Army Corps of Engineers Walla Walla District, with a magnitude between $100,000 to $250,000. The NAICS code is 237990 and size standard is $39.5 million. The bid opening will be approximately 30 days after posting to beta.sam.gov in late May 2021.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MCL Diversion Dam Low Flow Radial Arm Gate Repairs W912EF21B0012 Amendment - 002
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15.00 28 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 32 16.00 28 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 28 CONTRACTOR QUALITY CONTROL
01 51 00.00 28 TEMPORARY UTILITIES
01 54 19.10 28 USE OF CRANES
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
01 78 23.00 28 OPERATION AND MAINTENANCE DATA
01 91 00.00 28 SYSTEMS TESTING AND COMMISSIONING
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 23.00 28 REMOVAL AND REINSTALLATION WORK
02 83 33.14 28 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
DI VI SI ON 05 - METALS
05 05 23.00 28 METAL WORK
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 91 00.10 28 GATE RUBBER SEALS AND BUMPER
DI VI SI ON 09 - FI NI SHES
09 97 02.00 28 PAINTING: HYDRAULIC STRUCTURES
DI VI SI ON 25 - I NTEGRATED AUTOMATI ON
25 05 11.00 28 CYBERSECURITY
25 31 00.01 28 ELECTRICAL CONTROL AND RELAY PANEL
DI VI SI ON 26 - ELECTRI CAL
26 05 00.00 28 GENERAL ELECTRICAL WORK
26 05 19.00 28 INSULATED WIRE AND CABLE
26 05 33.10 28 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 24 16.00 28 SECTION INTERIOR DISTRIBUTION SYSTEM
DI VI SI ON 31 - EARTHWORK
PROJECT TABLE OF CONTENTS Page 1
31 00 00.12 28 EARTHWORK
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 01 41.00 28 LIFTING GEAR REFURBISHMENT
35 05 40.17 28 SELF-LUBRICATED BEARINGS - FABRICATION, HANDLING, AND
ASSEMBLY
DI VI SI ON 40 - PROCESS I NTERCONNECTI ONS
40 05 23.00 28 SELF-REGULATING ELECTRIC HEATING CABLE
40 94 43.01 28 PROCESS CONTROLLERS - PROGRAMMABLE LOGIC CONTROLLERS (PLC)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 45 04.00 28
CONTRACTOR QUALITY CONTROL
PART 1 GENERAL
1.1 REFERENCES
1.2 PAYMENT
1.3 SUBMITTALS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL
3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN
3.2.1 General
3.2.2 Content of the CQC Plan
3.2.3 Acceptance of Plan
3.2.4 Notification of Changes
3.3 COORDINATION MEETING
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
3.4.2 CQC System Manager
3.4.3 CQC Personnel
3.4.4 Additional Requirement
3.5 SUBMITTALS
3.6 CONTROL
3.6.1 Preparatory Phase
3.6.2 Initial Phase
3.6.3 Follow-up Phase
3.6.4 Additional Preparatory and Initial Phases
3.7 TESTS
3.7.1 Testing Procedure
3.7.2 Testing Laboratories
3.7.2.1 Capability Check
3.7.3 Onsite Laboratory
3.7.4 Furnishing or Transportation of Samples for Testing
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
3.8.2 Pre-Final Inspection
3.8.3 Final Acceptance Inspection
3.9 DOCUMENTATION
3.10 NOTIFICATION OF NONCOMPLIANCE
3.11 PROJECT CLOSE OUT
ATTACHMENTS:
Sample of Quality Control Report, WWD-QCR (Rev Sep 85)
SECTION 01 45 04.00 28 Page 1
-- End of Section Table of Contents --
SECTION 01 45 04.00 28 Page 2
SECTION 01 45 04.00 28
CONTRACTOR QUALITY CONTROL
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D 3740 (2004a) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM E 329 (2007) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program, and all costs associated therewith shall be included in the applicable prices contained in The Schedule.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. A designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan ; G, C
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 GENERAL
Provide quality control and establish and maintain an effective quality control system in compliance with the clause entitled INSPECTION OF CONSTRUCTION of the CONTRACT CLAUSES. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product that complies with the contract requirements. The system shall cover all on-site construction operations and shall be keyed to the proposed construction sequence. Utilize established in-house quality control procedures to assure full compliance with all off-site work.
Submit daily reports in compliance with paragraph DOCUMENTATION for all on-site work and for all off-site work.
SECTION 01 45 04.00 28 Page 3
3.2 CONTRACTOR QUALITY CONTROL (CQC) PLAN
3.2.1 General
Submit for review by the Government, not later than 15 calendar days after receipt of Notice to Proceed , the Contractor Quality Control Plan proposed to implement the requirements of the clause entitled INSPECTION OF CONSTRUCTION of the CONTRACT CLAUSES. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used.
Construction will be permitted to begin only after acceptance of the CQC Plan.
3.2.2 Content of the CQC Plan
The CQC Plan shall include, as a minimum, the following to cover all construction operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents:
a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff shall implement the three phase control system for all aspects of the work specified. The CQC System Manager shall report directly to the owner of the firm or a senior manager not responsible for executing the work. The CQC can not work directly for the Project Manager or manager responsible for the execution of the work.
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a QC function.
c. A copy of the letter to the CQC System Manager signed by the owner of the firm, or an equivalent individual within the company who is not responsible for managing this project, which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work and rework of any nonconformance work which is not in compliance with the contract. The CQC System Manager shall issue letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities.
Copies of these letters shall also be furnished to the Government.
d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents. These procedures shall be in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES.
e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities will be subject to approval by the Contracting Officer.)
f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
g. Procedures for tracking construction deficiencies from identification through acceptable corrective action. These procedures
SECTION 01 45 04.00 28 Page 4 shall establish verification that identified deficiencies have been corrected.
h. Reporting procedures, including proposed reporting formats.
i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks and has separate control requirements. It could be identified by different trades or disciplines, or it could be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable feature under a particular section. This list will be agreed upon during the Coordination Meeting.
3.2.3 Acceptance of Plan
Acceptance of the Contractor's plan is required prior to the start of construction . Acceptance is conditional and will be predicated on satisfactory performance during the construction . The Government reserves the right to require the Contractor to make changes in the CQC plan and operations including removal of personnel, as necessary, to obtain the quality specified.
3.2.4 Notification of Changes
After acceptance of the CQC plan, notify the Contracting Officer in writing a minimum of seven (7) calendar days prior to any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
3.3 COORDINATION MEETING
After the Preconstruction Meeting , before start of construction , and prior to acceptance by the Government of the Quality Control Plan, meet with the Contracting Officer and discuss the Contractor's quality control system.
During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording the CQC operations, control activities, testing, administration of the system for both on-site and off-site work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance inspection. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor. Contractor is responsible for preparing the meeting minutes.
See Section 01 11 01.00 28 , paragraph ADDITIONAL MEETINGS.
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
The requirements for the CQC organization are a CQC System Manager and sufficient number of additional qualified personnel to ensure safety and contract compliance. The Site Safety and Health Officer (SSHO) shall serve as a member of the CQC staff. Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The CQC staff shall maintain a presence at the site at all times during progress of the work and have complete authority and
SECTION 01 45 04.00 28 Page 5 responsibility to take any action necessary to ensure contract compliance. The CQC staff shall be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Complete records of all letters, material submittals, shop drawing submittals, schedules and all other project documentation shall be promptly furnished to the CQC organization by the Contractor.
The CQC organization shall be responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.
3.4.2 CQC System Manager
Identify as CQC System Manager an individual within the onsite work organization who is responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager shall be a graduate engineer, or a graduate of construction management, with a minimum of 3 years construction experience on construction similar to this contract. This CQC System Manager shall be on the site at all times during construction and be employed by the prime Contractor. The CQC System Manager can be assigned as the Project Superintendent . Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager. Identify as CQC System Manager an individual within the onsite work organization who is responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager shall be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 5 years construction experience on construction similar to this contract, or may substitute the degree with 10 years or more experience in construction on similar projects to this contract. This CQC System Manager shall be on the site at all times during construction and be employed by the prime Contractor. The CQC System Manager shall be assigned no other duties . Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager. Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.
3.4.3 CQC Personnel
In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: electrical, mechanical, civil, structural, environmental, materials technician, submittals clerk, . These individuals shall be directly employed by the prime Contractor and may not be employed by a supplier or subcontractor on this project ; be responsible to the CQC System Manager; be physically present at the construction site during work on their areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein.
These individuals may perform other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan. A single person may cover more than one area provided that they are qualified to perform QC activities in each designated and that workload allows.
SECTION 01 45 04.00 28 Page 6
Experience Matrix
Area Qualifications
a. Civil Graduate Civil Engineer or Construction Manager with 2 years experience in the type of work being performed on this project or technician with 5 years related experience
b. Mechanical Graduate Mechanical Engineer or Construction Manager with 2 years experience or person with 5 years related experience
c. Electrical Graduate Electrical Engineer or Construction Manager with 2 years related experience or person with 5 years related experience
d. Structural Graduate Structural Engineer or Construction Manager with 2 years experience or with 5 years related experience
e. Architectural Graduate Architect with 2 years experience or person with 5 years related experience
f. Submittals Submittal Clerk with 1 year experience
g. Testing, Adjusting and Balancing Specialist must be a member (TAB) Personnel of AABC or an experienced technician of the firm certified by the NEBB.
3.4.4 Additional Requirement
In addition to the above experience and/or education requirements, the CQC System Manager and CQC assistant shall have completed the course entitled "Construction Quality Management for Contractors" within the last five (5) years. This course will periodically be offered at various locations throughout the Pacific Northwest. For information concerning this course call your local Associated General Contractors (AGC) Plan Room.
NOTE: For contractor personnel who otherwise fulfill all requirements for designation as a CQC System Manager but have not had the opportunity to obtain a CQM certificate as a result of pandemic restrictions, the Government will tentatively accept proposed personnel until COVID-19 restrictions are lifted. Once the COVID-19 restrictions are lifted and USACE is able to provide face to face CQM training, the proposed personnel has 120 calendar days to obtain the CQM certificate.
SECTION 01 45 04.00 28 Page 7
3.5 SUBMITTALS
Submittals shall be as specified in SECTION 01 33 00 SUBMITTAL PROCEDURES.
The CQC System Manager shall be responsible for certifying that all submittals are in compliance with the contract requirements.
3.6 CONTROL
Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. The controls shall be adequate to cover all construction operations, including on-site fabrication, and shall be keyed to the proposed construction sequence.
The controls shall include at least three (3) phases of control to be conducted by the CQC System Manager for all definable features of work, as follows:
3.6.1 Preparatory Phase
This phase shall be performed prior to beginning work on each definable feature of work and shall include:
a. A review of each paragraph of applicable specifications.
b. A review of the contract plans.
c. A check to assure that all materials and/or equipment have been tested, submitted, and approved.
d. A check to assure that provisions have been made to provide required control inspection and testing.
e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.
f. A physical examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawing or submitted data, and are properly stored.
g. A review of the appropriate Activity Hazard Analysis to assure safety requirements are met.
h. Discussion of procedures for constructing the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that phase of work.
i. A check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
j. The Government shall be notified at least 48 hours in advance of beginning any of the required action of the preparatory phase. This phase shall include a meeting conducted by the CQC system manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. The results of the preparatory phase actions shall be documented by separate minutes prepared by the CQC System Manager and attached to the daily QC report. Instruct applicable workers as to the acceptable level of
SECTION 01 45 04.00 28 Page 8 workmanship required in order to meet contract specifications.
k. The preparatory meeting will include a review of the submittal register to ensure all the required submittals for this portion of the work have been approved and contractor has approved submittals in hand.
3.6.2 Initial Phase
This phase shall be accomplished at the beginning of a definable feature of work. The following shall be accomplished:
a. A check of preliminary work to ensure that it is in compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verification of full contract compliance. Verify required control inspection and testing.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with sample panels as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government shall be notified at least 24 hours in advance of beginning the initial phase. Separate minutes of this phase shall be prepared by the CQC System Manager and attached to the daily CQC report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.
g. The initial phase shall be repeated for each new crew to work on-site, or any time acceptable specified quality standards are not being met.
3.6.3 Follow-up Phase
Daily inspections shall be performed to assure continuing compliance with contract requirements, including control testing, until completion of the particular feature of work. The inspections shall be made a matter of record in the CQC documentation. Final follow-up inspections shall be conducted and all deficiencies corrected prior to the start of additional features of work which may be affected by the deficient work. Do not build upon or conceal non-conforming work. Maintain working "as-built" contract drawings as required in SECTION 01 78 00.00 28 CLOSEOUT
SUBMITTALS.
3.6.4 Additional Preparatory and Initial Phases
Additional preparatory and initial phases shall be conducted on the same definable features of work as determined by the Government if the quality of on-going work is unacceptable; or if there are changes in the applicable QC staff or in the on-site production supervision or work crew;
or if work on a definable feature is resumed after a substantial period of inactivity, or if other problems develop.
SECTION 01 45 04.00 28 Page 9
3.7 TESTS
3.7.1 Testing Procedure
Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements.
Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and/or acceptance tests when specified. Procure the services of a Corps of Engineers approved testing laboratory or establish an approved testing laboratory at the project site. Perform the following activities and record and provide the following data:
a. Verify that testing procedures comply with contract requirements.
b. Verify that facilities and testing equipment are available and comply with testing standards.
c. Check test instrument calibration data against certified standards.
d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.
e. Results of all tests taken, both passing and failing tests, shall be recorded on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test shall be given. If approved by the Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken.
An information copy of tests performed by an offsite or commercial test facility shall be provided directly to the Contracting Officer.
Failure to submit timely test reports as stated may result in nonpayment for related work performed and disapproval of the test facility for this contract.
3.7.2 Testing Laboratories
3.7.2.1 Capability Check
The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel shall meet criteria detailed in ASTM D 3740 and ASTM E 329 .
3.7.3 Onsite Laboratory
The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government.
3.7.4 Furnishing or Transportation of Samples for Testing
Costs incidental to the transportation of samples or materials shall be borne by the Contractor. Samples of materials for test verification and acceptance testing by the Government shall be delivered to the Contracting
SECTION 01 45 04.00 28 Page 10
Officer.
3.8 COMPLETION INSPECTION
At the completion of all work or any increment thereof established by a completion time stated in clause: COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK or stated elsewhere in the specifications, the CQC System Manager shall conduct an inspection of the work and develop a "punch list" of items which do not conform to the approved plans and specifications. Such a list of deficiencies shall be included in the CQC documentation, as required by paragraph DOCUMENTATION below, and shall include the estimated date by which the deficiencies will be corrected.
The CQC System Manager or staff shall make a second inspection to ascertain that all deficiencies have been corrected and so notify the Contracting Officer. These inspections and any deficiency corrections required by this paragraph shall be accomplished within the time stated for completion of the entire work or any particular increment thereof if the project is divided into increments by separate completion dates.
3.8.1 Punch-Out Inspection
Near the end of the work, or any increment of the work established by a time stated in the Contract Clauses Section, "Commencement, Prosecution, and Completion of Work," or by the specifications, the CQC Manager shall conduct an inspection of the work. A punch list of items which do not conform to the approved drawings and specifications shall be prepared and included in the CQC documentation, as required by paragraph DOCUMENTATION. The list of deficiencies shall include the estimated date by which the deficiencies will be corrected. The CQC System Manager or staff shall make a second inspection to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government and provide the list of correct deficiencies to the Government.
3.8.2 Pre-Final Inspection
The Government will perform the Pre-Final Inspection to verify that the facility is complete and ready to be occupied . A Government Pre-Final Punch List may be developed as a result of this inspection. The Contractor's CQC System Manager shall ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection can be scheduled. Any items noted on the Pre-Final Inspection shall be corrected in a timely manner. These inspections and any deficiency corrections required by this paragraph shall be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.
3.8.3 Final Acceptance Inspection
The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting Officer's Representative shall be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from the District Office , may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notice shall be given to the Contracting Officer at least 14 days prior to the final acceptance inspection and shall include the Contractor's assurance that
SECTION 01 45 04.00 28 Page 11 all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the contract clause titled "Inspection of Construction" .
3.9 DOCUMENTATION
Maintain current records of quality control operations, activities, and tests performed, including the work of subcontractors and suppliers.
These records shall be on an acceptable form, see attached Sample of Quality Control Report, WWD-QCR (Rev Sep 85) , and shall include factual evidence that required quality control activities and/or tests have been performed, including but not limited to the following:
a. Contractor/subcontractor and their area of responsibility.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Test and/or control activities performed with results and references to specifications/plan requirements. The control phase should be identified (Preparatory, Initial, Follow-up). List deficiencies noted along with corrective action.
d. Off-site surveillance activities, including actions taken.
e. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
f. List instructions given/received and conflicts in plans and/or specifications.
g. Contractor's verification statement.
h. Work performed today, giving location, description, and by whom.
When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.
i. Material received with statement as to its acceptability and storage.
j. Identify submittals reviewed, with contract reference, by whom, and action taken.
k. These records shall indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. These records shall cover both conforming and deficient features and shall include a statement that equipment and materials incorporated in the work and workmanship comply with the contract. The original and one (1) copy of these records in report form shall be furnished to the Government daily within 24 hours after the date(s) covered by the report, except that reports need not be submitted within 24 hours for days on which no work is performed. As a minimum, one report shall be prepared and submitted for every seven (7) calendar days of no work and on the last
SECTION 01 45 04.00 28 Page 12 day of a no work period. All calendar days shall be accounted for throughout the life of the contract. The first report following a day of no work shall be for that day only. Reports shall be signed and dated by the CQC System Manager. The report from the CQC System Manager shall include copies of test reports and copies of reports prepared by all subordinate quality control personnel.
3.10 NOTIFICATION OF NONCOMPLIANCE
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. After receipt of such notice, immediately take corrective action. Such notice, when delivered to the Contractor at the site of the work, shall be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order suspending or stopping all or part of the work until satisfactory corrective action has been taken.
3.11 PROJECT CLOSE OUT
Within 30 calendar days of construction completion date, the CQC System Manager shall review the Submittal Register and formally notify the Contracting Officer of the schedule in submitting all outstanding submittals. A weekly update shall be provided with an updated schedule until all submittals have been received. Once all the submittals have been approved, the CQC System Manager submits a letter Contracting Officer certifying all submittals have been submitted.
-- End of Section --
SECTION 01 45 04.00 28 Page 13
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 45 04.00 28 Page 14
| PROJECT TABLE OF CONTENTS |
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 45 04.00 28 - CONTRACTOR QUALITY CONTROL |
| 01 45 04.00 28 - CONTRACTOR QUALITY CONTROL |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 PAYMENT |
| 1.3 SUBMITTALS |
| PART 2 PRODUCTS Not Applicable |
| PART 3 EXECUTION |
| 3.1 GENERAL |
| 3.2 CONTRACTOR QUALITY CONTROL CQC PLAN |
| 3.2.1 General |
| 3.2.2 Content of the CQC Plan |
| 3.2.3 Acceptance of Plan |
| 3.2.4 Notification of Changes |
| 3.3 COORDINATION MEETING |
| 3.4 QUALITY CONTROL ORGANIZATION |
| 3.4.1 Personnel Requirements |
| 3.4.2 CQC System Manager |
| 3.4.3 CQC Personnel |
| 3.4.4 Additional Requirement |
| 3.5 SUBMITTALS |
| 3.6 CONTROL |
| 3.6.1 Preparatory Phase |
| 3.6.2 Initial Phase |
| 3.6.3 Follow-up Phase |
| 3.6.4 Additional Preparatory and Initial Phases |
| 3.7 TESTS |
| 3.7.1 Testing Procedure |
| 3.7.2 Testing Laboratories |
| 3.7.2.1 Capability Check |
| 3.7.3 Onsite Laboratory |
| 3.7.4 Furnishing or Transportation of Samples for Testing |
| 3.8 COMPLETION INSPECTION |
| 3.8.1 Punch-Out Inspection |
| 3.8.2 Pre-Final Inspection |
| 3.8.3 Final Acceptance Inspection |
| 3.9 DOCUMENTATION |
| 3.10 NOTIFICATION OF NONCOMPLIANCE |
| 3.11 PROJECT CLOSE OUT |
File details come from the government source that posted it. Updated .