W912DS20R0022 Amendment 7.pdf
PDF 416 KB Posted
- Attached to
- Solicitation: Gun Tube Heat Treat Furnace Replacement at the Watervliet Arsenal, Watervliet, NY
- Solicitation number
- W912DS20R0022
About this file
This document contains an amendment to a solicitation for a gun tube heat treat furnace replacement project at Watervliet Arsenal. The amendment provides responses to bidder questions to clarify the project scope. The existing furnace contains hazardous materials that must be removed per the quantities specified. Demolition of the furnace system and placement in government trucks is required. The contractor must remove the entire existing furnace system and has access to coordinate crane operations. The wood flooring at the project location contains asbestos and must be managed accordingly if impacted by the work. Overhead piping and conduit taken out of service must be removed, while inaccessible underground utilities must be sealed in place.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Provide responses to RFIs
Offeror must acknowledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow in methods: in the space provided on SF1442, by separate letter, or by signing block 15 below. FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS20R0022
X 9B. DATED (SEE ITEM 11)
13-Jan-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
19-Feb-2021
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DS20R0022
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been added by full text:
AMENDMENT 7
Gun Tube Heat Treat Furnace Replacement at Watervliet Arsenal, NY Solicitation W912DS20R0022 Amendment 7 Bidder Inquiry Questions and Responses OFFERORS' QUESTIONS AND GOVERNMENT REPLY: Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below.
These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only ”and do not revise the solicitation, plans or specifications. By this Amendment Offerors are advised of this provision, applicable to all RFI responses.
RESPONSES TO RFIs:
Question 1:
Request clarification of assumed scope for removal and disposal of Hazardous Materials.
Response 1:
Refer to SECTION 01 57 19 paragraph 3.8 HAZARDOUS MATERIALS quoted, in part:
“On March 6, 2018, a limited hazardous materials inspection was performed for materials suspect of containing asbestos or lead paint at Watervliet's existing Selas furnace system. The results of the inspection, sample collection and subsequent sample analysis are detailed in the Limited Asbestos and Lead Survey Report in the Appendix of the Field Investigation Report located in the Appendix of this RFP. The Contractor must assume the presence of hazardous materials for the purposes of bidding based on the findings of this report.”
The Government has reviewed the report and ascertained that hazardous materials are present in AT LEAST the following quantities:
ASBESTOS – Wire Insulation – 113,600 Linear Feet ASBESTOS – Gaskets – 2,243 Square Feet (SF) ASBESTOS – Exhaust Duct Insulation – 11,111 SF ASBESTOS – Corrugated Cementitious Panel Siding – 119,340 SF OZONE DEPLETING SUBSTANCES (ODS) - Refrigerant gases and fluids which must be recovered and recycled in accordance with federal regulations – 10 Vessels or 10 Pounds (lbs)
Question 2:
It is stated that the hauling of the existing furnace is the responsibility of Watervliet's scrap contractor and the operation of the existing overhead cranes will be provided by Watervliet Arsenal for the removal (and install of new furnaces). Please provide the maximum weight and size that the scrap contractors trucks can handle. Please also clarify if the existing furnace will be scrapped, restored or salvaged as this will dictate how the systems will be dismantled. Furthermore please provide the extent of the demolition required other that the furnace such as existing modules, steel, piping and control modules.
Response 2:
The Government will haul the scrapped SELAS furnace away. The existing furnace is to be scrapped. The scrap hauler can apply for oversize load permits as needed. Refer to paragraph 2.4.3 Site Preparation. Site preparation must include demolition of the existing furnace system and placement of it in the Government's trucks. The Design/Build Contractor is responsible for the removal of the entire furnace system as stated in Section 01 10 00 Statement of Work. Refer to paragraph 1.2.3 Project Scope Summary which states, "The D/B Contractor must
W912DS20R0022
provide a complete, turnkey project that includes: a. Removal of the existing Selas furnace system." The extent of demolition includes the system. The contractor shall assume that the Government’s scrap hauler trucks utilize standard 30-yard dumpsters.
Question 3:
For the demolition of the existing furnace and associated equipment we will need unrestricted access (from one side of the building to the other) with a crane trellis. Does the arsenal and or the USACE need to use any of the three cranes while these operations are ongoing? Please confirm if there will be any restrictions for operating a trellis crane to convey material from the south end of the building to the loading area on the north end of the building during demolition?
Response 3:
Refer to Section 01 10 00 Paragraph 1.2.6 Site Access and Deliveries.
All crane activities will need to be coordinated with Watervliet Arsenal prior to use and shall be reflected in the contractor's project schedule for coordination. The Government will use the contractor’s project schedule to de-conflict simultaneous operations to the extent practical and necessary.
Question 4:
The field investigation report indicates that the existing wood flooring where the new furnace will be located will be removed and replaced under a separate contract; is this still the case as the report makes mention that it could be done under the furnace replacement project? If it is not under the furnace replacement project please provide a start and end date when this work will occur? If it is covered under the furnace replacement contract please indicate if the flooring has asbestos, lead or other hazardous materials?
Response 4:
The Government does not intend to use a separate contract for flooring work nor flooring removal. This contract includes flooring work and, if necessary, flooring removal pursuant to SECTION 01 10 00 paragraph 3.3.1 Summary of Architectural Work.
Refer to LIMITED ASBESTOS AND LEAD SURVEY dated 2 APRIL 2018 item #7 listed under Section 4.0:
"Wood Block and Concrete Flooring – The flooring system for the facility consists of concrete flooring and wood block flooring systems depending on the function of the area on the factory floor. The area proposed for the location of the new equipment is equipped with wood block. Given the age of the facility, and the manufacturing processes conducted within the facility, there is an elevated potential that over the life of the facility chlorinated solvents, PCBs and various types of cutting oils with complex chemistry may have been used at the facility. The concrete flooring is permeable, and the wood flooring is highly porous and is susceptible to absorbing any chemicals spilled over the years. In the event the flooring systems are to be impacted during the demolition of the existing furnace or installation of the new furnace it should be evaluated for potential contamination and managed accordingly."
Samples of the wood floor blocks were taken and tested and are documented on Page 8 of the LIMITED
ASBESTOS AND LEAD SURVEY.
Question 5:
Does any piping and or conduit that is set to be demoed be cut, capped and abandoned in place if it is inaccessible?
Response 5:
The Government considers any overhead suspended piping and conduit to be accessible, and, therefore, any overhead suspended piping and conduit which is taken out of service must be removed by the contractor.
The Government considers piping and conduit to be inaccessible if it is buried underground, beneath a slab-on-grade, within a wall/partition, or above a closed/finished ceiling. Inaccessible piping and conduit which is taken out of service must be cut, capped, and sealed by the contractor and shown on the contractor's as-built drawings. If the work damages the fire or smoke rating of an existing surface, the contractor shall repair the existing surface to restore the fire or smoke rating.
(End of Summary of Changes)