This solicitation is for the rehabilitation of generator rewinds at Chief Joseph Dam in Washington state. The U.S. Army Corps of Engineers, Seattle District is seeking bids to disassemble and reassemble 16 generators, including the removal of existing stator windings and installation of new windings. Additional work includes supplying a new stator core for one unit, cleaning and testing existing cores for potential reuse in other units, replacing generator breaker current transformers and raw water piping, cleaning and reusing brake systems, replacing brake rings and pads, and installing new machine condition monitoring systems. Optional work includes replacement of up to 15 stator cores, field winding refurbishment, and model validation testing of units. The magnitude of the project is estimated between $100 million and $250 million. Bids are due by the date specified in solicitation W912DW22R0005.

View the file

Other files

File Type Posted
W912DW22R0005 R0006.pdf PDF
W912DW22R0005 R0005.pdf PDF
W912DW22R0005-R0004.pdf PDF
W912DW22R0005-R0003.pdf PDF
W912DW22R0005-R0002.pdf PDF
W912DW22R0005-R0001.pdf PDF
Brand Name JA - CJD Generator Rewinds 1-16.pdf PDF
Attachment C PROPOSAL DATA SHEET.docx DOCX document
Attachment A Past Performance Project Relevancy Template.docx DOCX document
Attachment B SBPCD.docx DOCX document
Attachment D PPQ.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. W912DW22R0005

Seattle District

Chief Joseph Dam Generator Rewinds (1-16), Bridgeport, WA

Construction Solicitation and Specifications

UNRESTRICTED

November 2021

W912DW22R0005

Chief Joseph Dam Generator Rew inds (1-16)

MONIQUE A PAANO 206-764-6084

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

23-Nov-2021

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________2920 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________0 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________22 Feb 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

10:00 AM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

206-764-6817FAX:TEL: TEL: FAX:

W912DW22R0005 111

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 01 10 - Table of Contents

TABLE OF CONTENTS

SECTION TITLE

SF1442 Construction Solicitation

00 10 00 Price Schedule

00 21 00 Instructions, Conditions and Notice to Offerors

00 21 16 Proposal Submission

00 22 00 Evaluation Criteria

00 45 00 Representations and Certifications and other Statements of Offerors, and Pre-Award Information

00 62 00 Corporate Certificate

00 72 00 Contract Clauses

00 73 00 Supplementary conditions, which include the following:

a) Davis-Bacon General Wage Decision No. WA20210068 rev.1

b) Special Clauses

c) 00 73 00-A Index of Drawings

d) Government Furnished Property

e) Economic Price Adjustment information

01 00 00 Technical Specifications

Section 00 10 00 - Solicitation

PRICE SCHEDULE

PRICE SCHEDULE

CHIEF JOSEPH DAM GENERATOR REWINDS (1-16)

CLIN DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT

Base Items (Units 5-12)

0100 Site Mobilization 1 Job N/A $____________

0101 Site Demobilization 1 Job N/A $____________

Pre-Disassembly Investigation & Measurements

8 Each $________ $____________

Disassemble Generating Unit & Inspect Components

8 Each $________ $____________

Reassemble Generating Unit with New Components

8 Each $________ $____________

Operational Testing After Reassembly of Generating Unit

8 Each $________ $____________

0106 Stator Winding Design 1 Job N/A $____________

Complete Set of Stator Coils, Supplies, & Accessories Furnish, Install, & Test

8 Each $________ $____________

Manufacture Prototype Coils Identical to Production Coils & Perform Prototype Testing

1 Job N/A $____________

Furnish Production Run Coils For & Perform Production Run Testing

1 Job N/A $____________

0110 Remove Stator Winding 8 Each $________ $____________

0111 Inspect & Clean Stator Core 8 Each $________ $____________

Perform Interlaminar Insulation Testing

8 Each $________ $____________

0113 Furnish Stator Core 1 Each $________ $____________

0114 Inspect, Clean, & Test Rotor 8 Each $________ $____________

0115 Reinsulate Rotor Field Leads 8 Each $________ $____________

0116 Perform Special Field Tests 1 Job N/A $____________

0117 Furnish Spare Generator Parts 1 Job N/A $____________

Replace Raw Water Piping, Insulation and Valves

8 Each $________ $____________

0119 Replace Generator Air Coolers 8 Each $________ $____________

0120 Replace the Generator Brake Pads 8 Each $________ $____________

Inspect & Clean the Generator Brake System

8 Each $________ $____________

0122 New Generator Brake Ring Design 1 Job N/A $____________

Furnish & Install New Generator Brake Ring

8 Each $________ $____________

Machine Condition Monitoring System Furnish, Install, Test, & Make Operational

8 Each $________ $____________

Machine Condition Monitoring System Furnish Spare Parts

1 Job N/A $____________

Replace Unit Panel Meters & Misc.

Electrical Work

8 Each $________ $____________

Replace Generator Heaters & Wiring

8 Each $________ $____________

Replace Generator Bearing Protective Devices & Enclosure

8 Each $________ $____________

Initial Stator Foundation Inspection & Minor Repair Plan

8 Each $________ $____________

0130 Replace Generator Breaker CTs 8 Each $________ $____________

Furnish Operations and Maintenance (O&M) Manuals

1 Job N/A $50,000

0132 Furnish As-built Drawings 1 Job N/A $50,000

Total Amount for Base Items $______________________

Optional Items (Units 13-16 and Units 1-4)

0200-0220 OPTIONAL WORK

Pre-Disassembly Investigation & Measurements 8 Each

Disassemble Generating Unit & Inspect Components 8 Each

Reassemble Generating Unit with New Components 8 Each

Operational Testing After Reassembly of Generating Unit

8 Each $________ $____________

Complete Set of Stator Coils, Supplies, & Accessories Furnish, Install, & Test 8 Each

0205 Remove Stator Winding 8 Each

Inspect & Clean Stator Core 7 Each

Perform Interlaminar Insulation Testing 7 Each

Inspect, Clean, & Test Rotor 8 Each

Reinsulate Rotor Field Leads 8 Each

Replace Raw Water Piping, Insulation and Valves 8 Each

Replace Generator Air Coolers 8 Each

Replace the Generator Brake Pads

Each

Inspect & Clean the Generator Brake System

8 Each $________ $____________

Furnish & Install New Generator Brake Ring 8 Each

Machine Condition Monitoring System Furnish, Install, Test, & Make Operational 8 Each

Replace Unit Panel Meters & Misc. Electrical Work

Each

Replace Generator Heaters & Wiring

Each

Replace Generator Bearing Protective Devices & Enclosure

Each

Initial Stator Foundation Inspection & Minor Repair Plan

Each

Replace Generator Breaker CTs

Each

0300-0312 OPTIONAL WORK

Reinsulate Field Coils NTE 1152 Each

Furnish Production Run Coils & Perform Production Run Testing for Additional Batches 1 Job

0302 Inspect & Clean Stator Core 1 Each

Perform Additional Interlaminar Insulation Testing NTE 16 Each

0304 Perform Minor Stator Core Repair NTE 15 Each

Furnish Stator Core NTE 15 Each

Install Stator Core NTE 16 Each

0307 Perform NERC Compliance Testing NTE 16 Each

0308 Low-Pressure Epoxy Adhesive Grout Injection NTE 300

Linear Feet

Stator Foundation Shallow- Face Grout & Concrete Damage Repair NTE 4

Cubic Feet

0310 Liquid Penetrant Method

100 EST

Man Hours

0311 Magnetic Particle Method

100 EST

Man Hours

0312 Ultrasonic Method

100 EST

Man Hours

Total Amount for Optional Items

TOTAL OF BASE AND

OPTIONAL ITEMS

Notes:

1. In the event there is a difference between a unit price and the extended total, the unit price will be held to be the intended offer. If the offeror shows only the total price but fails to enter a unit price, the total divided by the estimated quantity will be held to be the intended unit price.

2. Any price for items indicated above which are unbalanced as to price may be rejected as non-responsive. An unbalanced offer is one which is based on price significantly less than cost for some work and price which is significantly overstated for other work.

3. 100% Design Projects cannot be altered, changed, or re-designed in any way. No alternate proposals will be accepted.

4. Award of optional items will be made in Clause 52.217-7 OPTION FOR INCREASED QUANTITY.

5. The dollar amount established in Contract Line Item Nos. 0131 and 0132 shall not be revised by the Offerors.

-- End of Document --

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

Section 00 21 00 - Instructions

INSTRUCTIONS FOR OFFERORS

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFEROR

1. General Description of Work

2. Disclosure of the Magnitude

3. Copies of Solicitation Documents and Amendments

4. Offeror’s Questions and Comments

5. Small Business Size Standard / NAICS Code

6. Proposal Expenses and Pre-Award Costs

7. Accuracy in Proposals

8. Proposal Submittals

9. Bid Guarantee

10. Subcontracting Plan

11. Solicitation Provisions

1. General Description of Work:

Contract Title: Chief Joseph Dam Generator Rewinds (1-16)

The U.S. Army Corps of Engineers (USACE), Seattle District, requires rehabilitation of the Chief Joseph Generator Rewinds (16 Units) and incidental related work. The following is a list of the major items of work included in this Contract. The work includes the removal of the existing components and systems of components which are known to have lead-based paint, without being specifically identified. The work includes:

a. Mobilization and demobilization.

b. Disassemble and reassemble 16 generators, including generator alignment.

c. Removal of 16 existing stator windings.

d. Installation of 16 new stator windings, including winding supplies and connections such as circuit rings, surge rings, main and neutral leads, neutral Current Transformer (CTs), wedges, fillers, etc.

e. Supply and install one stator core in a to be determined unit.

f. Reuse up to 15 existing stator cores, following cleaning and testing.

g. Optional replacement of up to 15 stator cores.

h. Reuse existing field winding and collector rings of all units, following cleaning and testing.

i. Optional field winding refurbishment on a per pole basis.

j. Replace generator breaker CTs for all units.

k. Replacement of all generator raw water piping from the cooling water strainer to the discharge valve, with the exception of the thrust bearing cooling branch, for all units.

l. Clean, inspect, and reuse the brake system of all units without disassembly.

m. Redesign and replace the brake ring of all units.

n. Replace generator brake pads.

o. Install new Machine Condition Monitoring (MCM) system including shaft vibration, generator air gap, and continuous online partial discharge monitoring devices for all units.

p. Instrumentation for generator temperature monitoring, Resistance Temperature Detector (RTDs), MCM system design drawings and specifications, interfacing with Generic Data Acquistiion and Control System (GDACS) or evaluating alternative interfaces for all units.

q. Stator foundation inspection of all units with optional minor repairs.

r. Replace all generator air coolers.

s. Optional model validation testing of up to 16 units.

2. Disclosure of the Magnitude of Construction:

In accordance with FAR 36.204 “Disclosure of the Magnitude of Construction Projects,” the magnitude of the project is estimated between $100,000,000 and $250,000,000.

3. Copies of Solicitation Documents and Amendments:

Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the U.S. Government’s Contract Opportunities website at: https://SAM.gov under Solicitation Number W912DW22R0005. A list of interested vendors (potential offerors and subcontractors) is available on the web site (registration required) with the solicitation announcement.

NOTE: SAM.gov is the new official U.S. Government website for Contract Opportunities.

It shall be the contractor’s responsibility to check the websites for any amendments. The Offeror shall submit in the proposal all requested information specified in this solicitation.

There will be no public opening of the proposals received as a result of this solicitation.

4. Offeror’s Questions and Comments:

Bidder Inquiry

I. Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet.

a. To submit and review bid inquiry items, bidders/offerors will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and then click continue.

b. From this page you may view all bidder inquiries or add inquiry.

c. Bidders/offerors will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

d. The Solicitation Number is: W912DW22R0005

e. The Bidder Inquiry Key is: 6HNC9S-522UQC

II. The Bidder Inquiry System will be unavailable for new inquires 3 business days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

III. Offerors are requested to review the specification in its entirety, review the

Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

IV. The call center operates weekdays from 8AM to 5PM U.S. Central Time

Zone (Chicago). The telephone number for the Call Center is 800-428-

HELP.

V. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

5. Small Business Size Standard / NAICS Code:

See Section 00 45 00, Provision 52.204-8 for the NAICS code and small business size standard.

6. Proposal Expenses and Pre-Award Costs:

This Request for Proposals (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.

7. Accuracy in Proposals:

Proposals must set forth full, accurate, and complete information as required by this RFP (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.

8. Proposal Submittals

THE SOLICITATION PERIOD FOR THIS RFP WILL BE 90 DAYS. This period is based on industry feedback and is inclusive of upcoming holidays. There will be no extensions.

In strict compliance with guidance relating to the current situation with COVID-19 and social distancing, the only authorized transmission methods for proposals in response to this solicitation is electronically via SAFE.

INSTRUCTIONS FOR SUBMITTING ELECTRONIC PROPOSALS:

In an effort to reduce paperwork and cost, all proposals shall be submitted electronically through the SAFE site. Submission shall be in Adobe PDF format. You are limited to five

(5) maximum files per upload (total size cannot exceed 2GB). If you have a large number of files, it is recommended that you combine or ZIP your files before uploading to the

SAFE site. Offerors may use compression utility software such as WinZip or PKZip to reduce file size and facilitate transmission.

REQUEST FOR UPLOAD CODE: Offerors must email Contract Specialist Monique Paano at monique.a.paano@usace.army.mil AND to Contracting Officer Camilla (Cam) Allen at Camilla.allen@usace.army.mil no later than five (5) working days prior to the proposal due date to receive a request code which will allow for file uploads via the SAFE site. Offerors that fail to email for a request code five (5) working days before the proposal submission date may not be able to receive a request code in time to upload their submission.

FILE DESCRIPTION: Include a “File Description” for each file(s) you upload. The “File Description” will be included in the e-mail notice to each of the recipients you choose to have access your file(s). NOTE: Do NOT enter Privacy Act Data (Personal Identifiable Information (PII) in the File Description).

FILE NAMING CONVENTION: Each file name shall begin with the solicitation number followed by the firm’s name and a brief file description. Please see examples below. To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention:

W912DW22R0005-FIRMNAME-Proposal Volume I W912DW22R0005-FIRMNAME-Proposal Volume II

See Section 00 21 16 for detailed content requirements for Volumes I and II.

INSTRUCTIONS TO FOLLOW ON THE SAFE WEBSITE:

1. Once at the SAFE website, select the “Drop-Off” icon. This allows users without a CAC or users whose computer is not configured to read a CAC the option to access the SAFE site as a guest.

2. After selecting the “Click Here” link you will be prompted to add your personal information, file information, recipient (Government representative) information and e-mail settings.

3. When completing your file information for transmittal via the SAFE website, you will be required to enter the e-mail address for all recipients. For this solicitation, the recipients are the Contract Specialist and the Contracting Officer. The Contract Specialist for this solicitation is monique.a.paano@usace.army.mil and the Contracting Officer is camilla.allen@usace.army.mil. The e-mail address of the Government Employee who initiated the request code will be automatically entered. The Proposer must enter the e-mail address for both the Contracting Officer and Specialist. The Proposer can enter an additional e-mail address if desired. After entering the e-mail address, click the ADD button to add the person(s) e-mail to the “Recipients List” of your response. When your proposal is submitted, a notification will be sent to the recipients you added.

NOTE: Do NOT send the SAFE site packages to group e-mail accounts.

Even if you successfully upload your proposal to the SAFE site, notification will not be sent to the government recipients until you verify your e-mail address. Entering an incorrect e-mail may result in the rejection of your submission for lateness. An Offeror can confirm proper submission by the “Drop-Off Completed” screen which generates based on proper file submission.

NOTE: It has been reported that documents are more quickly uploaded into the SAFE website when using a Firefox web browser. The Government cannot verify that this is true and offers no guarantee that Offerors will have more success utilizing any particular browser.

RECEIPT OF SUBMISSIONS:

For the purposes of establishing whether a proposal submission is considered timely, the Government considers the date and time the submission is completely uploaded into the SAFE website. For proposals larger than the 2GB capacity of the SAFE website and require multiple submissions, the Government will consider the date and time the last submission is completely uploaded into the SAFE website. Do not assume that electronic communication is instantaneous. It can take several minutes or even hours in some cases.

9. Bid Guarantee:

The Standard Form (SF) 24, dated 08/2016, shall be used for the submission of your bid bond and can be obtained from https://www.gsa.gov/reference/forms#SF. Submit the bid bond via email with your proposal

10. Subcontracting Plan

Submission Requirements (NOTE: This Requirement only applies to the otherwise successful Offeror if it is other than a Small Business.)

If the Offeror proposing on this solicitation is a large business concern, in accordance with the definition as identified in FAR Clause 52.219-1, “SMALL BUSINESS PROGRAM REPRESENTATION”, upon notification that it is the apparent successful Offeror, the firm must submit a small business subcontracting plan in accordance with FAR Clause 52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN. The subcontracting plan format will be provided to the apparent successful offeror if it is a large business. The goals established for small business, small disadvantaged business, woman-owned business, HUBZone business, Service-disabled veteran-owned small business participation are:

Goals. The U.S. Army Corps of Engineers considers the following goals reasonable and achievable for the performance of the resultant contract:

Small Business – 5%

HUBZone Small Business – 0.25%

Service-Disabled Veteran-Owned Small Business – 0.75%

Veteran-Owned Small Business – 2%

Small Disadvantaged Business – 1.5%

Women-Owned Small Business – 1.5%

The Small Business Subcontracting Plan shall be thorough, complete, and in accordance with FAR Clause 52.219-9 and DFARS Clause 252.219-7003, as it will be incorporated into the contract upon award of the contract to the Offeror, if acceptable and upon final approval of the Contracting Officer. The Plan shall include a description of the types of services the firm proposes to subcontract with small business (SB), small disadvantaged business (SDB), woman-owned small business (WOSB), HUBZone business, and service-disabled veteran-owned small business (SDVOSB), along with the proposed percentages of their participation, to demonstrate a plan to meet the subcontracting goals that will apply to these contracts. The Offeror shall provide specific information on proposed subcontracted effort for this project.

11. Solicitation Provisions

See the applicable Provisions for this Solicitation in Section 00 21 00 and Section 00 45 00.

CLAUSES INCORPORATED BY REFERENCE

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.211-6 Brand Name or Equal AUG 1999 52.215-1 Alt I Instructions to Offerors--Competitive Acquisition (Jan 2017) -

Alternate I

OCT 1997

52.215-16 Facilities Capital Cost of Money JUN 2003 52.215-20 Requirements for Certified Cost or Pricing Data or

Information Other Than Certified Cost or Pricing Data

OCT 2010

52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work

MAY 2014

52.228-1 Bid Guarantee SEP 1996 252.215-7008 Only One Offer JUL 2019 252.215-7010 Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data

JUL 2019

252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors.

JAN 2018

CLAUSES INCORPORATED BY FULL TEXT

52.215-20 REQUIREMENTS FOR COST OR PRICING DATA OR INFORMATION OTHER THAN COST

OR PRICING DATA (OCT 2010)—ALTERNATE III (OCT 1997)

(a) Exceptions from cost or pricing data. (1) In lieu of submitting cost or pricing data, offerors may submit a written request for exception by submitting the information described in the following subparagraphs. The Contracting Officer may require additional supporting information, but only to the extent necessary to determine whether an exception should be granted, and whether the price is fair and reasonable.

(i) Identification of the law or regulation establishing the price offered. If the price is controlled under law by periodic rulings, reviews, or similar actions of a governmental body, attach a copy of the controlling document, unless it was previously submitted to the contracting office.

(ii) Commercial item exception. For a commercial item exception, the offeror shall submit, at a minimum, information on prices at which the same item or similar items have previously been sold in the commercial market that is adequate for evaluating the reasonableness of the price for this acquisition. Such information may include--

(A) For catalog items, a copy of or identification of the catalog and its date, or the appropriate pages for the offered items, or a statement that the catalog is on file in the buying office to which the proposal is being submitted. Provide a copy or describe current discount policies and price lists (published or unpublished), e.g., wholesale, original equipment manufacturer, or reseller. Also explain the basis of each offered price and its relationship to the established catalog price, including how the proposed price relates to the price of recent sales in quantities similar to the proposed quantities;

(B) For market-priced items, the source and date or period of the market quotation or other basis for market price, the base amount, and applicable discounts. In addition, describe the nature of the market;

(C) For items included on an active Federal Supply Service Multiple Award Schedule contract, proof that an exception has been granted for the schedule item.

(2) The offeror grants the Contracting Officer or an authorized representative the right to examine, at any time before award, books, records, documents, or other directly pertinent records to verify any request for an exception under this provision, and the reasonableness of price. For items priced using catalog or market prices, or law or regulation , access does not extend to cost or profit information or other data relevant solely to the offeror's determination of the prices to be offered in the catalog or marketplace.

(b) Requirements for cost or pricing data. If the offeror is not granted an exception from the requirement to submit cost or pricing data, the following applies:

(1) The offeror shall prepare and submit cost or pricing data and supporting attachments in accordance with Table 15-2 of FAR 15.408.

(c) Submit the cost portion of the proposal via the following electronic media: Electronic Spreadsheet

As soon as practicable after agreement on price, but before contract award (except for unpriced actions such as letter contracts), the offeror shall submit a Certificate of Current Cost or Pricing Data, as prescribed by FAR 15.406-2.

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Fixed Price with Economic Price Adjustment contract resulting from this solicitation.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

Contracting Officer U.S. Army Corps of Engineers – Seattle District 4735 East Marginal Way South, Bldg 1202 Seattle, WA 98134-2388

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://www.acquisition.gov

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

252.215-7012 REQUIREMENTS FOR SUBMISSION OF PROPOSALS VIA ELECTRONIC MEDIA (JAN 2018)

The Offeror shall submit the cost portion of the proposal via the following electronic media: Electronic Spreadsheet and PDF files via electronic mail.

Section 00 21 16 - Instructions to Proposers

PROPOSAL SUBMISSION

A. PROPOSAL SUBMISSION

The proposal submission instructions are contained in Section 00 21 16 of the Request for Proposal (RFP). Section 00 21 16 of the solicitation contains specific information on what must be furnished with the proposal and identifies evaluation criteria that will be used in evaluating proposals received.

1. INTRODUCTION

1.1 Your firm is invited to submit a proposal in response to Request for Proposal (RFP) Number W912DW22R0005 for the project entitled “CJD Generator Rewind Units 1-16” located at Bridgeport, WA”. The Government intends to procure this requirement on a competitive basis in accordance with the provisions set forth in FAR Part 15 Contracting by Negotiations and within this RFP.

1.2. A fixed-price contract with economic price adjustment will be awarded to the Offeror submitting a proposal that (a) conforms to this RFP, (b) is considered to offer the best value to the Government in terms of the evaluation factors, including price, and (c) is determined to be in the best interest of the Government.

Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.

2. GENERAL PROPOSAL REQUIREMENTS

2.1 Proposal Format

The proposal shall be organized into the following two volumes:

a. Volume 1: Technical Proposal, 1 electronic copy (defined in paragraph 3 of this Section)

b. Volume 2: Price Proposal, 1 electronic copy (defined in paragraph 3 of this Section)

2.2 Content – General

The submission shall be clearly indexed and logically assembled. Proposals must set forth full, accurate, and complete information as required by this RFP. Absence of information will be deemed as if no support for that criterion was provided. Offerors submitting proposals should limit submission to data essential for evaluation of proposals so that a minimum of time and money is expended in preparing information required by the RFP. Penalty for making false statements in proposals is prescribed in 18 U.S.C. 1001.

2.3 Table of Contents

A Table of Contents should be incorporated within both Volumes.

2.4 Page Numbering

All pages of each volume shall be appropriately identified with complete company name, date and RFP number in the header and/or footer.

3. ELECTRONIC PROPOSAL SUBMITTAL REQUIREMENTS

3.1 File format

The electronic proposal shall be Portable Document Format, filename extension: “.pdf” and suitable for viewing in Adobe Reader. Text must be searchable. Please use Arial font, type 11.

3.2 Number of files

The proposal contents shall be presented as a separate PDF file for each Volume – (1) Technical Proposal, (2) Price Proposal.

3.3 Method of submission The electronic version of the proposals shall be submitted via SAFE.

REQUIRED SECTIONS FOR SUBMITTAL Proposals shall be organized as indicated below:

REQUIRED SECTIONS FOR VOLUME 1: TECHNICAL PROPOSAL

Table of Contents

Tab 1: Factor 1: Past Performance

Tab 1a – Relevancy of Past Performance (Include Attachment A)

Tab 1b – Past Performance Questionnaires (Include PPQ) Tab 2: Factor 2: Technical Approach and Schedule Tab 3: Factor 3: Small Business Participation (Include Attachment B)

REQUIRED SECTIONS FOR VOLUME 2: PRICE PROPOSAL

Table of Contents Factor 4: Price Proposal

Tab 1: Cover Letter

Tab 2: SF1442, Solicitation, Offer and Award Tab 3: Pricing Schedule (Include Attachment C) Tab 4: Representations and Certifications Tab 5: Most recent Financial Statement Tab 6: Bid Bonds

5. DETAILED CONTENT REQUIREMENTS FOR VOLUME 1: TECHNICAL

PROPOSAL

Technical Proposal, Volume 1: consists of three (3) factors. This section shall be specific and complete, demonstrating a thorough understanding of the requirements. It shall include, where applicable, diagrams and/or charts. Repeating or restating the specifications without sufficient elaboration will be determined to show a lack of understanding of the requirement.

PAGE LIMITS:

Factor 1 – Not to exceed thirty (30) pages, not including PPQs or CPARs.

Factor 2 – Not to exceed forty (40) pages Factor 3 – Not to exceed twenty (20) pages

See Section 00 22 00 for submission requirements for Evaluation Factors 1-3.

6. DETAILED CONTENT REQUIREMENTS FOR VOLUME 2: PRICE PROPOSAL

This volume shall consist of all information, required to support proposed prices.

Price Proposal, Volume 2 (TABS 1-6)

TAB 1: Cover Letter: Submit a cover letter as the first page of this volume. The cover letter shall reflect the following information:

a. RFP number.

b. Name, address, e-mail address, and telephone numbers of the firm signing the SF 1442.

c. Names, titles, e-mail addresses, telephone numbers of person(s) authorized to negotiate on the firm's behalf with the Government in connection with this RFP.

d. Name, title, and signature of the person(s) authorized to sign the proposal.

e. A statement specifying agreement with all terms, conditions, and provisions included in the RFP and agreement to furnish any and all items upon which prices are offered at the proposed item prices.

f. A statement indicating compliance with all insurance requirements stated herein and that evidence of such will be provided after Contract award.

g. Organizational Conflicts of Interest (OCI) Disclosure: See Section 00 22 00 for requirements.

h. Final Proposal Revisions: If required to submit a Final Proposal Revision following evaluation of initial proposals, the accompanying cover letter must identify all changes made to the firm's initial proposal.

i. Prime Offeror: If the Offeror is submitting as a Joint Venture (JV), the DUNS and CAGE

Code for each firm representing the JV must be included.

TAB 2: SF1442, SOLICITATION, ALL AMENDMENTS AND OFFER

This tab will not be rated but will be evaluated for responsiveness. The SF1442 shall be filled out completely by the offeror and signed by an official that is authorized to bind the company.

The offeror shall also acknowledge all amendments to the solicitation in Block 19 of the 1442.

TAB 3: Pricing Schedule

Section 00 10 00. Provide a completed pricing schedule along with a price breakdown as described in Section 00 22 00.

TAB 4: COMPLETED REPRESENTATIONS AND CERTIFICATIONS

Section 00 45 00, Representations, Certifications and Pre-Award information, fill in all information to include company information, banking information and bonding/surety information of the firm signing the SF1442.

Include a completed corporate certificate as found in section 00 62 00.

TAB 5: Most recent Financial Statement

TAB 6: Bid Bonds

PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

The Government is not responsible for costs incurred in the preparation of a proposal or for any other costs incurred prior to the execution of a contract.

Section 00 22 00 - Supplementary Instructions

EVALUATION CRITERIA

A. BASIS FOR AWARD

The award will be made based on the best overall (i.e., best value) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the four (4) evaluation factors: Past performance is more important than technical approach and schedule with small business participation being the least important. The non-price factors when combined will be significantly more important than price. To receive consideration for award, the proposal must obtain an evaluation rating of “Neutral Confidence” or higher for Factor 1 Past Performance, must obtain an evaluation rating of “Acceptable” or higher for Factor 2 Technical Approach and Schedule, must obtain an evaluation rating of “Acceptable” or higher for Factor 3 Small Business Participation, and must have a price that is considered fair and reasonable. Award may not necessarily be made to the lowest price offered. NOTE: ALL NON-

PRICE FACTORS WHEN COMBINED ARE SIGNIFICANTLY MORE IMPORTANT

THAN PRICE.

B. FACTORS TO BE EVALUATED

The following evaluation factors will be used to evaluate each proposal:

Award will be made to the offeror whose proposal is most advantageous to the Government based upon an integrated assessment of the evaluation factors described below.

FACTOR 1: Past Performance - Each offeror’s past performance will be reviewed to determine recency, relevancy and quality.

FACTOR 2: Technical Approach and Schedule - Evaluation of the offeror’s proposal shall address the technical approach and schedule as it applies to the Summary of Work (SOW). A detailed explanation of the criteria for the evaluation is set forth in the “Evaluation Approach”, Paragraph C of this section. During evaluations of each proposal, the Government will assign each factor an adjectival rating and write a narrative evaluation reflecting the identified findings.

FACTOR 3: Small Business Participation – Evaluation of the proposal will include the review of the Small Business Participation Commitment Document and the extent of Small Business Participation. A detailed explanation of the criteria for the evaluation is set forth in the “Evaluation Approach”, Paragraph C of this section.

FACTOR 4: Cost/Price - The resulting contract will be fixed-price with economic price adjustment. Price reasonableness will be utilized in the evaluation of the proposal. Offers will also be analyzed to determine if the prices are unbalanced (FAR 15.404-1(g)).

C. EVALUATION APPROACH

All proposals shall be subject to evaluation by the Source Selection Team (SST).

1. The overarching evaluation approach for all factors is as follows:

a. Adequacy of Response. The proposal will be evaluated to determine whether the offeror’s methods and approach have adequately and completely considered, defined, and satisfied the requirements specified in the RFP. The proposal will be evaluated to determine the extent to which each requirement has been addressed in the proposal in accordance with the proposal submission section of the RFP.

b. Feasibility of Approach. The proposal will be evaluated to determine the extent to which the proposed approach is workable and the end results achievable. The proposal will be evaluated to determine the extent to which successful performance is contingent upon proven devices and techniques. The proposal will be evaluated to determine the extent to which the offeror is expected to be able to successfully complete the proposed tasks and technical requirements within the required schedule.

2. The Non-Price Evaluation Factors are as follows:

2.1 Factor 1- Past Performance: The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required work during performance of the awarded contract. The past performance evaluation considers an offeror's demonstrated recent and relevant record of performance in supplying products and services required to meet the contract’s requirements. The recency and relevance of the information, source of the information, context of the data, and general trends in contractor's performance shall be considered. There are three aspects to the past performance evaluation:

recency, relevancy (including context of data), and quality of performance (including general trends in contractor performance and source information). These will be combined to establish one past performance rating for each Offeror.

2.1.1 Relevancy of Past Performance, Tab 1a

The Offeror shall submit information on at least three (3) projects, but no more than five

(5) projects to demonstrate the offeror’s recent and relevant experience. If more than five (5) projects are submitted only the first five projects will be evaluated. Relevant means that submitted projects are similar in terms of scope, and complexity as work described in Section 01 11 00.00 26 Summary of Work of the solicitation. The relevancy of each Offeror’s submitted Past Performance projects will be rated based on the completeness and technical details of each project’s narrative describing the work performed (i.e. how well the project’s scope is described) and how pertinent the work is to the Section 01 11 00.00 26 Summary of Work, as well as the depth and breadth of each project’s scope (i.e. how many of the Section 01 11 00.00 26 Summary of Work technical requirements are covered by the project’s scope). Offerors shall ensure each project meets the definition of a ‘project’ below.

2.1.2 Past Performance Relevant Experience Submission Criteria

Criteria for the Offeror’s Factor 1:

a. Submit information of at least three (3),but no more than five (5) projects to demonstrate the offeror’s relevant past work experience and subsequent performance.

b. Ensure submitted projects are relevant to the work requirements noted in Section 01 11

00.00 26 of the RFP individually or in combination thereof.

c. Ensure each submitted project meets the definition of a ‘project’, as defined below; AND

d. Submitted projects shall be at least 75% physically completed, not based on amount invoiced, within the last ten (10) years prior to the solicitation issue date. At least 75% physically completed means at least 75% of the contractual requirements have been accomplished.

e. Submit Past Performance Project Relevancy Information Summary Form (Attachment A) for each submitted project.

f. All submitted information for each project provided in Tab 1a should be limited to four (4) pages per project.

2.1.3 Definitions

a) Scope is defined as:

The rewind of a large hydropwer generator of which the scope will be repeated multiple times.

b) An Offeror is defined as:

For the purpose of past performance evaluation, an ‘Offeror’ shall be defined as the Prime submitting the proposal. The past experience and past performance record of each firm meeting the definition in the business arrangement may be evaluated by the Government.

c) Prime is defined as:

For the purpose of past performance evaluation, a ‘Prime’ shall be defined as the Firm or any of the Firms making up a Joint Venture (JV) submitting a proposal in response to this solicitation.

d) A Project is defined as:

In order to be deemed a ‘project’, it must meet one, and only one, of the following:

a. 1 single Task Order against an IDC (a “D” contract) covering work performed at one single site;

b. 1 single Task Order against an IDC (a “D” contract) covering work at multiple sites within one single installation or facility;

c. 1 single “C” type contract (not a “D” contract) covering work performed at one single site (the following also will qualify as a non-‘D’-type: a Cooperative Agreement or Grant; single BPA/BOA Call; single order against a GSA Schedule;

or Purchase Order);

d. 1 single “C” type contract (not a “D” contract) covering work performed at multiple sites within one single installation or facility (the following also will qualify as a non-‘D’-type: a Cooperative Agreement or Grant; single BPA/BOA Call; single order against a GSA Schedule; or Purchase Order);

e. 1 single Task Order against an IDC (a “D” contract) covering work performed at multiple but separate installations, meaning the installations are in different cities, states, etc.; OR

f. 1 single “C” type contract (not a “D” contract) covering work performed at multiple but separate installations, meaning the installations are in different cities, states, etc. (the following also will qualify as a non- ‘D’-type: a Cooperative Agreement or Grant; single BPA/BOA Call; single order against a GSA Schedule;

or Purchase Order)

e) Recent is defined as:

Project that has been completed within ten (10) years of the solicitation issue date, or one where the construction is at least 75% complete (measured by performance period days) as of the solicitation issue date. (Offerors are responsible for providing start and completion dates for each completed project, or the start and scheduled completion dates for projects currently under construction.)

f) Relevant is defined as:

Projects that are similar in scope (type, size, complexity and dollar value) to the project described in this solicitation. For a project to be assessed any degree of “relevancy”, it must reflect performance of construction type work similar to the project required by this solicitation.

g) Quality of Performance is defined as:

The offeor’s quality or work, as well as the offeror’s management of a quality control program, while performing as a contractor on past contracts. Quality will be reviewed for all past performance information collected to determine the quality of the offeror’s performance. The evaluation of quality will be used to determine if the offeror has demonstrated consistent quality of performance that conformed to contractual requirements. Specific to construction contracts/orders, the evaluation of an offeror’s quality of performance may include and consider the following aspects based on information obtained from past projects:

- Has a quality product been provided?

- Did the contractor maintain a quality control system during contract performance?

If yes, how well were the following areas performed:

Contractor’s ability to maintain quality control Performance of accessory testing Implementation of 3-phase inspection process CQC (Contractor Quality Control) documentation

Identification and correction of deficient work Reviews of materials and shop drawings Whether there was incorporation of unspecified materials

For establishing the overall quality of the offeror’s past performance, the evaluation conducted does not establish, create, or change the existing record and history of the offeror’s past performance on past contracts; rather, the past performance evaluation process gathers information from customers and through review of assessment reports (i.e. CPARs) to determine how well the offeror performed on past contracts. A separate quality assessment rating will not be given, rather, Factor 1 Past Performance confidence assessment rating is based on the offeror’s overall evaluation of recency, relevance, and quality of performance.

2.1.4 Past Performance Project Relevancy Information Summary:

The Past Performance Project Relevance Information Summary Form (Attachment A) must be used, completed in its entirety, and submitted as part of Factor 1 for each project.

The information obtained from this form is required to evaluate relevancy. Offerors may expand the form as necessary to accommodate the required project information; however, the use of an alternate form will not be accepted.

Attachment A (example):

Past Performance Project Relevancy

Information Summary Form Project Name:

Project Location:

Address:

Installation Name (if applicable)

Owners/Client Point of Contract (POC):

POC Name:

POC Phone Number:

POC E-mail:

Contract Number: Task Order Number (if applicable):

Was the project terminated early, were cure/show-cause letters issued or were Liquidated Damages assessed?

Yes or No (if yes, explain)

Offeror’s Role: (Prime or Subcontractor) [What specific items of work did you perform as the prime or subcontractor]

Percentage of total value of contract performed by the Offeror: (If the Offeror was the Prime, what percentage was subcontracted; if the Offeror was the subcontractor, what dollar amount and percentage of the total project amount, as well as the total contract amount, was awarded to the subcontractor?)

Date Contract and/or Award began:

Original Completion Date:

Actual Completion Date (or ongoing, if applicable):

Initial Award Amount:

Final Contract Amount:

Amount added by…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .