Amendment 03 to W912DY21R0063.pdf

PDF 366 KB Posted

Attached to
Modular/Pre-Fabricated SCIF Federal contract opportunity
Solicitation number
W912DY21R0063
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

This document provides an amendment to a request for proposals for the construction of a modular/prefabricated sensitive compartmented information facility at Fort Shafter, Hawaii. The amendment corrects a previous response to a contractor question, incorporates additional questions and answers, and updates the table of contents to include the additional questions and answers. The objective of the project is to construct a one-story facility using a modular, prefabricated construction method. The acquisition is being solicited as a total small business set-aside for a firm fixed price contract. Interested vendors must submit a statement of affiliation and meet security requirements to receive controlled unclassified information attachments pertaining to the statement of work, construction security plan, and other specifications. Proposals are due by the closing date listed in the solicitation.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Correct a previous response to contractor question #27; and

2. Incorporate additional questions and answ ers.

All other terms and conditions of the RFP remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DY21R0063

X 9B. DATED (SEE ITEM 11)

19-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Sep-2021

CODE

US ARMY ENGINEERING & SUPPORT CENTER

HUNTSVILLE ENGINEERING & SUPPORT CENTER

P.O. BOX 1600

HUNTSVILLE AL 35807-4301

W912DY 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DY21R0063

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 01 10 - TABLE OF CONTENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Statement+of+Affiliation

+(SoA)

Attachment 10 Q&A Spreadsheet RFP

Attachment 11 Government Response to Q&A

Attachment 12 COMBINED

QUESTION_RFP_W912

DY21R0063 GISA

Pacific SCIF

Attachment 2 CUI - SOW Revision 30-AUG-2021 Attachment 3 CUI-Draft Construction

Security Plan

23-JUL-2021

Attachment 4 CUI-Document Control Procedures

Attachment 5 CUI-Prohibited Items Attachment 6 Division 01 Specs Attachment 7 Factor 1 Element 1

Specialized Experience

Attachment 8 Factor 2 Past Performance Questionnaire

Attachment 9 DBA Wage Determination

16-JUL-2021

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Attachment 1 Statement+of+Affiliation

+(SoA)

Attachment 10 Q&A Spreadsheet RFP

Attachment 11 Government Response to Q&A

Attachment 12 COMBINED

QUESTION_RFP_W912

DY21R0063 GISA

Pacific SCIF

Attachment 13 Additional Questions & Answers (33-41)

14-SEP-2021

a0ctsmnb Highlight

Attachment 2 CUI - SOW Revision 30-AUG-2021 Attachment 3 CUI-Draft Construction

Security Plan

23-JUL-2021

Attachment 4 CUI-Document Control Procedures

Attachment 5 CUI-Prohibited Items Attachment 6 Division 01 Specs Attachment 7 Factor 1 Element 1

Specialized Experience

Attachment 8 Factor 2 Past Performance Questionnaire

Attachment 9 DBA Wage Determination

16-JUL-2021

(End of Summary of Changes)

Document and Section Page Question Response

What is the longest acceptable exterior length? CORRECTED RESPONSE: Whatever length is required to accommodate the approximately 2000, 2500, or 3000 sq ft facility and that will fit on the proposed site.

Document and Section Page Question Response

1.1 3 A "split system heat pump" is specified for this project. Are altenative HVAC systems acceptable so long as they meet local climate conditions and ICD 705?

Yes, an alternative HVAC system is acceptable

2.1.1 5 The SCIF perimeter door specifies a 90 minute fire rating and R22 insulation, whereas the construction of the facility does not. Is this required?

R-value should be based on climate zone for project location and special requirements in case of equipment. Keep in mind that IC Tech Spec requires a minimum STC rating based on project specifics.

2.1.2.b 5 The exterior construction specifies a panelized wall system with steel skins and framing. Are alternative construction methods acceptable?

Construction systems/finishes to follow Garrison design standards to meet asthetics, if any are required. Specific construction methods not specified as long as they meet Specifications for SCIFs found in IC Tech Spec Chapter 3 and UFC 4-010-05, along with any other code that applies.

2.1.2.b 5 Is a hermitically sealed enclosure required? If so, please expand on the purpose for this so that we can adquately design all treatments

Hermitically sealed enclosure is not required but IAW SOW 2.1, facility will require TEMPEST shielding. ICD/ICS gives examples of wall construction and sealing.

2.1.2.c 6 Is raised flooring a requirement or is this just a standard iFortress offering? Raised floor are not required. This should be coordinated with the client and space needs for supporting systems. If raised floors are used, additional measures maybe required. Floors should have same forced entry protection as walls.

2.1.2.c 6 Is vinyl wall covering required or is this just a standard iFortress offering?

Are other interior finishes acceptable, provided they meet local building codes?

Vinyl covering not required but finishes should be uniform from true floor to true ceiling and to be easily inspected to tampering.

2.1.2.c 6 Is 9ft interior clearance required or is this just a standard iFortress offering? Please specify alternative interior clearance height No special height requirements outside of IBC and Life Safety.

2.1.4 6 Structural requirements specify a blast load, which seems odd for a US base, unless this is going near a firing or test range. Is this a requirement or is this just a standard iFortress offering? Will the government accept non-blast resistant solutions?

A ballistic rating is an explosion test that typically yields 11.5 psi / 102ms at a 10 foot standoff. These results are also listed in structural , Paragraph 4, Blast Load. These values can be more or less depending on the manufacturer . IC TECH SPEC-FOR ICD/ICS 705 (SCIF) doesn't state a minimum blast rating but contractors are encouraged to provide this information if available.

4.6 15 Will the government consider proposals with a period of performance greater than 240 days?

Depends on the proposed duration of the period of performance, there is follow on work schedule for BLDG 1543 that requires the SCIF to be completed in 240 days after NTP. Justification for the longer than 240 day period of performance should also be included with the proposal

END OF QUESTIONS

QUESTION AND ANSWERS (Q&A) SPREADSHEET

Request for Proposals (RFP) W912DY21R0063