RTA Submission - DA APP A - Structural Design Calculations Mooring Pier 24-06-28.pdf
PDF 513 KB Posted
- Attached to
- Troy Lock (AFO) Mooring Pier
- Solicitation number
- W912DS25B0001
About this file
This is a detailed structural design calculation worksheet for the Troy Lock Dam Mooring Pier fender support framing design. The calculations analyze various components including fender support members, posts, struts, brackets, and connections to ensure they can withstand expected loads and forces.
The worksheet provides comprehensive engineering calculations for material properties, structural component properties, load calculations, and resistance factors. Key design elements include W12X58 fender support beams, C9X20 channel struts, and various connection details including welded and bolted connections. The calculations account for multiple load types including dead loads, live loads, impact loads from debris/ice/barges, wind loads, earthquake loads, and thermal expansion. Critical design considerations include maximum moments, shears, and axial forces under various load combinations. The document includes detailed analysis of bracket designs, weld specifications, and bolt requirements. All calculations follow AISC, AASHTO, and other relevant engineering standards with appropriate safety factors applied.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN WORK SHEET
PROJECT
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
Purpose
Design Fender Support System
Check Existing-to-Remain Components of Mooring Pier
General Assumptions
Assume Existing Connection Locations will be used for the proposed fender system.
Assume that the connection between the support members and the fender system will be determined by the manufacturer.
Assume breaking waves act as if the fenders are a solid wall with no water behind
Assume that atmospheric ice conditions will only control when concurrent with a Ice Impact or Thermal Expansion Load Condition.
Assume that the only dynamic loads that occur simultaneously with each other are Wave and Hydrodynamic Loads.
Assume that Debris Impact or Barge Impact doesn't occur with Thermally-Expanding Ice Loads
Assume that Impact and Wave loads do not occur in Usual or Unusual Load Combinations.
Assume that the Barge Impact is applied only to two Fender Supports
Assume that the maximum positive and the negative moments occur at the same locations for all load cases.
References
Name Edition Year Abbreviation
1968 Troy Lock & Dam Mooring Pier Contract Documents 1968 1968 TLDMP
AASHTO LRFD Bridge Design Specifications (2020, 9th Ed.) 9 2020 AASHTO LRFD
AASHTO LRFD Specifications for Structural Supports for Highway Signs, Luminaires and Traffic Signals 2015 AASHTO Signs
AISC Steel Construction Manual (4th Ed.) 4 AISC 4
AISC Steel Construction Manual (15th Ed.) 15 2017 AISC 15
AISC Design Guide 9: Torsional Analysis of Structural Steel Members 2003 AISC DG9
International Building Code 2021 IBC
International Existing Building Code 2021 IEBC
USS Hot-Rolled Steel, Shapes and Plates 1963 USS
ASCE/SEI 7-16: Minimum Design Loads and Associated Criteria for Buildings and Other Structures 2016 ASCE 7-16
USACE UFC 3-301-01: Structural Engineering Change 1 2023 UFC 3-301-01
EM 1110-2-2107: Design of Hydraulic Steel Structures * 2022 EM 1110-2-2107
EM 1110-2-2502: Flood Walls and Other Hydraulic Retaining Walls 2022 EM 1110-2-2502
EM 1110-2-2607: Planning and Design of Navigational Dams 1995 EM 1110-2-2607
EM 1110-2-3402: Barge Impact Forces for Hydraulic Structures 2022 EM 1110-2-3402
* The Troy Lock & Dam Mooring Pier is not considered a "Hydraulic Steel Structure" since its primary purpose is not to retain water. However, EM 1110-2-2107 is still used as a reference for determining design loads and details since the Mooring Pier is a steel structure submerged in water.
1. General Input
1.1 Unit Weights
γC 0.150 kcf Unit Weight of Concrete AASHTO Bridge C3.5.1 γS 0.490 kcf Unit Weight of Steel AASHTO Bridge Table 3.5.1-1 γW 0.062 kcf Unit Weight of Water ASCE 7-16 5.4.4.2 γE 0.120 kcf Unit Weight of Compacted Soil AASHTO Bridge Table 3.5.1-1 γI 0.056 kcf Unit Weight of Ice ASCE 7-16 10.4.1 γCF 0.063 kcf Unit Weight of Composite Fender Material USACERL TR-98/123 Table 1
1.2 Datum Conversions
ZMLW-N88 2.620 ft Conversion from Mean Low Water to NAVD88 NOAA Datums for 8531680 Sandy Hook, NJ
ZSH-N88 0.240 ft Conversion from Mean Sea Level at Sandy Hook, NJ to NAVD88 NOAA Datums for 8531680 Sandy Hook, NJ
ZNG29-N88 3.600 ft Conversion from NGVD29 to NAVD88 USGS Conversion Factors and Datums
S:\STRUCTURES\Project Files\TLD Mooring Pier\RTA\RTA_TLD_Mooring Pier Fender Design.xlsx Revision 00
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
1. General Input (cont.)
1.3 Material Properties
f'c 4.500 ksi Deck Concrete Strength
K1 1.000 Correction Factor for Aggregate Source AASHTO Bridge 5.4.2.4
Ec 4435.31 ksi = 120,000 *K1 * γc (kcf) 2.0
* f'c (ksi) 0.33
Modulus of Elasticity of Concrete AASHTO Bridge Eq. 5.4.2.4-1 fy 50.000 ksi Yield Strength of Steel fu 65.000 ksi Ultimate Strength of Steel
Es 29000 ksi Modulus of Elasticity of Steel
G 11200 ksi Shear Modulus of Steel AISC 15 E4 n 6.54 = Es / Ec Transformational Factor AASHTO Bridge Eq. 4.6.2.2.1-2
2. Structural Component Properties
2.1 Existing Post Properties
SIZE 1968 TLDMP
LP 11.000 ft Proposed Span Length of Pile (between Channel Struts)
LP-T 14.000 ft Total Length of Pile (from Top to Bottom Fender Support) 1968 TLDMP
WP 53.000 plf Self Weight of Channel AISC 4 Pg. 52 dP 11.780 in Depth of Channel tP-w 0.436 in Web Thickness AISC 4 Pg. 52 bP-f 12.046 in Flange Width tP-f 0.436 in Flange Thickness AISC 4 Pg. 52
AP 15.580 in
Cross Sectional Area AISC 4 Pg. 52
IP-x 394.800 in
Major Axis Moment of Inertia IP-y 127.300 in
Minor Axis Moment of Inertia AISC 4 Pg. 52
SP-x 67.000 in
Major Axis Section Modulus SP-y 21.200 in
Minor Axis Section Modulus AISC 4 Pg. 52 rP-x 5.030 in Major Axis Radius of Gyration rP-y 2.860 in Minor Axis Radius of Gyration AISC 4 Pg. 52
2.2 Proposed Strut Properties
SIZE
LCS 2.500 ft Length of Strut Match Existing θCS 27.000 ° Angle between CL of Strut and CL of Post Match Existing
WP 20.000 plf Self Weight of Channel AISC 15 Table 1-5 dP 9.000 in Depth of Channel tP-w 0.448 in Web Thickness AISC 15 Table 1-5 bP-f 2.650 in Flange Width tP-f 0.413 in Flange Thickness AISC 15 Table 1-5
APF 5.870 in
Cross Sectional Area AISC 15 Table 1-5
IPF-x 60.900 in
Major Axis Moment of Inertia IPF-y 2.410 in
Minor Axis Moment of Inertia AISC 15 Table 1-5
SPF-x 13.500 in
Major Axis Section Modulus SPF-y 1.170 in
Minor Axis Section Modulus AISC 15 Table 1-5 rPF-x 3.220 in Major Axis Radius of Gyration rPF-y 0.640 in Minor Axis Radius of Gyration AISC 15 Table 1-5
ZPF-x 16.900 in
Major Axis Plastic Modulus ZPF-y 2.460 in
Minor Axis Plastic Modulus AISC 15 Table 1-5
12BP53
C9X20
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
2. Structural Component Properties (cont.)
2.3 Proposed Fender Support Properties
The proposed fender support will be a continuous beam between Hydraulic Cells with a intermediate support at the steel posts
SIZE
LPF 12.575 ft Maintain Span Length of Beam Between Hydraulic Cell and Post 1968 TLDMP
LPF-T 25.150 ft Total Length of a Single Piece of Beam
Lb-PF 25.150 ft Maximum Unbraced Length (Both Flanges)
WPF 58.000 plf Self Weight of Beam AISC 15 Table 1-1 dPF 12.200 in Depth of Beam tPF-w 0.360 in Web Thickness AISC 15 Table 1-1 bPF-f 10.000 in Flange Width tPF-f 0.640 in Flange Thickness AISC 15 Table 1-1
APF 17.000 in
Cross Sectional Area kdes 1.240 in Outside of Flange to Inside of Fillet AISC 15 Table 1-1
IPF-x 475.000 in
Major Axis Moment of Inertia IPF-y 107.000 in
Minor Axis Moment of Inertia AISC 15 Table 1-1
SPF-x 78.000 in
Major Axis Section Modulus SPF-y 21.400 in
Minor Axis Section Modulus AISC 15 Table 1-1 rPF-x 5.280 in Major Axis Radius of Gyration rPF-y 2.510 in Minor Axis Radius of Gyration AISC 15 Table 1-1
ZPF-x 86.400 in
Major Axis Plastic Modulus ZPF-y 32.500 in
Minor Axis Plastic Modulus AISC 15 Table 1-1
CPF-w 3570.000 in
Warping Constant JPF 2.100 in
Torsional Constant AISC 15 Table 1-1
WPF-no 28.900 in
SPF-w1 46.300 in
AISC DG9 Appendix A
2.5 Proposed Fender System
NFU 6 Number of Fender Supports
SFU 2.000 ft Maximum Vertical Spacing of Fender Support Beams
LFU 12.575 ft Length of one (1) Fender Unit 1968 TLDMP
3. Hydraulic Properties
3.1 Elevations
ZFB 1.000 Design Freeboard for Pier Extension EM 1110-2-2607 Section 5-6.d. & ASCE 7-16 5.4.2
ELLW -2.100 Low Water Elevation (January 1965) Mean Low Water 1968 TLDMP
ELHW 25.800 High Water Elevation (Peak at 12/31/1948 or 01/01/1949) Mean High Water 1968 TLDMP
ELBF 28.000 Base Flood Elevation NGVD 29 FEMA Firm Panel 360677002B
ELG -17.900 Ground Elevation (Riverbed) (between Cells 5 & 6) Mean Low Water 1968 TLDMP
ELT 16.000 Top of Mooring Pier Elevation Mean Low Water 1968 TLDMP
ELLW 0.520 Low Water Elevation (January 1965) Converted to NAVD88 Datum with ZMLW-N88
ELHW 28.420 High Water Elevation (Peak at 12/31/1948 or 01/01/1949) Converted to NAVD88 Datum with ZMLW-N88
ELBF 31.600 Base Flood Elevation Converted to NAVD88 Datum with ZNG29-N88
ELG -15.280 Ground Elevation (Riverbed) (between Cells 5 & 6) Converted to NAVD88 Datum with ZMLW-N88
ELT 18.620 Top of Mooring Pier Elevation Converted to NAVD88 Datum with ZMLW-N88
ELDF 32.600 = ELBF + ZFB Design Flood Elevation
3.2 Velocity of the stream
g 32.200 ft / s
Acceleration due to gravity
VW-max-f 3.470 ft / s Maximum velocity of water recorded USGS Water Data at Port of Albany, NY - 01359165
VW-min 30.47 ft / s = ds / 1 sec Approximate Lower Bound of Water Velocity ASCE 7-16 Eq. C5.4-1
VW-max 31.32 ft / s = (g * ds) 0.5
Approximate Higher Bound of Water Velocity ASCE 7-16 Eq. C5.4-2
W12X58
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations
4.1 General Parameters
CRISK I Risk Category Little to no risk to human life at failure UFC 3-301-01 Table 2-2
SRC D Surface Roughness Category, Water Surfaces ASCE 7-16 26.7.2
Exposure D Exposure Category, Water Surfaces ASCE 7-16 26.7.3
Exp. Roof Exposure of Roof ASCE 7-16 Table 7.3-1
IE 1.00 Importance Factor for Earthquake Loads UFC 3-301-01 Table 2-2
IS 0.80 Importance Factor for Snow Loads UFC 3-301-01 Table 2-2
Ii 0.80 Importance Factor for Ice Loads UFC 3-301-01 Table 2-2
ITSU N/A Importance Factor for Tsunami Loads UFC 3-301-01 Table 2-2
4.2 Vertical Loads
4.2.1 Dead Load of Fender Support System
Because the Fender product is to be chosen by the contractor, the following weight and center of gravity is assumed for the fender product ePANEL 2.000 ft Assumed Vertical Extension of Fender Panel Past Centerline of Support Beams
HPANEL 14.00 ft = (NFU - 1) * SFU + 2 * ePANEL Total Height of Assumed Fender Envelope
APANEL 2.33 ft
= tPANEL * HPANEL Cross-Sectional Area of Panel tHF 4.00 in = (2 * tPANEL) For Horizontal Members Assume a sides equal to 2 X the Panel Thickness
AHF 0.11 ft
= (tHF)
Assume a Rectangular Cross Section eHF 1.000 ft Assumed Distance from Outside of Fender Support Beam to Center of Gravity of Fender Product
WHF 0.200 klf Weight of Assumed Fender Product
WCF 0.02 klf = γCF * APANEL / NFU Weight of Assumed Composite Panel per Support Beam
WPF 0.06 klf Recall Self Weight of Fender Support Beam wDL 0.28 klf = 1.10 * (WHF + WPF) Total Assumed Dead Load per beam Assume 110% for contingency
Mv D-I -5.61 k-ft = -0.125 wDL * LPF
Maximum Moment due to Dead Loads at Center Support
Mv D-M 3.14 k-ft = 0.07 * wDL * LPF
Maximum Moment due to Dead Loads along Span
Vv D_E 1.34 kips = (3/8) * wDL * LPF Maximum Shear at End due to Dead Loads
Rv D_E 1.34 kips = (3/8) * wDL * LPF Maximum Reaction at End due to Dead Loads
Vv D_I 2.23 kips = (5/8) * wDL * LPF Maximum Shear at Intermediate Support due to Dead Loads
Rv D_I 4.46 kips = (10/8) * wDL * LPF Maximum Reaction at Intermediate Support due to Dead Loads
Full
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.2 Vertical Loads (cont.)
4.2.2 Dead Load of Grating, Channel, and Post
pGR 25.000 psf Assumed Weight of 1" Steel Grating
WCh 20.000 plf Weight of C9X20
WP 53.000 plf Weight of Existing 12 BP 53
Figure B.4: Tributary Width and Area of Channel Strut (in blue), Channel Cantilever (in pink) and Post (in Green)
Grating will be directly supported by the channels, which will transfer load to the post and the cell wall.
TLD 1968 Reconstruction Drawings, Drawing 5
WT-S 4.000 ft Average Tributary Width of Strut
AT-P 8.830 ft
Tributary Area of Post wv-D-Ch 0.12 klf = WCh + pGR * WT-S Dead Load Applied to Channel
Pv-D-P 0.22 kips = pGR * AT-P Maximum Dead Load Applied to Post
Mv D-Ch 0.06 k-ft = wv-D-Ch * LCS / 12 Maximum Moment due to Dead Load on Channel (with Welded Fixed Connections)
Vv D-Ch 0.15 kips = wv-D-Ch * LCS / 2 Maximum Shear due to Dead Load on Channel
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.2 Vertical Loads (cont.)
4.2.2 Gravity Loads
4.2.2.1 Mud / Sediment Accumulating on Section
Assume Mud Collects in Space between Beam Flanges hWELL 4.82 in = (bPF-f - tPF-w) / 2 Height of Empty Space above Beam Web bWELL 10.92 in = dPF - 2 * tPF-f Width of Empty Space above Beam Web wv G-m 0.05 klf = 1.10 * γE * (hWELL * bWELL) Assumed Weight of Mud Collected in Beam (Assume 110%)
4.2.2.2 Atmospheric Ice forming around Section
Assume that Ice forms in a certain thickness, tICE around every component and that an ice collar forms around the fender support beams. The size of the collar is assumed to be equal to the empty space between the fender support beams and the fender system components.
Because the Fender product is to be chosen by the contractor, a width of possible fender locations is assumed in this calculation.
bHF 2.00 ft = 2 * eHF Assumed Width of Fender Envelope tICE 1.000 in Nominal Ice Thickness ASCE 7-16 Fig. 10.4-2
Tc 5.000 °F Temperatures Concurrent with Ice Thicknesses from Freezing Rain ASCE 7-16 Fig. 10.6-1 h 18.10 ft = ELT - ELLW Conservatively Consider Height of Structure over Low Water Elevation fz 1.00 = (z / 33) 0.1
Height Factor, Maximum 1.4, Minimum 1.0 ASCE 7-16 Eq. 10.4-4 td 0.80 in = Ii * tICE * fz * Kzt 0.35
Design Ice Thickness for Freezing Rain ASCE 7-22 Eq. 10.4-5
Dc-HF 33.94 in = √(bHF
+ SFU
) Characteristic Dimension for Panel (Rectangular Envelope) ASCE 7-16 Fig. 10.4-1
Dc-BEAM 15.77 in = √(bPF-f + dPF
) Characteristic Dimension for Beam (W-Shape Cross Section) ASCE 7-16 Fig. 10.4-1
Ai-PANEL 7.12 in
Cross Sectional Area of Ice on Panel ASCE 7-16 Fig. 10.4-1
Ai-HF 7.12 in
Assumed Cross Sectional Area of Ice on Fender Envelope ASCE 7-16 Fig. 10.4-1
Ai-BEAM 3.32 in
Cross Sectional Area of Ice on Beam ASCE 7-16 Fig. 10.4-1
Ai-ES 585.60 in
= SFU * (2 * dPF) Cross Sectional Area of Ice Collar Between Fender Support Beams, Assume collar width is twice the depth of the beam wv G-i-PANEL 0.000 klf = γI * Ai-PANEL / NFU Weight of Atmospheric Ice on Assumed Panel wv G-i-HF 0.003 klf = γI * Ai-HF Weight of Atmospheric Ice on Assumed Horizontal Fender wv G-i-BEAM 0.001 klf = γI * Ai-BEAM Weight of Atmospheric Ice on Fender Support Beam wv G-i-COLL 0.228 klf = γI * Ai-ES Weight of Ice Collar Between Fender Support Beams wv G-i 0.23 klf = wv G-i-PANEL + wv G-i-HF + wv G-i-BEAM + wv G-i-ES Weight of Ice on each Beam
4.2.2.3 Snow Loads
pg 40.000 psf Ground Snow Load UFC 3-301-01 Tool
Ce 0.800 Exposure Factor ASCE 7-16 Table 7.3-1
Ct 1.200 Thermal Factor ASCE 7-16 Table 7.3-2 pf 21.50 psf = 0.7 * Ce * Ct * Is * pg ASCE 7-16 Eq. 7.3-1 bf 24.40 in = 2 * dPF Assume Snow resting on Surface Width Equal to twice the Fender Support Beam Depth wv G-s 0.04 klf = bf-SNOW * pf Weight of Snow on each Beam
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.2 Vertical Loads (cont.)
4.2.2.4 Total Gravity Loads
wv G-wI 0.28 klf = wv G-m + wv G-i Total Weight without snow & with Atmospheric Ice
Mv GwI-I -5.54 k-ft = -0.125 * wv-GwI * LPF
Maximum Moment due to Gravity Loads with Ice at Center Support
Mv GwI-M 3.10 k-ft = 0.07 * wv-GwI * LPF
Maximum Moment due to Gravity Loads with Ice along Span
Vv GwI_E 1.32 kips = (3/8) * wv-GwI * LPF Maximum Shear at End due to Gravity Loads with Ice
Rv GwI_E 1.32 kips = (3/8) * wv-GwI * LPF Maximum Reaction at End due to Gravity Loads with Ice
Vv GwI_I 2.20 kips = (5/8) * wv-GwI * LPF Maximum Shear at Intermediate Support due to Gravity Loads with Ice
Rv GwI_I 4.41 kips = (10/8) * wv-GwI * LPF Maximum Reaction at Intermediate Support due to Gravity Loads with Ice wv G-nI 0.09 klf = wv G-m + wv G-s Total Weight with snow & without Atmospheric Ice
Mv GnI-I -1.82 k-ft = -0.125 * wv-GnI * LPF
Maximum Moment due to Gravity Loads without Ice at Center Support
Mv GnI-M 1.02 k-ft = 0.07 * wv-GnI * LPF
Maximum Moment due to Gravity Loads without Ice along Span
Vv GnI_E 0.43 kips = (3/8) * wv-GnI * LPF Maximum Shear at End due to Gravity Loads without Ice
Rv GnI_E 0.43 kips = (3/8) * wv-GnI * LPF Maximum Reaction at End due to Gravity Loads without Ice
Vv GnI_I 0.72 kips = (5/8) * wv-GnI * LPF Maximum Shear at Intermediate Support due to Gravity Loads without Ice
Rv GnI_I 1.45 kips = (10/8) * wv-GnI * LPF Maximum Reaction at Intermediate Support due to Gravity Loads without Ice
4.2.3 Weight of Water (Hydrostatic Buoyancy)
Ab-PF 69.63 in
= APF + hWELL * bWELL Area of Beam + Air Trapped in Void below Web
Ab-T 4.00 ft
= bHF * SFU Total Area of Displaced Water per support beam wv Hs 0.00 klf = γW * Ab-T Total Buoyancy Force per Beam
Mv Hs-I 0.00 k-ft = 0.125 * wv-Hs * LPF
Maximum Moment due to Buoyancy Loads at Center Support
Mv Hs-M 0.00 k-ft = -0.07 * wv-Hs * LPF
Maximum Moment due to Buoyancy Loads along Span
Vv Hs_E 0.00 kips = -(3/8) * wv-Hs * LPF Maximum Shear at End due to Buoyancy Loads
Rv Hs_E 0.00 kips = -(3/8) * wv-Hs * LPF Maximum Reaction at End due to Buoyancy Loads
Vv Hs_I 0.00 kips = -(5/8) * wv-Hs * LPF Maximum Shear at Intermediate Support due to Buoyancy Loads
Rv Hs_I 0.00 kips = -(10/8) * wv-Hs * LPF Maximum Reaction at Intermediate Support due to Buoyancy Loads
Because the hydrostatic forces are significantly lower than that of the Dead + Gravity Loads, these loads will be conservatively ignored.
4.2.4 Vertical Live Loads on Top of Hydraulic Cell
pLL 100.000 lbs/ft
Live Load EM 1110-2-2107 4.2.11
There is no live load expected to be on top of the fenders or on their support members. However, there is expected live load on the grating at the top of the Post and its connected channels. Therefore, the live load as shown will be applied to the post and channel strut checks.
wv-L-Ch 0.40 klf = pLL * WT-S Live Load Applied to Channel
Pv-L-P 0.88 kips = pLL * AT-P Maximum Live Load Applied to Post
Mv L-Ch 0.21 k-ft = wv-L-Ch * LCS / 12 Maximum Moment due to Live Load on Channel (with Welded Fixed Connections)
Vv L-Ch 0.50 kips = wv-L-Ch * LCS / 2 Maximum Moment due to Buoyancy Loads
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads
4.3.1 Flood Load
4.3.1.1 Hydrostatic Lateral Load
Because the fender supports do not retain water, the water level will be the same on either side of the fenders. Therefore, there is no net Hydrostatic
Lateral Load wl Hs 0.000 klf
Ml Hs-I 0.00 k-ft = -0.125 * wl-Hs * LPF
Maximum Moment due to Lateral Hydrostatic Loads at Center Support
Ml Hs-M 0.00 k-ft = 0.07 * wl-Hs * LPF
Maximum Moment due to Lateral Hydrostatic Loads along Span
Vl Hs_E 0.00 kips = (3/8) * wl-Hs * LPF Maximum Shear at End due to Lateral Hydrostatic Loads
Rl Hs_E 0.00 kips = (3/8) * wl-Hs * LPF Maximum Reaction at End due to Lateral Hydrostatic Loads
Vl Hs_I 0.00 kips = (5/8) * wl-Hs * LPF Maximum Shear at Intermediate Support due to Lateral Hydrostatic Loads
Rl Hs_I 0.00 kips = (10/8) * wl-Hs * LPF Maximum Reaction at Intermediate Support due to Lateral Hydrostatic Loads
4.3.1.2 Hydrodynamic Lateral Load
Hd 1.250 ft Hydrodynamic Temporal Head EM 1110-2-2107 E.2.8 wl Hd 0.16 klf = (γw * Hd) * SFU Hydrodynamic Temporal Head Assume 110% for contingency
Ml Hd-I -3.08 k-ft = -0.125 * wl-Hd * LPF
Maximum Moment due to Lateral Hydrodynamic Loads at Center Support
Ml Hd-M 1.73 k-ft = 0.07 * wl-Hd * LPF
Maximum Moment due to Lateral Hydrostatic Loads along Span
Vl Hd_E 0.74 kips = (3/8) * wl-Hd * LPF Maximum Shear at End due to Lateral Hydrodynamic Loads
Rl Hd_E 0.74 kips = (3/8) * wl-Hd * LPF Maximum Reaction at End due to Lateral Hydrodynamic Loads
Vl Hd_I 1.23 kips = (5/8) * wl-Hd * LPF Maximum Shear at Intermediate Support due to Lateral Hydrodynamic Loads
Rl Hd_I 2.45 kips = (10/8) * wl-Hd * LPF Maximum Reaction at Intermediate Support due to Lateral Hydrodynamic Loads
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads (cont.)
4.3.1 Flood Load (cont.)
4.3.1.3 Wave Load
Without a detailed hydrodynamic study, ASCE 7-16 was used for wave loads ds 30.47 ft = 0.65 * (ELBF - ELG) Local Stillwater Depth ASCE 7-16 Eq. 5.4-3
Hb 23.77 ft = 0.78 * ds Breaking Wave Height ASCE 7-16 Eq. 5.4-2
Cp 1.60 Dynamic pressure coefficient ASCE 7-16 Table 5.4-1
Pmax 5.32 lbs/ft
= Cp * γW * ds + 1.2 * γW * ds Max Dynamic + Static Wave Pressures ASCE 7-16 Eq. 5.4-5
Ft-V 241.03 lbs/ft = 1.1 * Cp * γW * ds + 2.4 * γW * ds
Breaking Wave Force against wall ASCE 7-16 Eq. 5.4-6
From ASCE 7-16 dEP 11.780 in Depth of Post tEP-w 0.436 in Web Thickness AISC 4 bEP-f 12.046 in Flange Width tEP-f 0.436 in Flange Thickness AISC 4
D 16.86 in = 1.4 * bEP-f ASCE 7-16 Eq. 5.4.4
CD 2.250 Coefficient of drag for breaking waves (Used square piles or columns) ASCE 7-16 Eq. 5.4.4
FD 55.73 lbs/ft = 0.5 * γW * CD * D * Hb
ASCE 7-16 Eq. 5.4.4
Ft 241.03 lbs/ft = Max of Ft-V & FD ASCE 7-16 Eq. 5.4.9 α 45.000 degrees Assumed Angle of Wave Approach to Mooring Pier wl Hw 0.12 lbs/ft = Ft * sin α ASCE 7-16 Eq. 5.4.9
Ml Hw-I -2.38 k-ft = -0.125 * wl-Hw * LPF
Maximum Moment due to Lateral Wave Loads at Center Support
Ml Hw-M 1.33 k-ft = 0.07 * wl-Hw * LPF
Maximum Moment due to Lateral Wave Loads along Span
Vl Hw_E 0.57 kips = (3/8) * wl-Hw * LPF Maximum Shear at End due to Lateral Wave Loads
Rl Hw_E 0.57 kips = (3/8) * wl-Hw * LPF Maximum Reaction at End due to Lateral Wave Loads
Vl Hw_I 0.95 kips = (5/8) * wl-Hw * LPF Maximum Shear at Intermediate Support due to Lateral Wave Loads
Rl Hw_I 1.89 kips = (10/8) * wl-Hw * LPF Maximum Reaction at Intermediate Support due to Lateral Wave Loads
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads (cont.)
4.3.2 Impact Load
Impact equations due to Debris, Ice Floe, and Barge assume that the impact forces are directed perpendicular to the structure. However, the mooring pier is oriented parallel to the Hudson River flow. EM 1110-2-3402 provides guidance on the design of lock walls which similarily aren't perpendicular to the flow of water. The EM provides angles of approach to break the impact force into force components parallel and perpendicular to the structure.
While these angles are preliminary estimates for Barge Impact Forces, it is assumed that they also apply to debris and ice floe. This is considered a a conservative assumption since barges have more control over their bearing and their speed.
θBI_US 10.0 ° Max Angle Between Fender and Barge Trajectory in Usual Conditions EM 1110-2-3402 Table D.3 θBI_UN 20.0 ° Max Angle Between Fender and Barge Trajectory in Unusual Conditions EM 1110-2-3402 Table D.3 θBI_EX 25.0 ° Max Angle Between Fender and Barge Trajectory in Extreme Conditions EM 1110-2-3402 Table D.3
Because all Impact Forces are applied in extreme principal loading in EM 1110-2-2107 Table 4.1, Only the Extreme Angle will be used for these calculations.
For Concentrated Impact Forces, the controlling location of the force differs depending on whether you are calculating the maximum moment or shear.
To determine these locations, the derivative of the shear and maximum moment equations were calculated to find the max and min based on, a, the distance from the end support to the concentrated load. See the next page for the derivative equations.
AISC 14 Table 3-23
Because b = L PF - a, and a has to be between 0 ft and L PF ...
Mmax = P * aM * (LPF - aM) / (4 * LPF
) * (4 * LPF
- aM * (LPF + aM)) Rearranged Equation for Maximum Moment along Span
M1 = P * aM1 * (LPF - aM1) / (4 * LPF ) * (LPF + aM1) Rearranged Equation for Moment at Center Support
V1 = P * (LPF - aV1) / (4 * LPF
) * (4 * LPF
- aV1 * (LPF + aV1)) Rearranged Equation for Shear at Near End Support
V2 = P * aV2 / (2 * LPF
) * (2 * LPF
+ (LPF - aV2) * (LPF + aV2)) Rearranged Equation for Shear at Center Support
V3 = P * aV3 * (LPF - aV3) / (4 * LPF ) * (LPF + aV3) Rearranged Equation for Shear at Far End Support
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads (cont.)
4.3.2 Impact Load (cont.)
Find Location of Applied Load that produces the Maximum Moment along the Span
Mmax = P / (4 * LPF ) * (LPF * aM - aM
) * (4 * LPF
- LPF * aM - aM
)) Expanded Equation for Maximum Moment along Span
Mmax = P / (4 * LPF ) * (aM
- 5 * LPF
* aM
+ 4 * LPF
* aM) Expanded Equation for Maximum Moment along Span dMmax / daM = P / (4 * LPF ) * (4 * aM
- 10 * LPF
* aM + 4 * LPF
) Derivation of Equation for Maximum Moment along Span dMmax / daM = 0 → aM = - 1.75233 * LPF Find values of a where maximum moment occurs
= 0.43232 * LPF
= 1.32001 * LPF
Because the solutions, -1.75233 * L PF & 1.32001 * L PF , are outside the limits of a, the solution, 0.43232 * L PF , will be used.
aM 5.44 ft = 0.43232 * LPF Location of Load that produces the Maximum Moment along Span
Find Location of Applied Load that produces the Maximum Moment along the Span
M1 = P / (4 * LPF
) * aM * (LPF
- aM
) Expanded Equation for Moment at Center Support
M1 = P / (4 * LPF
) * (LPF
* aM - aM
) Expanded Equation for Moment at Center Support dM1 / daM1 = P / (4 * LPF
) * (LPF
- 3 * aM
) Derivation of Equation for Moment at Center Support dM1 / daM1 = 0 → aM1 = ± LPF / √3 Find values of a where maximum moment occurs
Because the solution, -L PF / √3, is outside the limits of a, the solution, L PF / √3, will be used aM1 7.26 ft = LPF / √3 Location of Load that produces the Maximum Moment at Center Support
Find Location of Applied Load that produces the Maximum Shear at Near End Support
V1 = P / (4 * LPF
) * (LPF - aV1) * (4 * LPF
- LPF * aV1 - aV1
)) Expanded Equation for Shear at Near End Support
V1 = P / (4 * LPF
) * (aM
- 5 * LPF
* aM + 4 * LPF
) Expanded Equation for Shear at Near End Support dV1 / daV1 = P / (4 * LPF ) * (3 * aM
- 5 * LPF
) Derivation of Equation for Shear at Near End Support dV1 / daV1 = 0 → aV1 = ± 5 * LPF / √3 Find values of a where maximum shear occurs
Because the calculated solutions are outside the limits of a, the location of the support itself will be a V1 aV1 0.00 ft Location of Load that produces the Maximum Shear at Near End Support
Find Location of Applied Load that produces the Maximum Shear at Center Support
V2 = P * aV2 / (2 * LPF
) * (2 * LPF
+ LPF
- aV2
) Expanded Equation for Shear at Center Support
V2 = P / (2 * LPF
) * (3 * LPF
* aV2 - aV2
) Expanded Equation for Shear at Center Support dV2 / daV2 = P / (2 * LPF
) * (3 * LPF
- 3 * aV2
) Derivation of Equation for Shear at Center Support dV2 / daV2 = 0 → aV2 = LPF Find values of a where maximum shear occurs aV2 12.58 ft = LPF Location of Load that produces the Maximum Shear at Center Support
Find Location of Applied Load that produces the Maximum Shear at Far End Support
V3 = P * aV3 * (LPF
- aV3
) / (4 * LPF
) Expanded Equation for Shear at Far End Support
V3 = P * (LPF
* aV3 - aV3
) / (4 * LPF
) Expanded Equation for Shear at Far End Support dV3 / daV3 = P * (LPF
- 3 * aV3
) / (4 * LPF
) Derivation of Equation for Shear at Far End Support dV3 / daV3 = 0 → aM1 = ± LPF / √3 Find values of a where maximum shear occurs
Because the solution, -L PF / √3, is outside the limits of a, the solution, L PF / √3, will be used aV3 7.26 ft = LPF / √3 Location of Load that produces the Maximum Shear at Far End Support
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads (cont.)
4.3.2 Impact Load (cont.)
4.3.2.1 Debris/Ice Impact Load
4.3.2.1.1 Debris Impact Load
g 32.200 ft/s
Recall Gravitational Acceleration
W 1.000 kips Debris Weight ASCE 7-16 C5.4.5
Δt 0.030 seconds Impact Duration ASCE 7-16 C5.4.5
Vb 31.32 ft/s = VW-max Maximum Velocity of Object (Assume Equivalent to Velocity of Water)
CI 0.600 Importance Coefficient ASCE 7-16 Table C5.4-1
CO 0.800 Orientation Coefficient ASCE 7-16 Eq. C5.4-3
CD 1.000 Depth Coefficient A-Zone, Stillwater Depth > 5ft ASCE 7-16 Table C5.4-2
CB 1.000 Blockage Coefficient No Screening 100 ft upstream of Mooring Pier ASCE 7-16 Table C5.4-3
K 3.12E-04 k / ft = Δ / P = 0.015 * LPF / (Es * IPF-x) Stiffness of two-span continuous fender-support beam AISC 15th Ed. Table 3-23 30 mB 0.05 k / (ft/s ) = WPF * LPF-T / g Mass of two-span continuous fender-support beam fn 0.08 seconds = √(K / mB) Natural Frequency of Two-Span Continuous fender-support beam
Δt / fn 0.36 Ratio of Impact Duration to Natural Period for Response Ratio
RMAX 1.28 Interpolated Response Ratio for Half-Sine Wave Impulsive Loads ASCE 7-16 Table C5.4-4
Fd-IM 31.41 kips = π * W * Vb * CI * CO * CD * CB * RMAX / (2 * g * Δt) Debris Impact Load ASCE 7-16 Eq. C5.4-3
Fd-IM-EX 13.28 kips = Fd-IM * sin (θBI_EX) Debris Impact Load Perpendicular to Structure with impact force orientation
Fd-IMA-EX 28.47 kips = Fd-IM * cos (θBI_EX) Debris Impact Load Parallel to Structure with impact force orientation
Mmax 34.63 k-ft Maximum Moment at Point of Load due to Fd_IM See Figure for M max equation with F d_IM applied at a M
M1 -16.06 k-ft Maximum Moment at Center Support due to Fd_IM See Figure for M 1 equation with F d_IM applied at a M1
V1 13.28 kips Maximum Shear at near end support due to Fd_IM See Figure for V 1 equation with F d_IM applied at a V1
V2 -13.28 kips Maximum Shear at intermediate support due to Fd_IM See Figure for V 2 equation with F d_IM applied at a V2
V3 1.28 kips Maximum Shear at far end support due to Fd_IM See Figure for V 3 equation with F d_IM applied at a V3
Md-IM-I -16.06 k-ft See M1 at aM Maximum Moment due to Debris Impact Loads at Center Support
Md-IM-M 34.63 k-ft See Mmax at aM Maximum Moment due to Debris Impact Loads along Span
Vd-IM_E 13.28 kips Max of V1 at aV1 or V3 at aV3 Maximum Shear at End due to Debris Impact Loads
Rd-IM_E 13.28 kips Max of V1 at aV1 or V3 at aV3 Maximum Reaction at End due to Debris Impact Loads
Vd-IM_I -13.28 kips = V2 Maximum Shear at Intermediate Support due to Debris Impact Loads
Rd-IM_I 12.00 kips = -(V2 + V3) Maximum Reaction at Intermediate Support due to Debris Impact Loads
Pd-IM 28.47 kips = FBIA_EX Maximum Longitudinal Force Applied by Debris Impact Loads
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads (cont.)
4.3.2 Impact Load (cont.)
4.3.2.1 Debris/Ice Impact Load
4.3.2.1.2 Ice Impact Load
wl-IM-p 0.500 klf Ice Impact Load EM 1110-2-2502 6.12.3 wl-IM 0.21 klf = wI-IM-p * sin (θBI_EX) Ice Impact Load Perpendicular to Structure with impact force orientation wl-IMA 0.45 klf = wI-IM-p * cos (θBI_EX) Ice Impact Load Parallel to Structure with impact force orientation
Ml IM-I -4.18 k-ft = -0.125 * wl-IM * LPF
Maximum Moment due to Ice Impact Loads at Center Support
Ml IM-M 2.34 k-ft = 0.07 * wl-IM * LPF
Maximum Moment due to Ice Impact Loads along Span
Vl IM_E 1.00 kips = (3/8) * wl-IM * LPF Maximum Shear at End due to Ice Impact Loads
Rl IM_E 1.00 kips = (3/8) * wl-IM * LPF Maximum Reaction at End due to Ice Impact Loads
Vl IM_I 1.66 kips = (5/8) * wl-IM * LPF Maximum Shear at Intermediate Support due to Ice Impact Loads
Rl IM_I 3.32 kips = (10/8) * wl-IM * LPF Maximum Reaction at Intermediate Support due to Ice Impact Loads
PI-IM 11.40 kips = wl-IMA * LPF-T Maximum Longitudinal Force Applied by Ice Impact Loads
4.3.2.2 Barge Impact Load
In the 2016 Troy Lock and Dam Miter Gate Design Computations, it is stated that this is a much larger barge than is expected at this location.
Therefore, this design is conservative.
IBARGE 112.0 kips Maximum Unsymmetric Barge Impact Force 2016 Troy Lock & Dam Miter Gate Design
IBARGE-s 179.2 kips Maximum Symmetric Barge Impact Force 2016 Troy Lock & Dam Miter Gate Design
Because of the size of the barge, assume that the impact load will be equally shared by three fender support beams
As per EM 1110-2-2107 Table 4.1, Only the Extreme Case Barge Impact Force is considered
FBI_EX 25.24 kips = MAX(IBARGE, IBARGE-s) * sin(θBI_EX) / 3 Barge Impact Force in Extreme Conditions Perpendicular to Mooring Pier
FBIA_EX 54.14 kips = MAX(IBARGE, IBARGE-s) * cos(θBI_EX) / 3 Barge Impact Force in Extreme Conditions Parallel to Mooring Pier
Mmax 65.85 k-ft Maximum Moment at Point of Load due to FBI_EX See Figure for M max equation with F BI_EX applied at a M
M1 -30.55 k-ft Maximum Moment at Center Support due to FBI_EX See Figure for M 1 equation with F BI_EX applied at a M1
V1 25.24 kips Maximum Shear at near end support due to FBI_EX See Figure for V 1 equation with F BI_EX applied at a V1
V2 -25.24 kips Maximum Shear at intermediate support due to FBI_EX See Figure for V 2 equation with F BI_EX applied at a V2
V3 2.43 kips Maximum Shear at far end support due to FBI_EX See Figure for V 3 equation with F BI_EX applied at a V3
MBI-I -30.55 k-ft See M1 at aM Maximum Moment due to Extreme Barge Impact Loads at Center Support
MBI-M 65.85 k-ft See Mmax at aM Maximum Moment due to Extreme Barge Impact Loads along Span
VBI_E 25.24 kips Max of V1 at aV1 or V3 at aV3 Maximum Shear at End due to Extreme Barge Impact Loads
RBI_E 25.24 kips Max of V1 at aV1 or V3 at aV3 Maximum Reaction at End due to Extreme Barge Impact Loads
VBI_I -25.24 kips = V2 Maximum Shear at Intermediate Support due to Extreme Barge Impact Loads
RBI_I 22.82 kips = -(V2 + V3) Maximum Reaction at Intermediate Support due to Extreme Barge Impact Loads
PBI 54.14 kips = FBIA_EX Maximum Longitudinal Force Applied by Extreme Barge Impact Loads
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads (cont.)
4.3.3 Wind Load
4.3.3.1 Wind Load
Vz 102.000 mph Basic Wind Speed for Risk Category I UFC 3-301-01 Tool α 11.50 Terrain Exposure Constant ASCE 7-16 Table 26.11-1 zg 1935.00 ft Terrain Exposure Constant ASCE 7-16 Table 26.11-1
Kh 0.89 = 2.01 * ((Maximum of h or 15 ft) / zg) 2 / α
Velocity Pressure Exposure Coefficient ASCE 7-16 Table 26.10-1
K1 The Wind is traveling over water, therefore Topographic Effects are not considered ASCE 7-16 Fig. 26.8-1
K2 The Wind is traveling over water, therefore Topographic Effects are not considered ASCE 7-16 Fig. 26.8-1
K3 The Wind is traveling over water, therefore Topographic Effects are not considered ASCE 7-16 Fig. 26.8-1
Kzt 1.00 = (1 + K1 * K2 * K3)
Topographic Factor ASCE 7-16 Eq. 26.8-1
Kd 0.850 Wind Directionality Factor for wall / open sign ASCE 7-16 Table 26.6-1
Ke 1.000 Ground Elevation Factor (Conservative) ASCE 7-16 Table 26.9-1 qh 0.02 ksf = 0.00256 * Kh * Kzt * Kd * Ke * Vb
ASCE 7-16 Eq. 26.10-1
Cf 2.000 Wind Force Coefficient ASCE 7-16 10.5.2, 10.5.3, Fig. 29.3-1 & 29.4-2
Fender System could be an open frame or a solid wall. The most conservative factor is used amongst the two.
G 0.850 Gust-Effect Factor ASCE 7-16 26.11.1 wl w-b 0.07 klf = qh * G * Cf * SFU Wind Load on each Fender Support Beam ASCE 7-16 Eq. 29.3-1 / Eq. 29.4-1
Ml w-b-I -1.36 k-ft = -0.125 * wl-w-b * LPF
Maximum Moment due to Lateral Wind Loads at Center Support
Ml w-b-M 0.76 k-ft = 0.07 * wl-w-b * LPF
Maximum Moment due to Lateral Wind Loads along Span
Vl w-b_E 0.32 kips = (3/8) * wl-w-b * LPF Maximum Shear at End due to Lateral Wind Loads
Rl w-b_E 0.32 kips = (3/8) * wl-w-b * LPF Maximum Reaction at End due to Lateral Wind Loads
Vl w-b_I 0.54 kips = (5/8) * wl-w-b * LPF Maximum Shear at Intermediate Support due to Lateral Wind Loads
Rl w-b_I 1.08 kips = (10/8) * wl-w-b * LPF Maximum Reaction at Intermediate Support due to Lateral Wind Loads
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.3 Horizontal Loads (cont.)
4.3.3 Wind Load (cont.)
4.3.3.2 Wind Load Concurrent with Atmospheric Ice from Freezing Rain
Vc 45.000 mph Gust Speeds Concurrent with Ice Thicknesses from Freezing Rain ASCE 7-16 Fig. 10.4-2 qh-i 0.00 ksf = 0.00256 * Kh * Kzt * Kd * Ke * Vc
ASCE 7-16 Eq. 26.10-1 wl w-i 0.01 klf = qh-i * G * Cf * SFU Wind Load on each Fender Support Beam ASCE 7-16 Eq. 29.3-1 / Eq. 29.4-1
Ml w-i-I -0.26 k-ft = -0.125 * wl-w-i * LPF
Maximum Moment due to Lateral Wind Loads at Center Support
Ml w-l-M 0.15 k-ft = 0.07 * wl-w-I * LPF
Maximum Moment due to Lateral Wind Loads along Span
Vl w-i_E 0.06 kips = (3/8) * wl-w-i * LPF Maximum Shear at End due to Lateral Wind Loads
Rl w-i_E 0.06 kips = (3/8) * wl-w-i * LPF Maximum Reaction at End due to Lateral Wind Loads
Vl w-i_I 0.11 kips = (5/8) * wl-w-i * LPF Maximum Shear at Intermediate Support due to Lateral Wind Loads
Rl w-i_I 0.21 kips = (10/8) * wl-w-i * LPF Maximum Reaction at Intermediate Support due to Lateral Wind Loads
4.3.3.3 Serviceability Wind Load
Vc 75.000 mph Gust Speeds with 10 Mean Recurrence Interval (for Service Loads) ASCE 7-16 Fig. CC.2-1 qh-S 0.01 ksf = 0.00256 * Kh * Kzt * Kd * Ke * Vc
ASCE 7-16 Eq. 26.10-1 wl w-S 0.04 klf = qh-S * G * Cf * SFU Wind Load on each Fender Support Beam ASCE 7-16 Eq. 29.3-1 / Eq. 29.4-1
Ml w-S-I -0.73 k-ft = -0.125 * wl-w-S * LPF
Maximum Moment due to Lateral Wind Loads at Center Support
Ml w-S-M 0.41 k-ft = 0.07 * wl-w-S * LPF
Maximum Moment due to Lateral Wind Loads along Span
Vl w-S_E 0.18 kips = (3/8) * wl-w-S * LPF Maximum Shear at End due to Lateral Wind Loads
Rl w-S_E 0.18 kips = (3/8) * wl-w-S * LPF Maximum Reaction at End due to Lateral Wind Loads
Vl w-S_I 0.29 kips = (5/8) * wl-w-S * LPF Maximum Shear at Intermediate Support due to Lateral Wind Loads
Rl w-S_I 0.58 kips = (10/8) * wl-w-S * LPF Maximum Reaction at Intermediate Support due to Lateral Wind Loads
4.3.4 Thermally Expanding Ice
wl-ICE 5.0 klf Ice Impact Load Thermally Expanding Ice EM 1110-2-2107 4.2.7
Ml ICE 98.83 k-ft = 0.125 * wl-ICE * LPF
Maximum Moment due to Thermally Expanding Ice Loads at Center Support
Ml ICE-M -55.35 k-ft = -0.07 * wl-ICE * LPF
Maximum Moment due to Thermally Expanding Ice Loads along Span
Vl ICE_E -23.58 kips = -(3/8) * wl-ICE * LPF Maximum Shear at End due to Thermally Expanding Ice Loads
Rl ICE_E -23.58 kips = -(3/8) * wl-ICE * LPF Maximum Reaction at End due to Thermally Expanding Ice Loads
Vl ICE_I -39.30 kips = -(5/8) * wl-ICE * LPF Maximum Shear at Intermediate Support due to Thermally Expanding Ice Loads
Rl ICE_I -78.59 kips = -(10/8) * wl-ICE * LPF Maximum Reaction at Intermediate Support due to Thermally Expanding Ice Loads
4.4 Self-Straining Loads in Fender Support Beams
The bolted connections will be pretensioned. While they are not intended to be slip-critical, the design still assumes that any axial expansion in the steel beam is restrained.
αT-St 6.50E-06 / °F Steel Temperature Expansion Coefficient AISC 15 Page 2-39
Tlow -30.000 °F Design Low Temperature for Cold Climates AASHTO Bridge Table 3.12.2.1-1
Thigh 120.000 °F Design High Temperature for Cold Climates AASHTO Bridge Table 3.12.2.1-1
ΔT-St 0.15 in = αT-St * (Thigh - Tlow) * LPF Design Expansion in beam due to Extreme Temperature Changes
Size Slotted Hole to accommodate this expansion.
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.5 Earthquake Loading
The Earthquake Loading was determined assuming site class B ground
PGA 10.60% G Peak Ground Acceleration UFC 3-301-01 Tool
SS 19.80% G MCER Spectral Response Acceleration Parameter at 0.2 seconds for Site Class BC UFC 3-301-01 Tool
S1 6.00% G MCER Spectral Response Acceleration Parameter at 1 second for Site Class BC UFC 3-301-01 Tool
SMS 17.80% G MCER Spectral Response Acceleration Parameter at short periods, Adjusted for Site Class Effects UFC 3-301-01 Tool
SM1 4.80% G MCER Spectral Response Acceleration Parameter at 1 second, Adjusted for Site Class Effects UFC 3-301-01 Tool
4.5.1 Earthquake-Generated Inertial Forces Loading
HPIER 33.90 ft = ELT - ELG Pool Depth to Riverbed. Assume entire Pier is submerged EM 1110-2-2107 Figure 4.1 y 7.00 ft = HPANEL / 2 Distance of applied force below pool surface, assume 1/2 Panel EM 1110-2-2107 Figure 4.1 ac 10.60% G = PGA Acceleration at inertial fluid pressures for short, stiff structures EM 1110-2-2107 4.4.6.6 pEQ-W 0.09 ksf = (7/8) * γW * ac * √(H* y) Earthquake-Generated Inertial Pressures at depth, y EM 1110-2-2107 Eq. 4.3 wEQ-W 0.18 klf = pEQ-W * SFU Earthquake-Generated Inertial Loading on Single Fender Support Beam
MEQ-i -3.52 k-ft = -0.125 * wEQ-W * LPF
Maximum Moment due to Earthquake Loads at Center Support
MEQ-M 1.97 k-ft = 0.07 * wEQ-W * LPF
Maximum Moment due to Earthquake Loads along Span
VEQ_E 0.84 kips = (3/8) * wEQ-W * LPF Maximum Shear at End due to Earthquake Loads
REQ_E 0.84 kips = (3/8) * wEQ-W * LPF Maximum Reaction at End due to Earthquake Loads
VEQ_I 1.40 kips = (5/8) * wEQ-W * LPF Maximum Shear at Intermediate Support due to Earthquake Loads
REQ_I 2.80 kips = (10/8) * wEQ-W * LPF Maximum Reaction at Intermediate Support due to Earthquake Loads
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.5 Unfactored Load Summary
4.5.2 Unfactored Loads at Fender Support Members
Gravity Gravity Impact Impact Impact Wind Wind w/ Ice w/o Ice Debris Ice Barge on Ice (Service)
D GICE G L Hd Hw IX IMD IMICE BI WICE W WS EQ
Mv-I (k-ft) -5.61 -5.54 -1.82
Mv-M (k-ft) 3.14 3.10 1.02
Vv_E (kip) 1.34 1.32 0.43
Rv_E (kip) 1.34 1.32 0.43
Vv_I (kip) 2.23 2.20 0.72
Rv_I (kip) 4.46 4.41 1.45
Ml-I (k-ft) -3.08 -2.38 98.83 -16.06 -4.18 -30.55 -0.26 -1.36 -0.73 -3.52
Ml-M (k-ft) 1.73 1.33 -55.35 34.63 2.34 65.85 0.15 0.76 0.41 1.97
Vl_E (kip) 0.74 0.57 -23.58 13.28 1.00 25.24 0.06 0.32 0.18 0.84
Rl_E (kip) 0.74 0.57 -23.58 13.28 1.00 25.24 0.06 0.32 0.18 0.84
Vl_I (kip) 1.23 0.95 -39.30 -13.28 1.66 -25.24 0.11 0.54 0.29 1.40
Rl_I (kip) 2.45 1.89 -78.59 12.00 3.32 22.82 0.21 1.08 0.58 2.80
P (kip) 28.47 11.40 54.14
T (k-ft)* 5.99 6.16 0.31
*Because the Fender Support Beam Connects to the Post at the Flange, there will be torsion on the connection. Assuming that the connection at the post resists all the torsion from the beam, this calculates the expected torsion in the beam and the connection. Assume that only vertical loads on the fender support beams apply torsion to the connection.
Moment Arm of Fender Support Beam from Outside Face of the Vertical Post xPF 6.10 in = dPF / 2 Moment Arm of Fender Support Beam from Outside Face of the Vertical Post xHF 24.20 in = dPF + eHF Moment Arm of Assumed Fender Product from Outside Face of the Vertical Post xCF 17.20 in = dPF + tHF + tPANEL / 2 Moment Arm of Assumed Fender Panel from Outside Face of the Vertical Post
Recall Vertical Forces
WHF 0.22 klf 110% of the Weight of Assumed Horizontal Fender Dead Load
WCF 0.03 klf 110% of the Weight of Assumed Composite Panel per Support Beam Dead Load
WPF 0.06 klf 110% of the Self Weight of Fender Support Beam Dead Load wv G-m 0.05 klf Recall Assumed Weight of Mud Collected in Beam (Assume 110%) Gravity Load wv G-i-PANEL 0.000 klf Recall Weight of Atmospheric Ice on Assumed Panel Gravity Load wv G-i-HF 0.003 klf Recall Weight of Atmospheric Ice on Assumed Horizontal Fender Gravity Load wv G-i-BEAM 0.001 klf Recall Weight of Atmospheric Ice on Fender Support Beam Gravity Load wv G-i-COLL 0.228 klf Recall Weight of Ice Collar Between Fender Support Beams Gravity Load
Calculate Torsion at Beam
LPF-T 12.58 ft Recall Length of Span Between Hydraulic Cell and Post
TDLb 5.99 k-ft = (WPF * xPF + WHF * xHF) * LPF Torsion on Beam due to Dead Load
TGL-Nib 0.31 k-ft = (wv-G-m * xPF) * LPF Torsion on Beam due to Gravity Load without Ice
TGL-Wib 6.16 k-ft = TGL-NIb + ((wv G-i-HF + wv G-i-COLL) * xHF + wv G-i-BEAM * xPF) * LPF Torsion on due to Gravity Load w/ Ice
Load
Earth-quake WindLiveDead
Hydro-
Dynam.
Wave Ice T Exp
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.5 Unfactored Load Summary (cont.)
4.5.3 Unfactored Loads at Post
4.5.3.1 Torsion at Post Connection
See Equations and Parameters from Previous Section
LPF-T 25.15 ft Recall Total Length of Single Fender Support Beam
TDL 11.97 k-ft = (WPF * xPF + WHF * xHF) * LPF-T Torsion on Connection due to Dead Load
TGL-NI 0.62 k-ft = (wv-G-m * xPF) * LPF-T Torsion on Connection due to Gravity Load without Ice
TGL-WI 12.32 k-ft = TGL-NI + ((wv G-i-HF + wv G-i-COLL) * xHF + wv G-i-BEAM * xPF) * LPF-T Torsion on due to Gravity Load w/ Ice
4.5.3.2 Unfactored Loads applied to the strut per fender support beam
PT = Rv_I + Pv-P
MT = T + Rv_I * dP / 2
VT = Rl_I
Gravity Gravity Impact Impact Impact Wind Wind w/ Ice w/o Ice Debris Ice Barge on Ice (Service)
D GICE G L Hs Hd Hw IX IMD IMICE BI WICE W EQ
Pv-P (kips) 0.22 0.88
PT (kips) 4.68 4.41 1.45 0.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
MT (k-ft) 14.16 14.49 1.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
VT (kips) 0.00 0.00 0.00 0.00 2.45 1.89 -78.59 12.00 3.32 22.82 0.21 1.08 0.58 2.80
4.5.4 Unfactored Loads at Struts
Load Dead
Earth-quake Live
Hydro-
Dynam.
Wave Ice T Exp Wind
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.6 Factored Load Combination
4.6.1 Load Factors
By inspection of the unfactored loads, the load combinations that will control in lateral forces towards the mooring pier are those with Ice
Thermal Expansion and Barge Impact as the principal loads. The load combinations that will control in lateral forces away from the mooring pier are those with Earthquake Loads as the principal load. Hydrodynamic, Live, and Wind loads will be companion loads. Wave, Debris Impact, Ice
Impact, Wind on Ice, and Earthquake Forces will not be included as they will not control by inspection.
LC 1 D Max 1.60 1.40
LC 2 D Min 0.00 1.40
LC 3 IX Max 1.20 1.60 1.30 1.00 1.00
LC 4 IX Min 0.90 0.00 1.30 1.00 1.00
LC 5 BI Max 1.20 1.60 1.30 1.00 1.00
LC 6 BI Min 0.90 0.00 1.30 1.00 1.00
LC 7 Max 1.20 1.60 0.00 1.00 0.50
LC 8 Min 0.90 0.00 0.00 1.00 0.50
LC 9 Max 1.20 1.60 0.00 1.00 1.00
LC 10 Min 0.90 0.00 0.00 1.00 1.00
LC S 1 D Max 1.00 1.00
LC S 2 D Min 0.00 1.00
LC S 3 IX Max 1.00 1.00 1.00 1.00 1.00
LC S 4 IX Min 1.00 0.00 1.00 1.00 1.00
LC S 5 BI Max 1.00 1.00 1.00 1.00 1.00
LC S 6 BI Min 1.00 0.00 1.00 1.00 1.00
LC S 7 Max 1.00 1.00 1.00 1.00 1.00
LC S 8 Min 1.00 0.00 1.00 1.00 1.00
LC S 9 Max 1.00 1.00 1.00 1.00 1.00
LC S 10 Min 1.00 0.00 1.00 1.00 1.00
LC F 1 D Max 1.00 1.00
LC F 2 D Min 0.00 1.00
LC F 3 IX Max 1.00 1.00 1.00 1.00 1.00
LC F 4 IX Min 1.00 0.00 1.00 1.00 1.00
LC F 5 BI Max 1.00 1.00 1.00 1.00 1.00
LC F 6 BI Min 1.00 0.00 1.00 1.00 1.00
LC F 7 Max 1.00 1.00 1.00 1.00 1.00
LC F 8 Min 1.00 0.00 1.00 1.00 1.00
LC F 9 Max 1.00 1.00 1.00 1.00 1.00
LC F 10 Min 1.00 0.00 1.00 1.00 1.00
LC N 1 D Max 2.00 2.00
LC N 2 D Min 0.00 2.00
LC N 3 IX Max 2.00 2.00 2.00 2.00 2.00
LC N 4 IX Min 2.00 0.00 2.00 2.00 2.00
LC N 5 BI Max 2.00 2.00 2.00 2.00 2.00
LC N 6 BI Min 2.00 0.00 2.00 2.00 2.00
LC N 7 Max 2.00 2.00 2.00 2.00 2.00
LC N 8 Min 2.00 0.00 2.00 2.00 2.00
LC N 9 Max 2.00 2.00 2.00 2.00 2.00
LC N 10 Min 2.00 0.00 2.00 2.00 2.00
* The Load Factor for Dead Loads will be Shown in γPR for Load Combinations LC 1, LC 2, LC S 1, LC S 2, LC F 1, LC F 2, LC N 1, and LC N 2 as the dead load is the principal load in these combinations.
SERVICE
FINITE FATIGUE
INFINITE FATIGUE
STRENGTH /
EXTREME
Impact (BI)
Service Wind Companion Load
Only
Hydrodynamic Companion
Load Only
Dead (Usual)*
Ice, Thermal Exp
Impact (BI)
Dead (Usual)*
Ice, Thermal Exp
Impact (BI)
Dead (Usual)*
Ice, Thermal Exp
Basic Wind Companion Load
Only
Hydrodynamic Companion
Load Only
Basic Wind Companion Load
Only
Hydrodynamic Companion
Load Only γc_Hd γc_W γc_WS
Dead (Usual)*
Ice, Thermal Exp
Impact (BI)
Basic Wind Companion Load
Only
Hydrodynamic Companion
Load Only
Comb. # Limit State Principal Load Max /
Min γp_D γp_G γp_GICE γpr γc_L
Troy Lock Dam Mooring Pier
SUBJECT
Fender Support Framing Design
Designed by:DSK
Date: 05/02/2024
Checked by: BLP
Date: XX/XX/2024
4. Load Calculations (cont.)
4.6 Factored Load Combination
4.6.2 Factored Loads at Fender Support Members
U = Σγp * Lp + γpr * Lpr + Σγc * Ltc + γc * Ldc Factored Applied Load on Hydraulic Steel Structures EM 1110-2-2107 Eq. 4.2
Axial Torsion
Lateral Vertical Lateral Vertical Lateral Vertical Lateral Vertical (kips) (k-ft)
LC 1 D 0.00 -16.72 0.00 9.37 0.00 3.99 0.00 6.65 0.00 18.24
LC 2 D 0.00 -7.85 0.00 4.40 0.00 1.87 0.00 3.12 0.00 8.38
LC 3 IX 125.40 -15.60 -70.22 8.74 -29.92 3.72 -49.86 6.20 0.00 17.04
LC 4 IX 125.40 -5.05 -70.22 2.83 -29.92 1.20 -49.86 2.01 0.00 5.39
LC 5 BI -42.79 -9.64 87.33 5.40 33.55 2.30 -31.59 3.83 70.38 7.68
LC 6 BI -42.79 -5.05 87.33 2.83 33.55 1.20 -31.59 2.01 70.38 5.39
LC 7 -0.68 -9.64 0.38 5.40 0.16 2.30 0.27 3.83 0.00 7.68
LC 8 -0.68 -5.05 0.38 2.83 0.16 1.20 0.27 2.01 0.00 5.39
LC 9 -3.08 -9.64 1.73 5.40 0.74 2.30 1.23 3.83 0.00 7.68
LC 10 -3.08 -5.05 1.73 2.83 0.74 1.20 1.23 2.01 0.00 5.39
LC S 1 D 0.00 -11.15 0.00 6.25 0.00 2.66 0.00 4.44 0.00 12.15
LC S 2 D 0.00 -5.61 0.00 3.14 0.00 1.34 0.00 2.23 0.00 5.99
LC S 3 IX 95.75 -11.15 -53.62 6.25 -22.84 2.66 -38.07 4.44 0.00 12.15
LC S 4 IX 95.75 -5.61 -53.62 3.14 -22.84 1.34 -38.07 2.23 0.00 5.99
LC S 5 BI -33.63 -7.43 67.57 4.16 25.98 1.77 -24.02 2.95 54.14 6.30
LC S 6 BI -33.63 -5.61 67.57 3.14 25.98 1.34 -24.02 2.23 54.14 5.99
LC S 7 -0.73 -7.43 0.41 4.16 0.18 1.77 0.29 2.95 0.00 6.30
LC S 8 -0.73 -5.61 0.41 3.14 0.18 1.34 0.29 2.23 0.00 5.99
LC S 9 -3.08 -7.43 1.73 4.16 0.74 1.77 1.23 2.95 0.00 6.30
LC S 10 -3.08 -5.61 1.73 3.14 0.74 1.34 1.23 2.23 0.00 5.99
LC F 1 D 0.00 -11.15 0.00 6.25 0.00 2.66 0.00 4.44 0.00 12.15
LC F 2 D 0.00 -5.61 0.00 3.14 0.00 1.34 0.00 2.23 0.00 5.99
LC F 3 IX 95.75 -11.15 -53.62 6.25 -22.84 2.66 -38.07 4.44 0.00 12.15
LC F 4 IX 95.75 -5.61 -53.62 3.14 -22.84 1.34 -38.07 2.23 0.00 5.99
LC F 5 BI -33.63 -7.43 67.57 4.16 25.98 1.77 -24.02 2.95 54.14 6.30
LC F 6 BI -33.63 -5.61 67.57 3.14 25.98 1.34 -24.02 2.23 54.14 5.99
LC F 7 -1.36 -7.43 0.76 4.16 0.32 1.77 0.54 2.95 0.00 6.30
LC F 8 -1.36 -5.61 0.76 3.14 0.32 1.34 0.54 2.23 0.00 5.99
LC F 9 -3.08 -7.43 1.73 4.16 0.74 1.77 1.23 2.95 0.00 6.30
LC F 10 -3.08 -5.61 1.73 3.14 0.74 1.34 1.23 2.23 0.00 5.99
LC N 1 D 0.00 -22.31 0.00 12.49 0.00 5.32 0.00 8.87 0.00 24.30
LC N 2 D 0.00 -11.22 0.00 6.28 0.00 2.68 0.00 4.46 0.00 11.97
LC N 3 IX 191.50 -22.31 -107.24 12.49 -45.68…
This is the start of the file's text. The full file is on GovTribe.