Attachment_2_-_NAVFAC-USACE_Past_Performance_Questionnaire.pdf

PDF 1 MB Posted

Attached to
Commercial Utilities Program (CUP) - Utilities Mgmt Consulting Services Federal contract opportunity
Solicitation number
W912DY18R0033
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

RFP Attachment 2 - NAVFAC-USACE Past Performance Questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to Commercial Utilities Program (CUP) - Utilities Mgmt Consulting Services, newest first.
File Type Posted
Solicitation_Amendment_3_CUP_MATOC.pdf PDF
Q&A_Set_3.pdf PDF
Solicitation_Amendment_2_CUP_MATOC.pdf PDF
Q&A_Set_2.pdf PDF
Solicitation_Amendment_1_CUP_MATOC.pdf PDF
Q&A_Set_1.pdf PDF
Attachment_1_-_Ltr_of_Committment_Key_Sub-Teaming.pdf PDF
Attachment_3_-_CUP_MATOC_Price_Workbook_24May2018.xlsx XLSX spreadsheet
RFP_W912DY18R0033_CUP_MATOC_5Jun18.pdf PDF
Draft_PWS_CUP_MATOC_Rev0_10Apr18.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVFAC / USACE Past Performance Questionnaire (PPQ) Form PPQ -0 (9/30/11)

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0) CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information Firm Name: CAGE Code:

Address: DUNs Number:

Phone Number:

Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain) Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work High Med Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name:

Title:

Phone Number:

Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC/USACE requests that the client completes this questionnaire and submits directly back to the offeror.

The offeror will submit the completed questionnaire to USACE with their proposal, and may duplicate this questionnaire for future submission on USACE solicitations. Clients are highly encouraged to submit questionnaires directly to the offeror. However, questionnaires may be submitted directly to USACE. Please contact the offeror for USACE POC information. The Government reserves the right to verify any and all information on this form.

a0ctaaef Typewritten Text Attachment 2:

RFP W912DY-18-R-0033

ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit.

The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

(S) Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable No information or did not apply to your contract Ra Rating will be neither positive nor negative.

a0ctaaef Typewritten Text a0ctaaef Typewritten Text Attachment 2

TO BE COMPLETED BY CLIENT

PLEASE CIRCLE THE ADJECTIVE RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

E VG S M U N

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

E VG S M U N

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer? E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force? E VG S M U N

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes E VG S M U N

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program) E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)? E VG S M U N a0ctaaef Typewritten Text

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

E VG S M U N

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

E VG S M U N

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section. Yes No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

Yes No

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below. Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

E VG S M U N

b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

E VG S M U N

b) Compliance with contractual terms/provisions (explain if specific issues) E VG S M U N

c) Would you hire or work with this firm again? (If no, please explain below) Yes No

d) In summary, provide an overall rating for the work performed by this contractor. E VG S M U N

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

a0ctaaef Typewritten Text

Table of Contents
UDG Part 5101
UDG Part 5102 - Reserved
UDG Part 5103
UDG Part 5104
UDG Part 5105
UDG Part 5106
UDG Part 5107
UDG Part 5108 - Reserved
UDG Part 5109 - Reserved
UDG Part 5110
UDG Part 5111
UDG Part 5112 - Reserved
UDG Part 5113 - Reserved
UDG Part 5114
UDG Part 5115
UDG Part 5116 - Reserved
UDG Part 5117 - Reserved
UDG Part 5118 - Reserved
UDG Part 5119 - Reserved
UDG Part 5120 - Reserved
UDG Part 5121 - Reserved
UDG Part 5122
UDG Part 5123 - Reserved
UDG Part 5124
UDG Part 5125
UDG Part 5126 - Reserved
UDG Part 5127 - Reserved
UDG Part 5128
UDG Part 5129 - Reserved
UDG Part 5130 - Reserved
UDG Part 5131 - Reserved
UDG Part 5132 - Reserved
UDG Part 5133
UDG Part 5134 - Reserved
UDG Part 5135 - Reserved
UDG Part 5136 - Reserved
UDG Part 5137
UDG Part 5138 - Reserved
UDG Part 5139 - Reserved
UDG Part 5140 - Reserved
UDG Part 5141 - Reserved
UDG Part 5142 - Reserved
UDG Part 5143 - Reserved
UDG Part 5144 - Reserved
UDG Part 5145 - Reserved
UDG Part 5146 - Reserved
UDG Part 5147 - Reserved
UDG Part 5148 - Reserved
UDG Part 5149 - Reserved
UDG Part 5150 - Reserved
UDG Part 5151 - Reserved
UDG Part 5152 - Reserved
UDG Attachment 1 (Review Matrix)
UDG Attachment 2 (COR)
UDG Attachment 3 (IGE)
UDG Attachment 4 (PPQ)
UDG Attachment 5 (Claims and Appeals)

File details come from the government source that posted it.