Amendment 0001 - W912DY-26-Q-A295 MC Multi Location - Rec Furniture.pdf
PDF 3 MB Posted
- Solicitation number
- W912DY-26-Q-A295
About this file
This file is an amendment to a federal solicitation and a how-to guide for responding to a Request for Quote (RFQ) for furniture procurement.
The amendment (dated July 15, 2026) modifies RFQ W912DY26QA295 issued by the U.S. Army Corps of Engineers Huntsville Center for multi-location recreational furniture across various military installations. The amendment provides vendor responses to three technical questions regarding installation timelines, bid submission requirements, and visitor access procedures. Key responses clarify that contractual installation dates are firm, vendors must reference the SF1449 form's "Instructions to Quoters" section for required attachments including Furniture Item Descriptions and Statements of Work, and that base access and security requirements for visitor authorization are detailed in the SOW's Table 1s. The RFQ How-To Guide provides comprehensive technical submission requirements for furnishings including panel-supported workstations, wood casegoods, seating, and related items. Vendors must submit organized, PDF-formatted technical responses bookmarked by FID (Furniture Item Description) item numbers with supporting documentation including: item product data sheets, plan views and electrical/data drawings, elevation views, isometric views, FID line item compliance documentation with annotated catalog sheets or component lists, construction and quality compliance specifications, testing documentation from accredited laboratories, environmental certifications, and warranty coverage letters. All documentation must be clearly annotated and cross-referenced with quoted model numbers, finishes, and specifications. Technical responses should be compact, searchable, and coordinate all product information with pricing submissions on Attachment 1.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
J 1 66
0001 15 JUL 2026
W912DY
W2V6 USA ENG SPT CTR HUNTSVIL
300 SECURE GATEWAY, KO CONTRACTING DIVISION
REDSTONE ARSENAL, AL 35898-0000
UNITED STATES
JESSICA SIZEMORE, EMAIL: JESSICA.SIZEMORE@USACE.ARMY.MIL
SCD: PAS:
W912DY26QA295
10 JUL 2026
SEE CONTINUATION
The purpose of this amendment is to:
a. Provide responses to vendor questions.
b. Provide an RFQ How To Guide.
c. All other terms and conditions remain the same.
Vendor Questions and Answers MC Multi Location, Rec Furniture
RFQ W912DY-26-Q-A295
1. Vendor Question: Considering the criteria for some of the equipment per the contract, especially the pool tables, they seem to be particular to certain brands. We’ve reached out to manufacturers and asked if this was feasible. Due to the amount of tables requested, it is likely that the tables would have to be manufactured at request. Also, game room furnishing set up is quite a lengthy process. Is there a way to adjust the timing described in the contract to fit a more reasonable installation time? Or is the contract firm in that regard?
HNC RESPONSE: Contractual installation dates are firm.
2. Vendor Question: Are there any “gotchas” that we would need to know about when submitting the bid that may not be listed in the contract?
HNC RESPONSE: Reference the Instructions to Quoters section of the SF1449 document which includes a list of attachments you will need to make a complete quote for the project.
Attachments in the RFQ document include Furniture Item Descriptions, Statement of Work (SOW), Contract clauses, etc. Additionally, please review the RFQ How To Guide should you need further assistance.
3. Vendor Question: For the Installations, could we send VARs manually, or would they have to go through the DISS system?
HNC RESPONSE: Please refer to the Table 1s within the SOW for base access and security requirements.
RFQ How-To Guide
REQUIREMENTS
EXAMPLES &
CHECKLISTS
Huntsville Center, Centralized Furnishings Program
Table of Contents Purpose of the RFQ How To Guide:
Submitting a RFQ Technical Response:
Technical Response Submittal Map for Bookmarking
Check Your Submittal
Cover Page:
Item Number Product Data Sheet:
Plan Views:
Plan Views - Electrical / Data:
Checklist - Elevation Views – Segmented Panel Details:
Isometric Views, includes Electrical / Data:
FID Item Number Compliance Documentation:
Construction and quality Compliance Documentation:
Testing Documentation:
Environmental Documentation:
Warranty Documentation:
Cover Page
Purpose:
Required Usage:
What Information Should Be Noted on the Cover Page?
Checklist - Cover Page:
Example – Cover Page
Item Number Product Data Sheets
Purpose:
What FID Items Require Item Number Product Data Sheets?
What Information Should Be Noted on the Item Number Product Data Sheet?
Checklist - Item Number Product Data Sheet:
Tips to Avoid Common Mistakes:
Scenario - Wood Casegoods
Example – Item Number Product Data Sheet
Drawing(s) –Plan Views
Purpose:
What FID Items Require Plan Views?
Plan Views:
Plan Views - Electrical / Data:
What Information Should Be Noted on Drawings?
Checklist - Plan Views:
Checklist - Electrical / Data Plan Views:
Tips to Avoid Common Mistakes:
Scenario - Panel Supported Workstations
Example – Overall Cluster Plan View:
Example – Typical Plan View:
Examples – Typical Electrical / Data View:
Drawing(s) – Elevation View - Segmented Panel Detail(s)
Purpose:
What FID Items Require Elevation Views?
What Information Should Be Noted on Elevations?
Checklist - Elevation Views – Segmented Panel Details:
Tips to Avoid Common Mistakes:
Scenario - Panel Supported Workstations
Example – Segmented Panel Detail – Typical(s):
Example – Elevation View - Segmented Panel Detail – Typical(s):
Drawing(s) - Isometric Views
Purpose:
What FID Items Require Isometric Views?
What Information Should Be Noted on Isometric Views?
Checklist – Isometric Views, includes Electrical / Data:
Tips to Avoid Common Mistakes:
Scenario - Panel Supported Workstations
Example - Isometric View – Overall Cluster:
Example - Isometric View – Typical(s):
Example - Isometric View – Interior:
Examples – Isometric Views – Exterior:
FID Line Item Compliance Documentation
What FID Items Require Compliance Documentation?
What Information Should Be Included for FID line item Compliance Documentation?
Checklist –FID Line Item Compliance Documentation:
Tips to Avoid Common Mistakes:
Scenario – Wood Casegoods
Example – Compliance Documentation - Catalog Sheet:
Example – Compliance Documentation – Catalog Sheet, Cont’d.:
Example – Compliance Documentation – Components List:
Construction and Quality Requirements Documentation
Purpose:
What FID Items Require Construction and Quality Compliance Documentation?
What Information Should Be Included for Compliance Documentation?
Checklist – For Construction and Quality Compliance Documentation:
Tips to Avoid Common Mistakes:
Scenario – Wood Casegoods
Example– Construction and Quality Compliance Documentation:
Example– Construction and Quality Compliance Documentation Cont’d.:
Testing Documentation
Purpose:
What FID Items Require Testing Documentation?
What Information Should Be Included in Testing Documentation?
Checklist – Testing Documentation:
Tips to Avoid Common Mistakes:
Scenario – Ergonomic Task Seating
Example – Test Report:
Example – Accreditation Certificate:
Environmental Documentation
Purpose:
What FID Items Require Environmental Documentation?
What Information Should Be Included in Testing Documentation?
Checklist – Requirements for Environmental Documentation:
Tips to Avoid Common Mistakes:
Scenario – Ergonomic Task Seating
Example – Third Party Certificate:
Warranty Documentation
Purpose:
What FID Items Require Warranty Documentation?
What Information Should Be Included in Warranty Documentation?
Checklist – Requirements for Warranty Documentation:
Tips to Avoid Common Mistakes:
Scenario – Ergonomic Task Seating
Construction and Quality Requirements- Warranty Requirements:
Example – Warranty:
What is a RFQ?
An RFQ is a request for quote by a contracting entity.
Purpose of the RFQ How To Guide:
This guide is offered by the Centralized Furnishings Program to help vendors understand the types of documentation and describe the format in which the documentation should be provided in a RFQ Technical Response Submittal.
Submitting a RFQ Technical Response:
Vendors interested in submitting a RFQ response shall follow all instructions provided within the RFQ contract requirements and Attachment 2, Furniture Item Description (FID), FID Submittal Requirements in Section 1.0. Questions should be directed to the Contracting Specialist POC in order to receive guidance.
Within this guide, examples of various types of supporting documentation are simulated to illustrate the general format technical reviewers expect to be included in a submittal to satisfy FID requirements.
Be organized and consistent. Technical responses shall be organized and bookmarked by FID item numbers. Under each FID item number, bookmark the supporting documentation such as drawings, line item description, construction and quality compliance requirements, testing, environmental, and warranty documentation. Create clear references to a FID item by annotating and/or highlighting the supporting documentation. In the event documentation is applicable to more than one item number, documentation can be located under the first item number where the documentation is required. All item numbers that apply to the documentation shall be clearly indicated on the supporting documentation.
Be searchable and compact. Technical responses shall be formatted using Adobe Acrobat Portable Document File (.PDF). When converting and inserting files to a .pdf, the vendor should verify information has been bookmarked per the order outlined in the FID Submittal Requirements in Section 1.0. One electronic file is preferred but it is understood some vendors may have limits for transmitting file over a certain size. We kindly request the submittal response be compacted to as few files as possible to save the vendor time in formatting and organizing and to save the reviewer time during technical review.
Be accurate and specific. Technical response documents shall be fully coordinated with all required documents in the submittal. Product information in the response should match and support the information entered into the Attachment #1. Provide only supporting documentation that specifically indicates your submittal satisfies the FID requirements. Additional unnecessary information adds time to a vendor’s submittal preparation and to the overall review process.
Technical Response Submittal Map for Bookmarking Cover Page Table of Contents – Optional Item Number - Product Data
Product Data Supporting Documentation Drawings Line Item Compliance Documentation:
Construction and Quality Compliance Documentation:
Testing Documentation:
Environmental Documentation:
Warranty Documentation:
Check Your Submittal Please use this as a tool for a final quality check for your response. This list of items is consolidated from each section of the How- To Guide as a quick reference tool to assist vendors in quality checks prior to submitting their response. It is not a substitute for any requirement outlined in the guide or identified in the RFQ and its attachments.
Cover Page:
Solicitation Number Project Name Project Number Project Location Technical Response Submittal Round: i.e, Initial Submittal, 1st Round, 2nd Round, etc.
Date
Item Number Product Data Sheet:
Data Sheet for each Line Item Number Item Number Item Description Manufacturer Product Line Model number(s) for each item and its components or bookmark a separate list included within section Product Description Overall Dimensions Product Image or bookmark a separate larger or detailed image included within section Proposed Fabric(s) and Finish(es) quoted and/or bookmark finish cards included within section Fabric Grade or bookmark finish cards identifying grade included within section
Plan Views:
Item Number Item Description Plan of Overall Cluster Detail Plan of Each Typical Label the required components of each typical, CADD graphic tags may be used to identify required components and dimensions Dimension overall cluster Dimension overall typical(s) Turn off unnecessary tags to ensure plan is legible Provide electrical / data components on a separate drawing
Plan Views - Electrical / Data:
Item Number Item Description Detail Electrical / Data Plan of each typical in a cluster Label required components of electrical / data components, CADD graphic tags may be used to identify required components and dimensions Indicate location (baseline / beltline) if possible. This may be shown on elevation as well Dimension overall cluster Dimension overall typical(s) Turn off unnecessary tags to ensure electrical / data notes and locations are legible Provide cluster/typical components on a separate drawing
Checklist - Elevation Views – Segmented Panel Details:
Item Number Item Description Segmented Panel Details of each side of each typical in cluster Details show location of components, such as tile locations, alignment of panel frames, power/data locations at all raceways Provide details as a separate drawing(s). These drawings may be submitted on the same page with other drawings as long as the graphics and text are legible Include labels or key notes to indicate required vertical components of typical/cluster. CADD graphic tags may be used identified required components Turn off unnecessary tags to ensure plan is legible
Isometric Views, includes Electrical / Data:
Item Number Item Description Detail Isometric of overall workstation cluster Detail Isometric of each typical in cluster Detail Exterior and Interior Views locating vertical locations of components, such as alignment of panel frames, electrical/data locations at beltline and base raceways; multiple views as required
Provide an isometric view as a separate drawing. These drawings may be submitted on the same page with other drawings as long as the graphics and text are legible
Include labels or key notes to indicate required vertical components of typical/cluster. CADD graphic tags may be used identified required components
Turn off unnecessary tags to ensure plan is legible
FID Item Number Compliance Documentation:
Annotated Item Number(s) Manufacturer’s product information as described above with quoted model numbers and features annotated and/or highlighted.
Annotation Notes and/or Highlights shall identify required salient features, specific model numbers, quoted options, dimensions, and any dimensional ranges.
Fabric/Finish Selection Cards, if not provided on Item Number Product Data Sheet.
Bookmark or key annotations / notes specific to an item number, if multiple items are referenced.
Drawings are keyed to parts or components list.
Construction and quality Compliance Documentation:
Annotated Item Number(s) Manufacturer’s product information as described above with quoted model numbers and features annotated and/or highlighted.
Annotation Notes and/or Highlights shall identify required Construction and quality technical specifications and construction for the item number quoted Bookmark or key annotations / notes specific to an item number, if multiple items are referenced
Testing Documentation:
Item Number(s) Item Description
Actual Test Reports for the required standard shall include the following components:
Test Standard and Edition Date (i.e., X5.5-2008) Manufacturer Product Tested Model Number Date(s) Tested Test Procedures / Description Observations Acceptance Levels (Functional / Proof Loads) Results Photographs, optional Test Equipment, optional Verifiable digital signature containing encryption or handwritten signature, date, and title of the company official accepting technical responsibility for testing Statement testing and certification apply to the product offered and that products offered meet all applicable test requirements (Note: This statement is a component of an actual test report and is not intended to be submitted in lieu of an actual report.)
Lab Accreditation Documentation containing include (1) of the following methods of documentation for testing results:
Lab accreditation number and certificate number for facility type.
Documentation of 3rd party certification of test results.
If one of the above is not available, provide photographs of actual testing processes that demonstrate the methodology used is in compliance with BIFMA guidelines.
Environmental Documentation:
Item Number(s) Item Description Manufacturer Name Product Name Third Party Certificate Environmental Compliance Statement has been checked – Refer to RFQ Attachment 7
Warranty Documentation:
Item Number(s) Manufacturer Warranty Coverage Period for quoted item Manufacturer’s Letter of Warranty Expansion to meet FID Section 2.0 warranty requirements, if standard warranty does not satisfy requirements.
Cover Page
Introduce information submitted in the technical response by vendor.
Required Usage:
Provided at the front of Technical Response Submittal.
What Information Should Be Noted on the Cover Page?
Checklist - Cover Page:
Solicitation Number Project Name Project Number Project Location Technical Response Submittal Round: i.e, Initial Submittal, 1st Round, 2nd Round, etc.
Date
Graphics may be used to create a distinctive presentation of submittal information. Cover page shall contain all required information listed in the checklist above.
Example – Cover Page
Item Number Product Data Sheets
Present required product information for specific FID item number in an organized and consistent format for efficient technical review.
What FID Items Require Item Number Product Data Sheets?
All items listed in FID sections and on should have an Item Number Product Data Sheet.
What Information Should Be Noted on the Item Number Product Data Sheet?
Checklist - Item Number Product Data Sheet:
Data Sheet for each FID section item FID Section Number Item Number Item Description Manufacturer Product Line Model number(s) for each item and its components or bookmark a separate list included within section Product Description Overall Dimensions Product Image or bookmark a separate larger or detailed image(s) included within section Proposed Fabric(s) and Finish(es) quoted and/or bookmark finish cards included within section Fabric Grade or bookmark finish cards identifying grade included within section
Tips to Avoid Common Mistakes:
Use data sheet as technical specification document to verify item requirements are provided. Data sheet should summarize supporting compliance documentation provided for an item; it cannot be accepted as a compliance document.
Coordinate product information within the submittal and with the Attachment #1 documentation. Inconsistencies with product information listed on the data sheet and product priced (such as dimensions, product line, model numbers, etc.) must be resolved prior to receiving technical acceptance on an item.
Scenario –
Wood Casegoods
4.3 Item No. D-1: Freestanding L-Shaped Desk, Wood Veneer, Executive III
Overall Dimensions: 6’-0”W x 6’-6”D
Contractor shall:
*Confirm handedness in field.
*Coordinate layout with existing windows, wall-mounted data boxes, etc., as applicable.
Components:
a. 72”W x 36”D Rectangular desk with overhang
i. 30”D Box/Box/File pedestal with pencil tray and drawer dividers for each box drawer
ii. Center drawer
iii. Full height modesty panel
b. 42”W x 24”D Rectangular return
i. 24”D File/File pedestal
ii. Partial height modesty panel
c. Grommets with covers on all work surfaces
d. Cable trays and/or clips for wire management below all work surfaces
e. Locks at all drawers, keyed alike
Finish:
a. Wood Veneer: Manufacturer’s standard selection, shall include cherry or walnut, dark brown stain
b. Pulls: Manufacturer’s standard selection
c. Fabric: Manufacturer’s standard mid-grade fabric selection
Example – Item Number Product Data Sheet
ITEM NUMBER ITEM DESCRIPTION
4.3 D-1: Freestanding L-Shaped Desk, Wood Veneer, Executive III
MANUFACTURER:
XYZ Furniture Maker
PRODUCT LINE:
Awesome Contemporary Casegoods
MODEL NUMBER(S) including required options:
DS7236; CD1621; PT1409; LKA, WMT; RL4224
PRODUCT DESCRIPTION: Use manufacturer’s description in pricing catalog;
72”W X 36”D Single Pedestal Desk with Center Drawer and Box/Box/File; 42”W X 24”D Return with File/File Pedestal
OVERALL DIMENSIONS:
6’-6” X 6’-0”
REFERENCES / NOTES:
Provide a components list and description of what is being provided in Section 3.0 Compliance Documentation
FINISHES/FABRICS PROPOSED: Finish cards may be referenced in lieu of images of finishes.
Finish: Medium Cherry Pulls: Brushed Nickel
PRODUCT IMAGE
Provide a photo quality graphic or line drawing image of the quoted item
FINISH IMAGE with applicable grade or Bookmark finish selection card in
Section 3.0 Compliance
FINISH IMAGE with applicable grade or Bookmark finish selection card in
Section 3.0 Compliance
FINISH IMAGE with applicable grade or Bookmark finish selection card in
Section 3.0 Compliance
Drawing(s) –Plan Views
The plan drawing provides a visual “top view” depiction of the required item. Plans are reviewed in comparison to the written FID requirements and contract drawings, as well as other documentation and drawings within the vendor’s submittal to ensure the item is accurately quoted to meet FID requirements.
Every FID Item may not require plan or electrical / data drawings, but vendors may provide them to clarify salient features.
What FID Items Require Plan Views?
Plan Views:
Drawings should be provided for the following FID section items, including but not limited to:
Panel supported work stations Metal laminate desks Freestanding integrated desking Metal furniture, including files, towers, cabinets, and bookcases Wood casegoods Wood conference tables Laminate casegoods Laminate tables, including training tables Work benches
Plan Views - Electrical / Data:
If electrical /data components are specified, a separate drawing from the plan view shall be provided to detail electrical and data for FID Section items, including but not limited to:
Panel supported work stations Integrated desking systems Wood conference tables Laminate tables, including training tables Work benches
What Information Should Be Noted on Drawings?
Checklist - Plan Views:
Item Number Item Description Plan of Overall Cluster Detail Plan of Each Typical Label the required components of each typical, CADD graphic tags may be used to identify required components and dimensions Dimensions overall cluster Dimension overall typical(s) Turn off unnecessary tags to ensure plan is legible Provide electrical / data components on a separate drawing
Checklist - Electrical / Data Plan Views:
Item Number Item Description Detail Electrical / Data Plan of each typical in a cluster Label required components of electrical / data components, CADD graphic tags may be used to identify required components and dimensions Indicate location (baseline / beltline) if possible. This may be shown on elevation as well Dimensions overall cluster Dimension overall typical(s) Turn off unnecessary tags to ensure electrical / data notes and locations are legible Provide cluster/typical components on a separate drawing
Tips to Avoid Common Mistakes:
All tags are left on components and make the drawing cluttered and illegible. Heavy line weights, blurred images, and images that are too small to decipher make plans illegible.
Combination of electrical / data plans with drawings with the above problems make it almost impossible to determine the locations in a work station.
Heavy line weights, manufacturer tags, etc, that overlap the electrical data symbols make it difficult for the technical reviewer to find.
Cluster Drawings and Typical Plan Drawings may be submitted on the same page as long as the graphics and text are legible when enlarged.
Scenario –
Panel Supported Workstations
ITEM
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
TYP-01: Panel Supported Work Station Individual Work Station Dimensions: 7’-6”W x 5’-0”D *Dimensions do not include panel thickness
Contractor shall:
*Confirm handedness in field.
*Coordinate layout with existing windows, wall-mounted data boxes, etc., as applicable.
*Provide all electrical connections, i.e. base feeds, power poles, and accessory items as needed.
Individual Workstation Components:
a. 60”W x 30”D Rectangular work surface
b. 36”W x 18”D Rectangular work surface
c. 30”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
d. 18”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
e. 60”W Overhead storage bin with flipper doors
i. Doors shall open over the case
ii. Overhead storage bin shall have dividers or bookends that attach securely to the bin
iii. Provide energy efficient task lighting with vertical cord manager and power cord long enough to reach power source
f. 24”W x 18”D Hybrid storage tower:
i. (1) Adjustable shelf with file/file below, one side
ii. Full height storage cabinet with coat rod, other side
g. 64-68”H Segmented, acoustical, tackable panels
i. Minimum of 3 tackable tiles
ii. Interior Tiles: All segments shall be tackable acoustical fabric
iii. Exterior tiles:
a. Bottom tile: Laminate
b. Middle Tile: Tackable acoustical fabric
c. Top Tile: Tackable acoustical fabric
h. 50-54”H Segmented, acoustical, tackable panels
i. Minimum of 2 tackable tiles
ii. Interior Tiles: All segments shall be tackable acoustical fabric
iii. Exterior tiles:
a. Bottom tile: Laminate
b. Top Tile: Tackable acoustical fabric
i. (5) Duplex receptacles located in the base raceway, beltline (above the work surface), and technology tile
i. (3) Duplex outlets shall be located in base raceways
ii. (1) Duplex outlet shall be located in beltline (above the work surface)
iii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) duplex outlet
j. Duplex receptacles shall be evenly distributed across all work surfaces
k. (4) Punch outs for data/comm. located in the base raceway, beltline (above the work surface), and technology tile. Refer to provided plans for locations
i. (2) Punch outs for data/comm. shall be located in base raceways
ii. (1) Punch out for data/comm. shall be located in beltline (above the work surface)
iii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) punch out for (1) data; (1) voice
l. Slatwall organizer shall include:
i. Paper management accessories: (1) pencil cup, (1) diagonal paper sorter
m. Grommets with covers and/or scallops on all work surfaces
n. Cable trays and/or clips for wire management below all work surfaces
o. Locks at all drawers and doors
i. Item shall be keyed to match adjacent furnishings within the workstation
p. All work surfaces shall be laminate. Storage cases and supports shall be metal
Finish:
a. High Pressure Laminate: Manufacturer’s standard selection
b. Edge: Manufacturer’s standard selection
c. Metal: Manufacturer’s standard powder coat paint selection
d. Pulls: Manufacturer’s standard selection
e. Panel Fabric: Manufacturer’s standard mid-grade fabric selection
f. Top Cap and Trim: Manufacturer’s standard metal selection
TYP-02: Panel Supported Work Station Individual Work Station Dimensions: 5’-6”W x 5’-0”D *Dimensions do not include panel thickness
Contractor shall:
*Confirm handedness in field.
*Coordinate layout with existing windows, wall-mounted data boxes, etc., as applicable.
*Provide all electrical connections, i.e. base feeds, power poles, and accessory items as needed.
Individual Workstation Components:
a. 60”W x 30”D Rectangular work surface
b. 36”W x 18”D Rectangular work surface
c. 30”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
d. 18”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
e. 60”W Overhead storage bin with flipper doors
i. Doors shall open over the case
ii. Overhead storage bin shall have dividers or bookends that attach securely to the bin
iii. Provide energy efficient task lighting with vertical cord manager and power cord long enough to reach power source
f. 64-68”H Segmented, acoustical, tackable panels
i. Minimum of 3 tackable tiles
g. (2) Duplex receptacles located in the base raceway and technology tile
i. (1) Duplex outlet shall be located in base raceways
ii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) duplex outlet
h. Duplex receptacles shall be evenly distributed
i. (2) Punch outs for data/comm. located in the base raceway and technology tile. Refer to provided plans for locations
i. (1) Punch outs for data/comm. shall be located in base raceways
ii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) punch out for (1) data; (1) voice
j. 12-16”H Privacy screen shall attach securely to the worksurface, see cluster descriptions for locations
k. Slatwall organizer shall include:
i. Paper management accessories: (1) pencil cup, (1) diagonal paper sorter
l. Grommets with covers and/or scallops on all work surfaces
m. Cable trays and/or clips for wire management below all work surfaces
n. Locks at all drawers and doors
i. Item shall be keyed to match adjacent furnishings within the workstation
o. All work surfaces shall be laminate. Storage cases and supports shall be metal
Finish:
a. High Pressure Laminate: Manufacturer’s standard selection
b. Edge: Manufacturer’s standard selection
c. Metal: Manufacturer’s standard powder coat paint selection
d. Pulls: Manufacturer’s standard selection
e. Panel Fabric: Manufacturer’s standard mid-grade fabric selection
f. Privacy screen: Manufacturer’s standard selection shall include a frosted finish
g. Top Cap and Trim: Manufacturer’s standard metal selection
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6 Overall Dimensions: 15’-6”W x 15’-3”D
*Coordinate layout with existing windows, wall-mounted data boxes, fire extinguishers, thermostats, radiators etc., as applicable.
Cluster Components:
a. (2) TYP-01, (4) TYP-02; refer to TYP-01 and TYP-02 for specific requirements
b. Privacy screens shall be a nominal dimension of 66”W and be located between workstation typicals
c. Refer to provided floor plans for cluster layout and shared panel configurations
Example – Overall Cluster Plan View (Example of what the vendor shall provide)
ITEM
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable cluster drawing. This representative image excludes information to prevent communication of non-proprietary information.
Example – Typical Plan View: (Example of what the vendor shall provide)
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable typical drawing. This representative image excludes information to prevent communication of non-proprietary information.
*Typicals Drawing(s) should include a key plan or correspond to a components list which defines the tagged part numbers.
Examples – Typical Electrical / Data View: (Example of what the vendor shall provide)
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable electrical / data typical drawing. This representative image excludes information to prevent communication of non-proprietary information.
Drawing(s) – Elevation View - Segmented Panel Detail(s)
Elevational views depict a vertical view of the panel and tile locations. Reviewed in comparison to written FID requirements, contract drawings, as well as other documentation and drawings within the vendor’s submittal, to ensure item is accurately quoted to meet all the FID requirements.
What FID Items Require Elevation Views?
Drawings shall be provided to clarify components located on the vertical plane for the following the FID Section items:
Panel supported work stations
What Information Should Be Noted on Elevations?
Checklist - Elevation Views – Segmented Panel Details:
Item Number Item Description Segmented Panel Details of each side of each typical in cluster Details show location of components, such as tile locations, alignment of panel frames, power/data locations at all raceways Provide details as a separate drawing(s). These drawings may be submitted on the same page with other drawings as long as the graphics and text are legible Include labels or key notes to indicate required vertical components of typical/cluster. CADD graphic tags may be used identified required components Turn off unnecessary tags to ensure plan is legible
Tips to Avoid Common Mistakes:
Tags are left on components and make the drawing cluttered and illegible. Heavy line weights, blurred images, and images that are too small to decipher.
Heavy line weights, manufacturer tags, etc, that overlap the electrical data symbols.
Details are not submitted in technical response.
Scenario - Panel Supported Workstations
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
Excerpt from Plan View Scenario (TYP-01: Panel Supported Work Stations):
a. 64-68”H Segmented, acoustical, tackable panels
i. Minimum of 3 tackable tiles
ii. Interior Tiles: All segments shall be tackable acoustical fabric
iii. Exterior tiles:
a. Bottom tile: Laminate
b. Middle Tile: Tackable acoustical fabric
c. Top Tile: Tackable acoustical fabric
b. 50-54”H Segmented, acoustical, tackable panels
i. Minimum of 2 tackable tiles
ii. Interior Tiles: All segments shall be tackable acoustical fabric
iii. Exterior tiles:
a. Bottom tile: Laminate
b. Top Tile: Tackable acoustical fabric
c. (5) Duplex receptacles located in the base raceway, beltline (above the work surface), and technology tile
i. (3) Duplex outlets shall be located in base raceways
ii. (1) Duplex outlet shall be located in beltline (above the work surface)
iii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) duplex outlet
d. Duplex receptacles shall be evenly distributed across all work surfaces
e. (4) Punch outs for data/comm. located in the base raceway, beltline (above the work surface), and technology tile. Refer to provided plans for locations
i. (2) Punch outs for data/comm. shall be located in base raceways
ii. (1) Punch out for data/comm. shall be located in beltline (above the work surface)
iii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1)
*Tagged plan shown to coordinate with detail drawing examples on the following page.
Example – Segmented Panel Detail – Typical(s): (Example of what the vendor shall provide)
ITEM
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable detail drawing. This representative image excludes
Example – Elevation View - Segmented Panel Detail – Typical(s): (Example of what the vendor shall provide)
ITEM
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable detail drawing. This representative image excludes information to prevent communication of non-proprietary information.
*Workstation components and accessories are not shown.
Drawing(s) - Isometric Views
Isometric drawing provides a visual “3-D” depiction of required item and are reviewed in comparison to the written FID requirements, contract drawings, as well as other documentation and drawings within vendor’s submittal, to ensure item is accurately quoted to meet all FID requirements.
Every FID Item does not require isometric drawing(s) but may be provided to clarify vertical locations of components of item.
What FID Items Require Isometric Views?
Drawings shall be provided for the following FID Section items:
Panel supported work stations Metal laminate desks Metal furniture, including files, towers, cabinets, and bookcases Wood casegoods Laminate casegoods Laminate training tables, if powered Seating, if detailed photograph image is not available Workbenches or technical workstations
What Information Should Be Noted on Isometric Views?
Checklist – Isometric Views, includes Electrical / Data:
Item Number Item Description Detail Isometric of overall workstation cluster Detail Isometric of each typical in cluster Detail Exterior and Interior Views locating vertical locations of components, such as alignment of panel frames, electrical/data locations at beltline and base raceways; multiple views as required
Provide an isometric view as a separate drawing. These drawings may be submitted on the same page with other drawings as long as the graphics and text are legible
Include labels or key notes to indicate required vertical components of typical/cluster. CADD graphic tags may be used identified required components
Turn off unnecessary tags to ensure plan is legible
Tips to Avoid Common Mistakes:
Isometrics of Interior/Exterior views are not included.
Components are included in all isometrics.
Unnecessary tags are left on components making drawing cluttered and illegible. Heavy line weights, blurred images, and images that are too small to decipher.
Cluster Drawings and Typical Plan Drawings may be submitted on the same page as long as graphics and text are legible when enlarged.
All FID Items do not require a drawing but may be provided to communicate salient features of item.
Scenario - Panel Supported Workstations
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
TYP-01: Panel Supported Work Station Individual Work Station Dimensions: 7’-6”W x 5’-0”D *Dimensions do not include panel thickness
Contractor shall:
*Confirm handedness in field.
*Coordinate layout with existing windows, wall-mounted data boxes, etc., as applicable.
*Provide all electrical connections, i.e. base feeds, power poles, and accessory items as needed.
Individual Workstation Components:
a. 60”W x 30”D Rectangular work surface
b. 36”W x 18”D Rectangular work surface
c. 30”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
d. 18”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
e. 60”W Overhead storage bin with flipper doors
i. Doors shall open over the case
ii. Overhead storage bin shall have dividers or bookends that attach securely to the bin
iii. Provide energy efficient task lighting with vertical cord manager and power cord long enough to reach power source
f. 24”W x 18”D Hybrid storage tower:
i. (1) Adjustable shelf with file/file below, one side
ii. Full height storage cabinet with coat rod, other side
g. 64-68”H Segmented, acoustical, tackable panels
i. Minimum of 3 tackable tiles
ii. Interior Tiles: All segments shall be tackable acoustical fabric
iii. Exterior tiles:
a. Bottom tile: Laminate
b. Middle Tile: Tackable acoustical fabric
c. Top Tile: Tackable acoustical fabric
h. 50-54”H Segmented, acoustical, tackable panels
i. Minimum of 2 tackable tiles
ii. Interior Tiles: All segments shall be tackable acoustical fabric
iii. Exterior tiles:
a. Bottom tile: Laminate
b. Top Tile: Tackable acoustical fabric
i. (5) Duplex receptacles located in the base raceway, beltline (above the work surface), and technology tile
i. (3) Duplex outlets shall be located in base raceways
ii. (1) Duplex outlet shall be located in beltline (above the work surface)
iii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) duplex outlet
j. Duplex receptacles shall be evenly distributed across all work surfaces
k. (4) Punch outs for data/comm. located in the base raceway, beltline (above the work surface), and technology tile. Refer to provided plans for locations
i. (2) Punch outs for data/comm. shall be located in base raceways
ii. (1) Punch out for data/comm. shall be located in beltline (above the work surface)
iii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1)
l. Slatwall organizer shall include:
i. Paper management accessories: (1) pencil cup, (1) diagonal paper sorter
m. Grommets with covers and/or scallops on all work surfaces
n. Cable trays and/or clips for wire management below all work surfaces
o. Locks at all drawers and doors
i. Item shall be keyed to match adjacent furnishings within the workstation
p. All work surfaces shall be laminate. Storage cases and supports shall be metal
Finish:
a. High Pressure Laminate: Manufacturer’s standard selection
b. Edge: Manufacturer’s standard selection
c. Metal: Manufacturer’s standard powder coat paint selection
d. Pulls: Manufacturer’s standard selection
e. Panel Fabric: Manufacturer’s standard mid-grade fabric selection
f. Top Cap and Trim: Manufacturer’s standard metal selection
TYP-02: Panel Supported Work Station Individual Work Station Dimensions: 5’-6”W x 5’-0”D *Dimensions do not include panel thickness
Contractor shall:
*Confirm handedness in field.
*Coordinate layout with existing windows, wall-mounted data boxes, etc., as applicable.
*Provide all electrical connections, i.e. base feeds, power poles, and accessory items as needed.
Individual Workstation Components:
a. 60”W x 30”D Rectangular work surface
b. 36”W x 18”D Rectangular work surface
c. 30”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
d. 18”D Box/Box/File pedestal with (1) pencil tray and (2) drawer dividers for each box drawer
e. 60”W Overhead storage bin with flipper doors
i. Doors shall open over the case
ii. Overhead storage bin shall have dividers or bookends that attach securely to the bin
iii. Provide energy efficient task lighting with vertical cord manager and power cord long enough to reach power source
f. 64-68”H Segmented, acoustical, tackable panels
i. Minimum of 3 tackable tiles
g. (2) Duplex receptacles located in the base raceway and technology tile
i. (1) Duplex outlet shall be located in base raceways
ii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) duplex outlet
h. Duplex receptacles shall be evenly distributed
i. (2) Punch outs for data/comm. located in the base raceway and technology tile. Refer to provided plans for locations
i. (1) Punch outs for data/comm. shall be located in base raceways
ii. (1) Technology tile shall include the following: (2) locations for cutouts each shall include; (1) punch out for (1) data; (1) voice
j. 12-16”H Privacy screen shall attach securely to the worksurface, see cluster descriptions for locations
k. Slatwall organizer shall include:
i. Paper management accessories: (1) pencil cup, (1) diagonal paper sorter
l. Grommets with covers and/or scallops on all work surfaces
m. Cable trays and/or clips for wire management below all work surfaces
n. Locks at all drawers and doors
i. Item shall be keyed to match adjacent furnishings within the workstation
o. All work surfaces shall be laminate. Storage cases and supports shall be metal
Finish:
a. High Pressure Laminate: Manufacturer’s standard selection
b. Edge: Manufacturer’s standard selection
c. Metal: Manufacturer’s standard powder coat paint selection
d. Pulls: Manufacturer’s standard selection
e. Panel Fabric: Manufacturer’s standard mid-grade fabric selection
f. Privacy screen: Manufacturer’s standard selection shall include a frosted finish
g. Top Cap and Trim: Manufacturer’s standard metal selection
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6 Overall Dimensions: 15’-6”W x 15’-3”D
*Coordinate layout with existing windows, wall-mounted data boxes, fire extinguishers, thermostats, radiators etc., as applicable.
Cluster Components:
a. (2) TYP-01, (4) TYP-02; refer to TYP-01 and TYP-02 for specific requirements
b. Privacy screens shall be a nominal dimension of 66”W and be located between workstation typical
c. Refer to provided floor plans for cluster layout and shared panel configurations
Example - Isometric View – Overall Cluster: (Example of what the vendor shall provide)
ITEM
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable isometric cluster drawing. This representative image excludes information to prevent communication of non-proprietary information.
Example - Isometric View – Typical(s): (Example of what the vendor shall provide)
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable isometric typical drawing. This representative image excludes information to prevent communication of non-proprietary information.
Example - Isometric View – Interior: (Example of what the vendor shall provide)
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable isometric detail drawing. This representative image excludes information to prevent communication of non-proprietary information.
*Workstation components and accessories are not shown.
Examples – Isometric Views – Exterior: (Example of what the vendor shall provide)
ITEM
NUMBER
ITEM DESCRIPTION
2.1 Item No. CL-4: Panel Supported Work Stations, Cluster of 6
NOTE: Drawing is shown for illustration purposes only and may not include all elements required for a technically acceptable isometric detail drawing. This representative image excludes information to prevent communication of non-proprietary information.
*Workstation components and accessories are not shown.
FID Line Item Compliance Documentation
Provide published documents that identifies the existence of and confirms required salient features of items in the manufacturer’s quoted price.
What FID Items Require Compliance Documentation?
All line items listed in the FID require manufacturer’s documentation to confirm the components and salient features of the item are provided.
What Information Should Be Included for FID line item Compliance Documentation?
Verifiable documentation should be provided for each item and consists of a manufacturer’s product information as published on the manufacturer’s website and/or in printed media customarily distributed to the A/E design industry.
Product information includes, but is not limited to, product pricing pages, specification guides/sheets, cut sheets, brochures, and provides all information to verify the construction, salient features, dimensions, model numbers, and model options for the item required in FID line item documentation.
Checklist –FID Line Item Compliance Documentation:
Annotated Item Number(s) Manufacturer’s product information as described above with quoted model numbers and features annotated and/or highlighted.
Annotation Notes and/or Highlights shall identify required salient features, specific model numbers, quoted options, dimensions, and any dimensional ranges.
Fabric/Finish Selection Cards, if not provided on Item Number Product Data Sheet.
Bookmark or key annotations / notes specific to an item number, if multiple items are referenced.
Drawings are keyed to parts or components list.
Tips to Avoid Common Mistakes:
To reduce the size of the submittal and streamline documentation, vendors may provide one annotated document that satisfies requirements for multiple FID Section Line Item Numbers. The document shall have notes and/or annotations to distinguish all applicable item numbers.
Non-verifiable documentation cannot be accepted Highlighting helps locate the required information.
Do not provide only a brochure as FID Compliance documentation. Brochures do not typically provide a complete representation of an item.
Documentation is provided but is not annotated or highlighted.
Quoted product information must match information entered in the Attachment 1
Do not copy FID Line item description in lieu of providing documentation.
Never create a document for the quote submittal to be presented as technical specification information. Documentation created for the sole purpose of responding to submittal requirements cannot be verified.
Avoid submitting documents not labeled with the item(s) they support.
Avoid submitting documents that do not visually indicate, with notes or annotations, the specific component, finish, part, etc., priced from among the many choices presented in the pricer, statement of line, or other published documentation.
Avoid stating “See BOM” on Attachment 1 instead of providing model numbers, without including model numbers from the BOM or the entire BOM.
Avoid submitting a BOM for an item but not including spec sheets, drawings, and published documents…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .