W68SBV50500431
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
FAR Clause 52.217-7, Option for Increased Quantity -- Separately Priced Line Item, has been revised to show the timeframe w hen optional
Item 0078 may be exercised. See attached.
LOWER MONUMENTAL DAM UNIT #1 REWIND, LINKAGE REPAIR & CAVITATION REPAIR, AND UNIT #2 CAVITATION REPAIR
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-May-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-15-R-0001
X 9B. DATED (SEE ITEM 11)
13-Mar-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-May-2015
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
PHYLLIS L. BUERSTATTE
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF-15-R-0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0004
Summary of changes for Amend -0004
Lower Monumental Unit 1 Rewind and Linkage Repair and Unit 1 and Unit 2 Cavitation Repair W912EF- 15-R-0001
1. Revised the following Clause: See Yellow Highlights
FAR 52.217-7 OPTION FOR INCREASED QUANTITY – SEPARATELY PRICED LINE ITEM
Item 0078 Refurbish Rotor Poles (Optional) Timeframe when optional ITEM may be exercised has been revised to match bid schedule revision in Amend-0001. See yellow highlights below for change.
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item(s), identified in the Schedule as an option item(s), in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option(s) by written notice to the Contractor as specified in the OPTIONAL ITEMS Table below:
OPTIONAL ITEMS
CLIN DESCRIPTION
Timeframe when optional ITEM may be exercised
If exercised, time extension to complete work for ITEM
UNIT 1
Perform Additional Stator Core Interlaminar Insulation Test (Optional)
Within Fifteen (15) days after Government Acceptance of the Interlaminar insulation test Report
Two (2) calendar days to 52.211-10 subparagraph (c)(3), after date of exercising the option.
0048 Stator Core Iron Repair (Optional)
Within Fifteen (15) days after Government Acceptance of the Interlaminar insulation
Five (5) calendar days to 52.211-10 subparagraph test Report
0049 Replace Stator Core (Optional) after Government Acceptance of the Stator Inspection Report
Forty-five (45) calendar days to subparagraph
Hone Runner Blade Servomotor Cylinder (Optional)
Within Fifteen (15) days after Government Acceptance of the As Found Inspection Report
No additional time will be allowed
Bore and Hone Runner Blade Servomotor Cylinder (Optional)
Within Fifteen (15) days after Government Acceptance of the As Found Inspection Report
Hone Wicket Gate Servomotor Cylinder (Optional)
Within Fifteen (15) days after Government Acceptance of the Wicket Gate Servomotor Inspection Report
Bore and Hone Wicket Gate Servomotor Cylinder (Optional)
Within Fifteen (15) days after Government Acceptance of the Wicket Gate Servomotor Inspection Report
Furnish and Install Wicket Gate Servomotor Piston Ring Set (Optional)
Within Fifteen (15) days after Government Acceptance of the Wicket Gate Servomotor Inspection Report
Light Machine Cut On The Packing Box Bore (Optional)
Within Fifteen (15) days after Government Acceptance of the Main shaft Packing Box Initial Inspection Report
Skim Cut on Both Faces of the Packing Box Mounting Flange (Optional)
Within Fifteen (15) days after Government Acceptance of the Main shaft Packing Box Initial Inspection Report
0057 Restore Packing Box Bore (Optional) after Government Acceptance of the Main shaft Packing Box Initial Inspection Report
0058 Furnish and Install One Set of Outer Within Fifteen (15) days No additional time will be
Head Cover Tie Down Studs and Nuts (Optional) after Government Acceptance of the Headcover Studs, Nuts, and Bolts Inspection Report
Furnish and Install One Set of Intermediate Head Cover Tie-Down Studs and Nuts (Optional)
Within Fifteen (15) days after Government Acceptance of the Headcover Studs, Nuts, and Bolts Inspection Report
Furnish and Install One Set of Inner Head Cover Tie Down Studs and Nuts (Optional)
Within Fifteen (15) days after Government Acceptance of the Headcover Studs, Nuts, and Bolts Inspection Report
Furnish Piston Cap Stud and Nut (Optional)
Within Fifteen (15) days after Government Acceptance of the Piston Cap, Piston, and Studs Inspection Report
Thrust Runner and Thrust Collar Phase 2 Inspections (Optional)
Within Fifteen (15) days after Government Acceptance of the Thrust Runner Phase 1 inspection Report.
Thrust Shoes Phase 2 Inspections (Optional)
Within Fifteen (15) days after Government Acceptance of the Thrust Shoes Phase 1 inspection Report.
Resurface the Running Surface of the Thrust Runner (Optional)
Within Fifteen (15) days after Government Acceptance of the Thrust Runner as found inspection Report
Complete Refurbishment of Thrust Runner (Optional)
Within Fifteen (15) days after Government Acceptance of the Thrust Runner as found inspection Report
Refurbish One Set of Thrust Bearing Shoes (Optional)
Within Fifteen (15) days after Government Acceptance of the Thrust Bearing Shoes as found inspection Report
Refurbish Thrust Bearing Collar (Optional)
Within Fifteen (15) days after Government Acceptance of the Thrust Bearing Collar Inspection Report
Refurbish One Turbine Guide Bearing (Optional)
Within Fifteen (15) days after Government Acceptance of the Turbine Guide Bearing Inspection Report
Refurbish One Set of Upper Generator Guide Bearing Shoes (Optional)
Within Fifteen (15) days after Government Acceptance of the Generator Guide Bearing Inspection Report
Refurbish One Set of Lower Generator Guide Bearing Shoes (Optional)
Within Fifteen (15) days after Government Acceptance of the Generator Guide Bearing Inspection Report
Spot Cavitation Repair - Mild Steel (Optional)
Within Fifteen (15) calendar days after initial excavation.
Five (5) calendar days to subparagraph (c)(3), after date of exercising the option.
Spot Cavitation Repair - Stainless Steel (Optional)
Within Fifteen (15) calendar days after initial excavation.
Five (5) to subparagraph
Furnish BLH Internal Hub Components (Optional)
Within Ninety (90) days after the Contractor’s receipt of the Notice to Proceed.
Shall be delivered in accordance with subparagraph (c)(3), Discharge Ring Cavitation Repair - Additional Stainless Steel Band Repair (1" X 1/4") (Optional)
Within Fifteen (15) calendar days after Government Acceptance of the discharge ring excavation.
One (1) additional calendar day to subparagraph (c)(3), per additional inch of cavitation repair after date of exercising the option.
Discharge Ring Cavitation - Additional Mild Steel Band Repair (1" X 1/8") (Optional)
Within Fifteen (15) calendar days after Government Acceptance
One (1) additional calendar day to subparagraph (c)(3), per of the discharge ring excavation.
additional inch of cavitation repair after
Repair of Discharge Ring Weld Seams (Optional)
Within Fifteen (15) calendar days of initial excavation.
Ten (10) to subparagraph (c)(3), 0077 Epoxy Injection (Optional) Immediately after initial excavation determines this work is necessary.
Five (5) to subparagraph
0078 Refurbish Rotor Poles (Optional) after Government Acceptance of the Rotor Inspection Report
No additional time will be allowed
OPTIONAL REQUIREMENTS
UNIT 2
Spot Cavitation Repair - Mild Steel (Optional)
Within Fifteen (15) calendar days of initial excavation.
Five (5) calendar days to 52.211-10 subparagraph (c)(2), after date of
Spot Cavitation Repair - Stainless Steel (Optional)
Within Fifteen (15) calendar days of initial excavation.
Five (5) calendar days to 52.211-10 subparagraph (c)(2), after date of
Additional Stainless Steel Band Repair (1" X 1/4") (Optional)
Within Fifteen (15) calendar days after Government Acceptance of the discharge ring excavation.
One (1) additional calendar day to subparagraph (c)(2), per additional inch of cavitation repair after
Additional Mild Steel Band Repair (1" X 1/8") (Optional)
Within Fifteen (15) calendar days after Government Acceptance of the discharge ring excavation.
One (1) additional calendar day to subparagraph (c)(2), per additional inch of cavitation repair after
Repair of Discharge Ring Weld Seams (Optional)
Within Fifteen (15) calendar days of initial excavation.
Ten (10) calendar days to 52.211-10 subparagraph (c)(2), 0084 Epoxy Injection (Optional) Immediately after initial excavation determines
Five (5) calendar days to 52.211-10 subparagraph this work is necessary. (c)(2), after date of
End of clause
(End of Summary of Changes)