W912DS20R0022 Amendment 4.pdf

PDF 591 KB Posted

Attached to
Solicitation: Gun Tube Heat Treat Furnace Replacement at the Watervliet Arsenal, Watervliet, NY
Solicitation number
W912DS20R0022
Issued by

About this file

This document provides responses to questions from offerors on an amendment to a solicitation for a gun tube heat treat furnace replacement project at the Watervliet Arsenal in New York. The amendment extends the proposal due date to February 24, 2021 and provides clarification but does not otherwise revise the scope of work. The project involves replacing the existing furnace and does not require any modifications to the existing fire suppression, mass notification, or fire alarm systems. The responses clarify that the solicitation does not mandate upgrades to meet certain standards. A requested extension to the bid date is denied and scheduling details are provided referring offerors to the solicitation for estimated project duration and review timelines.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Extend ProjNet inquiry date to 12 February 2021 at 11:59AM EST

2. Provide responses to RFIs

Offeror must acknowledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow in methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE

SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS20R0022

X 9B. DATED (SEE ITEM 11)

13-Jan-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Feb-2021

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS20R0022

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been added by full text:

AMENDMENT 4

OFFERORS' QUESTIONS AND GOVERNMENT REPLY: Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below.

These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only ”and do not revise the solicitation, plans or specifications. By this Amendment Offerors are advised of this provision, applicable to all RFI responses.

Question 1:

RFP does not mention anything about fire suppression work, please verify no fire suppression work is required.

Government Response 1:

The area of work for the replacement gun tube heat treat furnace does not have a fire suppression system. Therefore, no fire suppression system modifications are required under this scope of work.

Question 2:

Does building has a mass notification system? If not please verify scope does not require the installation of one.

Government Response 2:

Building 135 does not have a mass notification system. Therefore, no mass notification system modifications are required under this scope of work.

Question 3:

Please verify fire alarm system does not have to meet the requirements of ECB218-17 Government Response 3:

ECB 2018-17 requires the fire annunciation system to provide digital and text messages. The Government does not believe this project warrants this upgrade, but the Government also does not wish to preclude the fire protection designer of record from exercising due judgement with respect to technical requirements analysis.

Question 4:

EXTENSION OF BID DATE: The short allotment of time provided to develop a proposal for a project of this magnitude is unrealistic. Respectfully request an extension of the bid due date to 4 March 2021 three weeks after the current due date.

Government Response 4:

The required procurement schedule doesn't permit the Government to grant the requested extension.

The proposal due date is 24 February 2021 at 2PM EST.

Question 5:

COPY OF LOGISTICS PLAN: Documentation does not provide any timeline or information detailing WVA / USACE activities associated with this project, shut down schedule (when available to start project), maximum durations-if any, hold periods for testing and durations, hold periods between phase 1 and phase 2 and duration or submittal approval durations.

Respectfully request a timeline and logic schedule.

Government Response 5:

Refer to Solicitation Section C paragraph 5.2 TAB C – FACTOR 2 – PROPOSEDCONTRACT DURATION, PHASING AND SUMMARY SCHEDULE.

W912DS20R0022

The Offeror shall submit a summary level schedule. The Government will evaluate the Offeror's schedule. A schedule which offers advantages to the Government will receive additional consideration, and the Government will consider the Offeror’s proposed shut down schedule when making the evaluation.

SECTION 01 11 00 paragraph 1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION

OFWORK:

"The Contractor must be required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use, not later than 760 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion must include the final cleanup of the premises. (FAR 52.212-3)" SECTION 01 33 00 paragraph 1.10 SCHEDULING:

"Contracting Officer review will be completed within 30 calendar days after the date of submission. Allow an additional seven calendar days for review and approval of submittals for the furnace system."

The Government anticipates or expects to be able to issue Notice to Proceed in or around JUNE 2021.

(End of Summary of Changes)