W912DW23B0005R0007.pdf

PDF 920 KB Posted

Attached to
Yakima River at Union Gap Ecosystem Restoration Project Federal contract opportunity
Solicitation number
W912DW23B0005
Issued by
Department of the Army Corps of Engineers Engineering District Seattle

About this file

This document contains a bid schedule for a federal construction contract solicitation. The solicitation is for an ecosystem restoration project along the Yakima River between Terrace Heights and Union Gap in Washington. The work includes excavation, levee and berm construction, drainage structure installation, and material hauling and placement. The project is divided into three phases: a base contract and two options. The base contract involves work near Yakima Sportsman State Park, and Options 1 and 2 include additional work areas. Bidders must provide unit pricing for line items such as mobilization, excavation, fill placement, and engineering documents. The estimated value of the construction is between $10-25 million. The U.S. Army Corps of Engineers Seattle District is the contracting agency, and Yakima County is the non-federal sponsor. The solicitation number is W912DW23B0005 and bids are due in accordance with the IFB.

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

404465

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The Purpose of Amendment 0007 is to correct the Bid Schedule for CLIN# 0009.5.

CLIN 0009.5 quantity is 12 ACRES.

No other changes.

1. CONTRACT ID CODE PAGE OF PAGES

1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Jan-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW23B0005

X 9B. DATED (SEE ITEM 11)

29-Nov-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Jan-2023

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

Yakima River Gap to Gap Section 1135 Ecosystem Restoration 19008 Yakima, WA W912DW23B0005

00 11 00 - 5 R0005

BID SCHEDULE

CLIN Item # Description of Item Quantity Unit Unit Price Amount

BASE ITEMS – Sportsman Island Channel & Associated Structures + Newland Pond Fill Sites 1, 4, 5 and 6

0001 Mobilization & demobilization 1 JOB N/A $________________

0002 Construction, deconstruction, and area restoration of staging areas and access roads, and restoration of other disturbed areas, seeding, and permanent erosion control at all work areas.

1 JOB N/A $________________

0002.5 All work associated with clearing of vegetation

and LWD placement. See Note 11 below.

61 AC $________________

0003 All site work at Sportsman Park associated with large wood structures

1 JOB N/A $________________

0004 All site work at Sportsman Park including channels, berms, and upstream groin removals

0004AA Excavation 110,600 CY $_______________

0004AB Excavation 11,000 CY $_______________

0004AC Berm and groin onsite fill placement and compaction

18,400 CY $_______________

0004AD Berm and groin onsite fill placement and compaction

1,800 CY $_______________

0005 Hauling and all work to place material in Newland Pond Fill Sites 1,4, 5 and 6

0005AA Onsite disposal, fill placement and compaction 92,200 CY $________________

0005AB Onsite disposal, fill placement and compaction 9,200 CY $________________

0006 All work for O&M manuals as specified in Section 01 78 23 OPERATIONS AND MAINTENANCE MANUALS from preparation to final approval

1 JOB N/A $20,000

0007 All work for As-Built drawings as specified in Section 01 78 00 CLOSEOUT SUBMITTALS from preparation to final approval

1 JOB N/A $10,000

TOTAL ALL BASE ITEMS 0001-0007 $_____________________

OPTIONAL ITEMS #1 – Blue Slough Reconfiguration & Headgate + KOA Levee & Knob Degrade + Temporary staging area placement of fill material

00 11 00 - 6 R0005

# Description of Item Quantity Unit Unit Price Amount

0008 Mobilization & demobilization 1 JOB N/A $________________

0009 Construction, deconstruction, and area restoration of staging areas and access roads, and restoration of other disturbed areas, seeding, and permanent erosion control at all work areas.

1 JOB N/A $________________

0009.5 All work associated with clearing of vegetation

and LWD placement. See Note 11 below.

12 AC $________________

0010 Blue Slough Headwall and Headgate design (see note 5)

1 JOB N/A $________________

0011 All work associated with the construction of the Blue Slough Culvert and Headgate replacement

1 JOB N/A $________________

0012 All site work associated with Blue Slough Channel realignments

0012AA Excavation 7,000 CY $_______________

0012AB Excavation 700 CY $_______________

0013 All site work associated with Blue Slough Channel plantings and drainage structures

1 JOB N/A $________________

0014 All site work associated with the KOA Levee and KOA Knob degrades

0014AA Excavation 45,000 CY $_______________

0014AB Excavation 4,500 CY $_______________

0015 Hauling and all work to temporarily stockpile fill material in staging area(s)

0015AA Onsite disposal in staging area #3 52,000 CY $________________

0015AB Onsite disposal in staging area #3 5,200 CY $________________

0016 All work for O&M manuals as specified in Section 01 78 23 OPERATIONS AND MAINTENANCE MANUALS from preparation to final approval

1 JOB N/A $20,000

0017 All work for As-Built drawings as specified in Section 01 78 00 CLOSEOUT SUBMITTALS from preparation to final approval

1 JOB N/A $10,000

TOTAL ALL OPTIONAL ITEMS #1 0008-0017 $_____________________

00 11 00 - 7 R0005

# Description of Item Quantity Unit Unit Price Amount

OPTIONAL ITEMS #2 – DID #1 Removal + Building Blue Slough Levee + SR-24 Cross Dike Removal + Newland Pond Cut Sites 1-14 and Fill Sites 2,3 and 7

0018 Mobilization & demobilization 1 JOB N/A $_______________

0019 Construction, deconstruction, and area restoration of staging areas and access roads, and restoration of other disturbed areas, seeding, and permanent erosion control at all work areas.

1 JOB N/A $_______________

0019.5 All work associated with clearing of vegetation

and LWD placement. See Note 11 below.

144 AC $_______________

0020 All site work associate with DID #1 Levee removal, SR-24 Cross Dike degrade, and SR-24 grade control sill, including on-site borrow of riprap.

0020AA Excavation 145,000 CY $_______________

0020AB Excavation 14,500 CY $_______________

0020AC Onsite borrowed Class V riprap placement 10,000 CY $_______________

0020AD Class V riprap import and placement to supplement onsite borrow

5,000 CY $_______________

0021 All site work associate with building the Blue Slough Levee and Backwater Extension including on-site borrow and levee embankment material processing

1 JOB N/A $_______________

0022 Floodplain grading of the Newland Pond Cut Sites 1-14

0022AA Excavation 76,000 CY $_______________

0022AB Excavation 7,600 CY $_______________

0023 Hauling and all work to place material at Fill Sites 2, 3 and 7, including placement of material stockpiled in staging area 3

0023AA Onsite disposal, fill placement and compaction 252,000 CY $_______________

0023AB Onsite disposal, fill placement and compaction 25,000 CY $_______________

00 11 00 - 8 R0005

# Description of Item Quantity Unit Unit Price Amount

0024 All work for O&M manuals as specified in Section 01 78 23 OPERATIONS AND MAINTENANCE MANUALS from preparation to final approval

1 JOB N/A $20,000

0025 All work for As-Built drawings as specified in Section 01 78 00 CLOSEOUT SUBMITTALS from preparation to final approval

1 JOB N/A $10,000

TOTAL ALL OPTIONAL ITEMS #2 0018-0025 $_____________________

TOTAL ALL ITEMS 0001-0025 $_____________________

NOTES:

1) CY = Cubic Yards; AC = ACRES.

2) Quantities are estimated except where shown as “JOB.” Bids shall not be submitted for quantities less than those specified for each line item.

3) To better facilitate the receipt and proposal process, all proposals shall be submitted on copies of the latest Bid Schedule as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

4) Bidders must insert a price on all entry amount lines of numbered items of the Bid Schedule.

Failure to do so will result in the offer being unacceptable.

5) The dollar amount established in the O&M Manual and As-Built Drawings CLINS shall not be revised by Bidders.

6) Award of optional items will be made in accordance with clause 52.217-7 OPTION FOR

INCREASED QUANTITY – SEPARATELY PRICED LINE ITEM.

7) The design of the Blue Slough headwall and headgate applies only if the Optional Items #1 CLINs are exercised. Design work can’t begin until the either the full Option or CLIN 0010 is exercised.

8) Subject to DFARS 252.236-7004, Payment for Mobilzation and Demobilization.

9) Subject to FAR 52.211-18, Variation in Estimated Quantities.

10) Subject to AFARS 5152.211-9001, Variation in Estimated Quantites – Subline Items (CLINS 0004,0005,0012,0014,0015,0020,0022, and 0023)

11) CLINs 0002.5, 0009.5, and 0019.5 include, where required, felling trees with attached rootwads and branches, clearing and grubbing, decking, transport, and final placement of LWD and cleared vegetation as indicated on drawings. Given quantities for these CLINs represent dry planar areas of footprint within which clearing may be required, including portions of footprint where trees or other vegetation shall remain in place. Placement of earthen and inert fill in Newlands Ponds is covered by other CLINs.

File details come from the government source that posted it. Updated .