W912EF19B0002_Amend_0005.pdf

PDF 29 KB Posted

Attached to
Little Goose Oil Water Headcover Separator
Solicitation number
W912EF19B0002
Issued by

About this file

W912EF19B0002 Amend 0005

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to revise FAR Clause 52.211-10, specif ications and plans. See Summary of Changes and attachments.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 12-Feb-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF19B0002

X 9B. DATED (SEE ITEM 11)

11-Jan-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

12-Feb-2019

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

CYNTHIA H JACOBSEN

201 N. THIRD AVE

WALLA WALLA WA 99362-1876

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF19B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0005

Summary of Changes for Amend -0005 Little Goose Head Cover Oil Water Separator

1. Revised the following Specifications:

a. SECTION 00 01 15.00 28 LIST OF DRAWINGS

i) Updated Paragraph 1.2 CONTRACT DRAWINGS

b. SECTION 22 00 00.00 28 PIPING, GENERAL PURPOSE

i) Updated Paragraph 2.5.5 Totalizer

See revised specification for details

2. Revised the following Drawings (See clouded areas).

a. SHEET S-101

b. SHEET M-001

c. SHEET M-201

d. SHEET M-601

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than the dates listed below.

(1) The Contractor shall complete all on-site installation (ready for Government pre-operational test phase) of the headcover pumps for Main Units 1 - 6 between July 2019 and December 2019. The first unit will be Main Unit 6.

No two units may be out of service at the same time (not including Unit 5) unless allowed by the Contracting Officer. Each unit must be completely operational and commissioned prior to taking another unit out of service.

The Government will have the units available and prepared for the Contractor to start on-site installation work within the work windows listed below:

MAIN UNIT 5 (Currently Out-of-Service)

a. 08 Jul 2019 – Government to prepare unit for turnover to Contractor b 10 Jul 2019 – 08 Dec 2019 (Installation work window and final commissioning)

MAIN UNIT 6

a. 08 Jul 2019 – Government to prepare unit for turnover to Contractor b 10 Jul 2019 – 28 Jul 2019 (Installation work window and final commissioning)

THIRD UNIT

a. 12 Aug 2019 – Government to prepare unit for turnover to Contractor b 14 Aug 2019 – 1 Sep 2019 (Installation work window and final commissioning)

FOURTH UNIT

a. 09 Sep 2019 – Government to prepare unit for turnover to Contractor b 11 Sep 2019 – 29 Sep 2019 (Installation work window and final commissioning)

FIFTH UNIT

a. 07 Oct 2019 – Government to prepare unit for turnover to Contractor b 09 Oct 2019 – 27 Oct 2019 (Installation work window and final commissioning)

SIXTH UNIT

a. 18 Nov 2019 – Government to prepare unit for turnover to Contractor b 20 Nov 2019 – 08 Dec 2019 (Installation work window and final commissioning)

(2) At the end of each work window, the pumps must be operational, discharging into the existing dewatering system or other method approved by the Government.

(3) The contractor shall complete system commissioning within 30 days of final installation

(4) The Contractor shall complete final cleanup for each unit by not later than 7 calendar days after completion of work in (1) above. Demobilization will be not later than 15 calendar days after completion of the final unit.

(5) The Contractor shall complete final submission of O&M manuals and final approved versions of Contractor prepared drawings by not later than 30 calendar days after completion each unit in (1) above. Working “as-built” contract drawings will be completed for each unit before starting work on the next unit.

(End of clause)

(End of Summary of Changes)