This modification to a federal solicitation provides revised specifications for materials required for an Albeni Falls Dam transformer installation project. The U.S. Army Corps of Engineers, Seattle District, requires crushed rock surfacing and quench rock for placement within new transformer containment areas and chilling sumps. The quench rock must have a minimum bulk density of 80 pounds per cubic foot, moisture absorption rate of less than 3%, and conform to ASTM gradation and fracture requirements. Installation procedures outline preparing the substrate, carefully spreading the aggregates to avoid damaging existing components, and placing one even layer of quench rock at least 12 inches thick supported on a frame and grating at the correct elevation.

This modification also retains the previous proposal submission deadline of July 7, 2021 at 10:00 AM local time. The revised specifications replace sections in their entirety and identify changes through strikeouts, underlining, or margins. Bidders must acknowledge receipt of this amendment by number and date in their proposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

W912DW21R0021R0004

AFD Main Unit Transformer Installation, Oldtow n, Idaho

(see continuation page)

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Jun-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW21R0021

X 9B. DATED (SEE ITEM 11)

17-May-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Jun-2021

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DW21R0021

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

The following items are applicable to this modification:

R0004

1. This amendment four (0004) provides for the following:

a. Revision of spec sections:

32 11 23.01 26

2. The proposal submittal time and date of July 7, 2021 at 10:00:00 a.m. LOCAL TIME remains the same.

3. The attached revised sections are to be replaced in their entirety. Specifications changes are generally identified, for convenience, either by strikeout for deletions, and double underlining of text for additions or a single dark line in the margin. All portions of the revised sections shall apply whether or not changes have been indicated.

4. NOTICE TO OFFERORS: Offerors must acknowledge receipt of this amendment by number and date on offer.

Encl:

32 11 23.01 26 (revised)

ALF XFMR Install Final

SECTION 32 11 23.01 26

CRUSHED ROCK SURFACING AND QUENCH ROCK

01/07/19

PART 1 GENERAL

1.1 General

This section covers quench rock to be placed within Albeni Falls transformer containment s.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C127 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate

ASTM D448 (2012) Sizes of Aggregate for Road and Bridge Construction

ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Quench Rock

SD-04 Samples

Sample of the Aggregate for Quench Rock; G

SD-06 Test Results

Aggregate Sample Fracture Test Results ; G

SECTION 32 11 23.01 26 Page 1

PART 2 PRODUCTS

2.1 QUENCH ROCK

Quench rock for use within containment areas and chilling sumps shall be washed rock with a minimum bulk density of 80 pounds per cubic foot and moisture absorption rate equal to or less than 3% as determined by ASTM C127. Submit to project a Sample of the Aggregate for Quench Rock .

2.1.1 Aggregate Gradation

Gradation shall conform to ASTM D448 Size 2.

US Standard Sieve Sizes Percentage Passing Square Openings (inch) (by Weight)

3 100 2-1/2 90-100 2 35-70 1-1/2 0-15 3/4 0-5

2.1.2 Fracture of Gravel

On 95% of all particles retained on each sieve 1/4 inch and above shall have at least one mechanically fractured face. In addition, 70% of same particles shall have at least three mechanically fractured faces. Test per ASTM D75/D75M. Submit Aggregate Sample Fracture Test Results for approval.

PART 3 EXECUTION

3.1 PREPARATION OF SUBSTRATE

Correct irregularities in substrate gradient and elevation by scarifying, reshaping, and re-compacting. Aggregate shall not be placed on soft, muddy, or frozen surfaces. If this is unavoidable, bring it to the attention of the GQAR for remediation. Do not place surfacing materials until the GQAR has inspected and approved the subgrade gradients and elevations.

3.2 AGGREGATE PLACEMENT

The Contractor shall take great care to ensure placement and grading of the aggregate does not result in damage to the existing components.

Equipment used to spread or haul aggregate for placement shall meet the following requirements:

a. The equipment shall not have a curb weight in excess of 6,000-lbs;

b. The equipment shall have tracks to reduce ground pressures;

c. The equipment shall not create ground pressures in excess of 4-psi;

d. Spread aggregate over prepared substrate.

e. Level and contour surfaces to elevations and gradients indicated.

SECTION 32 11 23.01 26 Page 2

f. Use small mechanical tamping equipment in areas inaccessible to large compaction equipment.

3.3 PLACEMENT OF QUENCH ROCK

Quench rock must be placed in one even layer, 12 inches minimum thickness. Support quench rock using a frame and steel grating so that the top of the rock layer is even with the transformer foundation and top of containment wall, creating an even working surface. Wash down quench rock prior to placing in containment in order to ensure fines are removed to the extent practicable in order to avoid impact to function of chemical oil stop valves.

-- End of Section --

SECTION 32 11 23.01 26 Page 3

32 11 23.01 26.pdf
32 11 23.01 26 - CRUSHED ROCK SURFACING AND QUENCH ROCK
PART 1 GENERAL
1.1 General
1.2 REFERENCES
1.3 SUBMITTALS
PART 2 PRODUCTS
2.1 QUENCH ROCK
2.1.1 Aggregate Gradation
2.1.2 Fracture of Gravel
PART 3 EXECUTION
3.1 PREPARATION OF SUBSTRATE
3.2 AGGREGATE PLACEMENT
3.3 PLACEMENT OF QUENCH ROCK