Amendment 0002

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W16ROE81723863

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. Revise and reissue the bid schedule.

2. Answ er questions to prospective bidders for information purposes only.

3. Revise draw ings and specifications as outlined below .

NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 18

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Jan-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS18B0035

X 9B. DATED (SEE ITEM 11)

13-Dec-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Jan-2019

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS18B0035

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

Base Work

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for the construction of new Army Aviation Support Facility (Building 4421) as described in the plans and specifications except for work included in items below.

FOB: Destination

MILSTRIP: W16ROE81723863

PURCHASE REQUEST NUMBER: W16ROE81723863

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job

Base Work

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: Site work, (includes all plant, labor, and material), all work outside the five-foot line of the building perimeter, i.e. Apron Pavement, parking demolition of existing building, excluding items below.

FOB: Destination

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Job Base Work

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for the relocation of the blast berm, as described in the plans and specifications.

0004 1 Job Base Work

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for the Storage Facility (Building 4420) as described in the plans and specifications except for work included in items below.

0005 1 Job Base Work

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work for the Final Record Drawing Submission (See Section 00 73 00). Pre-priced at $35,000.00.

0006 1 Job OPTION Option 1

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for the reduction of parking spaces and associated travel aisle, concrete curb and site lighting at the western portion of the POV parking lot as illustrated on drawing CP102. Provide stabilized grass for this area.

0007 1 Job OPTION Option 2

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for reduction of asphalt surface for the parking spaces at the eastern portion of the POV parking lot and as illustrated on drawing CP102. The parking space are to remain gravel only.

0008 1 Job OPTION Option 3

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for the elimination of the access road south of the Army Apron as illustrated on drawing CP102.

0009 1 Job OPTION Option 4

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL:

Purchase, deliver, and install Furnishings and Appliances, per CID & FF&E packages.

0010 1 Job OPTION Option 5

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for the elimination of portion of parking apron by one parking spot as shown on drawings.

0011 1 Job OPTION Option 6

FFP

Construction of FY18 Aircraft Apron, Taxiway & Support Facility, JBMDL: All work (includes all plant, labor, and material) for the purchase delivery and installation of flight equipment lockers, as outlined in Appendix C, at an adjacent hangar facility.

TOTALS/NOTES

TOTAL BASE BID PRICE FOR LINE ITEMS 0001- 0005 ___________________

TOTAL OPTIONAL BID PRICE FOR LINE ITEMS 0006-0011 ___________________

TOTAL BASE BID PRICE & OPTIONS FOR LINE ITEMS 0001- 0011 ___________________

NOTES:

1. Bidders are required to bid on all the Base Bid and all the Optional Bid Items or their bids will be rejected.

2. Bidders are reminded that they must bid on the issued plans and specifications as amended. Any deviations, conditions or attachments made by the bidder himself, thereto, may render the bid non-responsive and be cause for its rejection.

3. Line item 0005 is pre-priced at $35,000.00 and this price shown may not be changed. See Section 00 73 00 for Final Record Drawing definition and requirement.

4. The Basis of Evaluation will be the lowest responsive, responsible bid based on the Total Amount for the Base Bid Items plus the Optional Bid Items (Line Items 0001 thru 0011).

5. Options 1 thru 3 and 5: The price for Options 1 thru 3 and 5 are credits and shall be designated with a (-) NEGATIVE SIGN. If exercised, Option(s) will be exercised at the time of award. These Options will not effect contract duration.

6. Option #4 and #6: At any time prior to 330 calendar days after issuance of the Notice to Proceed, the Government at its option, may direct the Contractor, by written order, to perform the work and/or services provided under this Option. Execution of this option will not alter the project completion date.

7. The Bid Acceptance Period is as stated on Standard Form 1442.

8. Submit technical inquiries and questions relating to this solicitation via Bidder Inquiry in ProjNet at

(https://www.projnet.org) at least 10 calendar days prior to the date established in the IFB for receipt of bids. The Government reserves the right to decline addressing questions received less than 10 calendar days prior to receipt of bids. If a bidder believes that the requirements in this Invitation for Bid contain an error, omission, or are otherwise unsound; immediately notify the Contract Specialist in writing with supporting rationale.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment or question will receive answers in an amendment. All timely questions and approved answers will be made available in amendments and posted to: www.FBO.gov

Bidder Inquiry Key: JC7MWY-6C84XH

Specific Instructions for Initial ProjNet Bid Inquiry Access:

1. From the ProjNet home page, click on Quick Add on the upper right side of the screen.

2. Identify the Agency as USACE.

3. Key. Enter the Bidder Inquiry Key listed above.

4. E-mail. Enter the e-mail address you would like to use for communication.

5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

6. Enter your Secret Answer and click Login. Once this is completed, you are logged into the

System.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been added by full text:

AMENDMENT 0002 to DRAWINGS and SPECIFICATIONS for P-650 Aircraft Apron, Taxiway & Support Facilities, Joint Base McGuire-Dix-Lakehurst, New Jersey.

TO BIDDERS

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- None

2. The following DRAWINGS have been REVISED and REISSUED:

- Drawing A-311

- Drawing A-603

- Drawing CS-301

- Drawing CP-101

- Drawing CP-301

- Drawing CP-302

- Drawing CP-521

- Drawing CP-530

- Drawing CP-531

- Drawing CS-311

- Drawing CU-101

- Drawing ES-101

- Drawing ES-201

3. The following DRAWINGS have been ADDED:

- None

4. The following DRAWINGS have been DELETED:

- None

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- Appendix C - P-650 Aircraft Aprons (Shelving)

- Appendix D - P-650 Aircraft Aprons (Antenna)

- Appendix E - Site Visit Sign In Sheet

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- None

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- CID, SID, FFE - The order form for the TB3 Conference Table is hereby replaced.

- Section 00 10 00 Solicitation – Bid schedule is hereby reissued in its entirety.

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

- Section 08 33 23 – Overhead Coiling Doors – delete the last sub-paragraph of paragraph

2.2.1.1 that relates to thermal performance of the coiling doors without replacement.

- Section 08 71 00 – Door Hardware – revise the last Hardware Set in the table in paragraph 3.6 under the Set # heading from “18” to “1B”

- Section 32 17 23 – Pavement Markings – revise paragraph 2.2.5.1 as follows: “FS TT-B-1325, Type I, Gradation A,”

- Section 32 13 14.13 – Concrete Paving For Airfield and Other Heavy Duty Pavements – Add the following to the beginning of the section as follows:

“1.0 UNIT PRICES

1.0.1 Measurements

The quantity of concrete to be paid for will be the volume of concrete in cubic yards including thickened edges, where required, placed in the completed and accepted pavement. Concrete will be measured in place in the completed and accepted pavement only within the neat line dimensions shown in the plan and cross section. No deductions will be made for rounded or beveled edges or the space occupied by pavement reinforcement, dowel bars, tie bars, or electrical conduits, nor for any void, or other structure extending into or through the pavement slab, measuring 3 cubic feet or less in volume. No other allowance for concrete will be made unless placed in specified locations in accordance with the approved contract modification. The quantity of other materials specified herein, and used in the construction of the work covered by this section, will not be measured for payment, but will be considered a subsidiary obligation, covered under the price per cubic yard for concrete.

Joint sealing materials are covered in Section 32 13 73 COMPRESSION JOINT SEALS FOR

CONCRETE PAVEMENTS.

1.0.2 Payments

1.0.2.1 Lump Sum

The quantity of concrete will be paid for and included in the lump-sum contract price. If less than 100 percent payment is due based on the pay factors stipulated below, a unit price of $557 per cubic yard will be used for purposes of calculating the payment reduction.

1.0.3 Payment of Lots

When a lot of material fails to meet the specification requirements, that lot will be accepted at a reduced price or be removed and replaced. The lowest computed percent payment determined for any pavement characteristic discussed below (for example, thickness, grade, and surface smoothness) becomes the actual percent payment for that lot. The actual percent payment will be applied to the unit price and the measured quantity of concrete in the lot to determine actual payment.

Use results of strength tests to control concreting operations. Strength will be evaluated, but will not be considered for payment adjustment. Remove and replace any pavement not meeting the required 'Concrete Strength for Final Acceptance' at no additional cost to the Government.

1.0.4 Payment Adjustment for Smoothness

1.0.4.1 Straightedge Testing

Record location and deviation from straightedge for all measurements. When more than 5.0 and less than or equal to 10.0 percent of all measurements made within a lot exceed the tolerance specified in paragraph SURFACE SMOOTHNESS, after any reduction of high spots or removal and replacement, the computed percent payment based on surface smoothness will be 95 percent. When more than

10.0 percent and less than or equal to 15.0 percent of all measurements exceed the tolerance, the computed percent payment will be 90 percent. When more than 15.0 and less than or equal to 20.0 percent of all measurements exceed the tolerance, the computed percent payment will be 75 percent.

Remove and replace the lot when more than 20.0 percent of the measurements exceed the tolerance, at no additional cost to the Government.

1.0.4.2 Profilograph Testing

Record location and data from all profilograph measurements. When the Profile Index of a 0.1 mile segment of a lot exceeds the tolerance specified in paragraph SURFACE SMOOTHNESS by 1.0 inch per mile but less than 2.0 inches per mile, after any reduction of high spots or removal and replacement, the computed percent payment based on surface smoothness will be 95 percent. When the Profile Index exceeds the tolerance by 2.0 inches per mile but less than 3.0 inches per mile, the computed percent payment will be 90 percent. When the Profile Index exceeds the tolerance by 3.0 inches per mile but less than 4.0 inches per mile, the computed percent payment will be 75 percent.

Remove and replace the lot when the Profile Index exceeds the tolerance by 4.0 inches per mile or more, at no additional cost to the Government.

1.0.5 Payment Adjustment for Plan Grade

When more than 5.0 and less than or equal to 10.0 percent of all measurements made within a lot are outside the specified tolerance, the computed percent payment for that lot will be 95 percent. When more than 10.0 percent but less than 50 percent are outside the specified tolerances, the computed percent payment for the lot will be 75 percent. Remove and replace the deficient area where the deviation from grade exceeds the specified tolerances by 50 percent or more, at no additional cost to the Government.

1.0.6 Payment Adjustment for Thickness

Using the Average Thickness of the lot, determine the computed percent payment for thickness by entering the following table:

Computed Percent Payment for Thickness

Deficiency in Thickness Determined by cores inches

Pavements Equal To or Greater Than 8 inches Thick

Pavements Less Than 8 inches Thick

0.00 to 0.24 100 100

0.25 to 0.49 75 65

0.50 to 0.74 50 0

Computed Percent Payment for Thickness

Deficiency in Thickness Determined by cores inches

Pavements Equal To or Greater Than 8 inches Thick

Pavements Less Than 8 inches Thick

0.00 to 0.24 100 100

0.75 or greater 0 0

Where 0 percent payment is indicated, remove the entire lot and replace at no additional cost to the Government. Where either of the two cores from a sublot show a thickness deficiency of 0.75 inch or greater, 0.50 inch for pavements 8 inches or less in thickness, drill two more cores in the sublot and compute the average thickness of the four cores. If this average shows a thickness deficiency of 0.75 inch or more, 0.50 inch for pavements 8 inches or less in thickness remove the entire sublot.”

- Section 32 13 14.13 – Concrete Paving For Airfield and Other Heavy Duty Pavements – revise paragraph 2.2.1 as follows: “Provide Portland cement conforming to ASTM C150/C150M, Type II, low alkali including false set requirements.”

- Section 32 12 15.13 – Hot-Mix Asphalt Airfield Paving – Add the following to the beginning of the section as follows:

“1.0 FULL PAYMENT

1.0.1 Method of Measurement

Measurement of the quantity of hot-mix asphalt, per ton placed and accepted, shall be made for the purposes of assessing the pay factors stipulated below.

1.0.2 Basis of Payment

The measured quantity of hot-mixed asphalt will be paid for and included in the lump sum contract price. If less than 100 percent payment is due based on the pay factors stipulated in paragraph QUALITY ASSURANCE, a unit price per ton will be used for purposes of calculating the payment reduction.

1.0.3 PERCENT PAYMENT

When a lot of material fails to meet the specification requirements for 100 percent pay as outlined in the following paragraphs, that lot shall be removed and replaced, or accepted at a reduced price which will be computed by multiplying the unit price by the lot's pay factor. The lot pay factor is determined by taking the lowest computed pay factor based on either laboratory air voids, in-place density, grade or smoothness (each discussed below). Pay factors based on different criteria (i.e., laboratory air voids and in-place density) of the same lot will not be multiplied together to get a lower lot pay factor. At the end of the project, an average of all lot pay factors will be calculated. If this average lot pay factor exceeds 95.0 percent and no individual lot has a pay factor less than 75.1 percent, then the percent payment for the entire project will be 100 percent of the unit bid price. If the average lot pay factor is less than 95.0 percent, then each lot will be paid for at the unit price multiplied by the lot's pay factor. For any lots which are less than 2000 short tons, a weighted lot pay factor will be used to calculate the average lot pay factor.

1.0.3.1 Mat and Joint Densities

The average in-place mat and joint densities are expressed as a percentage of the average theoretical maximum density (TMD) for the lot. The average TMD for each lot will be determined as the average TMD of the two random samples per lot. The average in-place mat density and joint density for a lot are determined and compared with Table 1 to calculate a single pay factor per lot based on in-place density, as described below. First, a pay factor for both mat density and joint density are determined from Table 1. The area associated with the joint is then determined and will be considered to be 10 feet wide times the length of completed longitudinal construction joint in the lot. This area will not exceed the total lot size. The length of joint to be considered will be that length where a new lane has been placed against an adjacent lane of hot-mix asphalt pavement, either an adjacent freshly paved lane or one paved at any time previously. The area associated with the joint is expressed as a percentage of the total lot area. A weighted pay factor for the joint is determined based on this percentage (see example below). The pay factor for mat density and the weighted pay factor for joint density is compared and the lowest selected. This selected pay factor is the pay factor based on density for the lot. When the TMD on both sides of a longitudinal joint is different, the average of these two TMD will be used as the TMD needed to calculate the percent joint density. Rejected lots shall be removed and replaced. Rejected areas adjacent to longitudinal joints shall be removed 4 inches into the cold (existing) lane. All density results for a lot will be completed and reported within 24 hours after the construction of that lot.

Table 1. Pay Factor Based on In-place Density

Average Mat Density (4 cores)

Pay Factor, percent Average Joint Density (4 cores)

94.0 - 96.0 100.0 Above 92.5

93.9 100.0 92.4

93.8 or 96.1 99.9 92.3

93.7 99.8 92.2

93.6 or 96.2 99.6 92.1

93.5 99.4 92.0

93.4 or 96.3 99.1 91.9

93.3 98.7 91.8

93.2 or 96.4 98.3 91.7

93.1 97.8 91.6

93.0 or 96.5 97.3 91.5

92.9 96.3 91.4

92.8 or 96.6 94.1 91.3

92.7 92.2 91.2

92.6 or 96.7 90.3 91.1

92.5 87.9 91.0

92.4 or 96.8 85.7 90.9

92.3 83.3 90.8

92.2 or 96.9 80.6 90.7

92.1 78.0 90.6

92.0 or 97.0 75.0 90.5 below 92.0, above 97.0 0.0 (reject) Below 90.5

1.0.3.2 Pay Factor Based on In-place Density

An example of the computation of a pay factor (in I-P units only) based on in-place density, is as follows: Assume the following test results for field density made on the lot: (1) Average mat density = 93.2 percent (of lab TMD). (2) Average joint density = 91.5 percent (of lab TMD). (3) Total area of lot = 30,000 square feet. (4) Length of completed longitudinal construction joint = 2,000 feet.

a. Step 1: Determine pay factor based on mat density and on joint density, using Table 1:

Mat density of 93.2 percent = 98.3 pay factor.

Joint density of 91.5 percent = 97.3 pay factor.

b. Step 2: Determine ratio of joint area (length of longitudinal joint x 10 feet) to mat area (total paved area in the lot): Multiply the length of completed longitudinal construction joint by the specified 10 feet width and divide by the mat area (total paved area in the lot).

(2,000 feet x 10 feet)/30000 square feet = 0.6667 ratio of joint area to mat area (ratio).

c. Step 3: Weighted pay factor (wpf) for joint is determined as indicated below:

wpf = joint pay factor + (100 - joint pay factor) (1 - ratio) wpf =97.3 + (100-97.3) (1-.6667) = 98.2 percent

d. Step 4: Compare weighted pay factor for joint density to pay factor for mat density and select the smaller:

Pay factor for mat density: 98.3 percent. Weighted pay factor for joint density: 98.2 percent Select the smaller of the two values as pay factor based on density: 98.2 percent

1.0.3.3 Payment Adjustment for Smoothness (Final Wearing Surface Only) Profilograph Testing. Record the location and data from all profilograph measurements. When the Profile Index of a lot exceeds the tolerance specified in paragraph SMOOTHNESS REQUIREMENTS by 1.0 inch per mile, but less than 2.0 inches per mile, after any reduction of high spots or removal and replacement, the computed pay factor for that lot based on surface smoothness will be 95 percent. When the Profile Index exceeds the tolerance by 2.0 inches per mile, but less than 3.0 inches per mile, the computed pay factor will be 90 percent. When the Profile Index exceeds the tolerance by 3.0 inches per mile, but less than 4.0 inches per mile, the computed pay factor will be 75 percent. Remove and replact the lot when the Profile Index exceeds the tolerance by 4.0 inches per mile or more, at no additional cost to the Government.

Regardless of the above, correct any small individual area with surface deviation which exceeds the tolerance given above by more than 5.0 inches per mile or more, by grinding to meet the specification requirements above or remove and replace at no additional cost to the Government.

1.0.3.4 Laboratory Air Voids and Theoretical Maximum Density

Laboratory air voids will be calculated in accordance with ASTM D3203/D3203M by determining the density of each lab compacted specimen using the laboratory-prepared, thoroughly dry method in ASTM D2726/D2726M and determining the theoretical maximum density (TMD) of two of the sublots using ASTM D2041/D2041M. Laboratory air void calculations for each lot will use the average theoretical maximum density values obtained for the lot. The mean absolute deviation of the four laboratory air void contents (one from each sublot) from the JMF air void content will be evaluated and a pay factor determined from Table 2. All laboratory air void tests will be completed and reported within 24 hours after completion of construction of each lot. The TMD is also used for computation of compaction, as required in paragraph MAT AND JOINT DENSITIES above.

1.0.3.5 Mean Absolute Deviation

An example of the computation of mean absolute deviation for laboratory air voids is as follows:

Assume that the laboratory air voids are determined from 4 random samples of a lot (where 3 specimens were compacted from each sample). The average laboratory air voids for each sublot sample are determined to be 3.5, 3.0, 4.0, and 3.7. Assume that the target air voids from the JMF is 4.0. The mean absolute deviation is then:

Mean Absolute Deviation = (|3.5 - 4.0| + |3.0 - 4.0| + |4.0 - 4.0| + |3.7 - 4.0|)/4 = (0.5 + 1.0 + 0.0 + 0.3)/4 = (1.8)/4 = 0.45 The mean absolute deviation for laboratory air voids is determined to be 0.45. It can be seen from Table 2 that the lot's pay factor based on laboratory air voids, is 100 percent.

Table 2. Pay Factor Based on Laboratory Air Voids

Mean Absolute Deviation of Lab Air Voids from

JMF

Pay Factor, Percent

0.60 or less 100

0.61 - 0.80 98

0.81 - 1.00 95

1.01 - 1.20 90 Above 1.20 reject (0)

1.0.3.6 Pay Adjustment Based on Grade

Within 5 working days after completion of a particular lot incorporating the final wearing course, test the final wearing surface of the pavement for conformance with specified plan grade requirements. Perform all testing in the presence of the Governmentr. Provide a final wearing surface of pavement conforming to the elevations and cross sections shown and not vary more than 0.03 foot for runways or 0.05 foot for taxiways and aprons from the plan grade established and approved at site of work. Match finished surfaces at juncture with other pavements with finished surfaces of abutting pavements. Deviation from the plan elevation will not be permitted in areas of pavements where closer conformance with planned elevation is required for the proper functioning of drainage and other appurtenant structures involved. The grade will be determined by running lines of levels at intervals of 25 feet, or less, longitudinally and transversely, to determine the elevation of the completed pavement surface. Maintain detailed notes of the results of the testing and provide a copy to the Government immediately after each day's testing. When more than 5 percent of all measurements made within a lot are outside the 0.03 or 0.05 foot tolerance, the pay factor based on grade for that lot will be 95 percent. In areas where the grade exceeds the tolerance by more than 50 percent, remove the surface lift full depth; and replace the lift with hot-mix asphalt to meet specification requirements, at no additional cost to the Government. Diamond grinding may be used to remove high spots to meet grade requirements. Skin patching for correcting low areas or planning or milling for correcting high areas will not be permitted.”

- Section 32 12 15.13 – Hot-Mix Asphalt Airfield Paving – Add subparagraph 2.2.1 (f) as follows:

“The sodium sulfate soundness loss not exceeding 12 percent, or the magnesium sulfate soundness loss not exceeding 18 percent after five cycles when tested in accordance with ASTM C88.”

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

1. CP531 A5, C5: Please provide dimensions, details, specs, manufacturer of ductile iron mooring device per comments made on attached portions of dwg. # CP531. Thank you. Response:

Detail C5/CP531 to be updated and re-issue sheet CP531. Additional dimensions provided per UFC standards.

2. Due to the size and complexity of the project and considering that the project came out just before the Christmas and New Year Holidays, during which time many interested parties are on vacation, we request a three week extension to the current bid date of January 15, 2019.

Response: An extension of this magnitude cannot be granted at this time, please refer to the new Due date as issued in the previous amendment.

3. The two Pavement Marking Layout Drawings CP301 & CP302 appear to be incomplete and are difficult to interpret for bidding purposes. With regard to these two drawings please clarify the following issues and deficiencies in these drawings.

a. The Legend provides a symbol for a Grounding Point, but we cannot find any Grounding Points shown on Dwg's CP301 and CP302.

b. The line weight for the new Striping is not consistent between the two drawings, which makes interpretation difficult. For example: all new Striping should be shown in Thick, Bold Line Weight, and Thick, Bold Dashed Lines should be shown where the Striping is discontinuous.

c. The Legend on both drawings should provide and define a Symbol for existing Striping that is to remain.

d. Key Note #10 on Dwg CP301 calls-out a Free Standing Military Sign but it does not indicate where the corresponding sign details can be found in the set of drawings.

e. Dwg CP301 shows a square area with diagonal lines where the new sidewalk meets the new parking lot. But, there is no Key Note for this area.

f. Dwg CP301 does not call-out the need to provide any of the Taxi-Lane Centerline Striping for the C130 Aircraft that is shown on Dwg CS212.

g. Dwg CP301 does not call-out the need to provide all of the Taxi-Lane Centerline Striping for the UH-60 Aircraft that is shown on Dwg CS210.

h. Dwg CP302 does not call-out the need to provide all of the Taxi-Lane Centerline Striping of the AH-1Z/UH-1Y Aircraft as shown on Dwg CS213.

i. Dwg CP302 shows six very small Handicapped Symbols in the existing parking lot. Are these existing or new? Please identify and clarify with Key Notes or Call-Outs.

j. Dwg CP302 shows six parking spaces at 9'. Are these Existing or New? Please identify and clarify with Key Notes or Call-Outs. Response: a. Grounding points not shown on sheets CP301 and CP302. See Electrical drawings for grounding point information, ES-102 and E- 502.

b. Drawings CP301 and CP302 have been updated and reissued to make new striping consistent. Existing striping to remain is shaded. Additional key note call-outs have been added for clarity. New striping is bold. Sheet CP301: all striping within the new aircraft apron is new. Key Note #5 denotes location to tie into existing striping. Sheet CP302: all striping within the new apron expansion is new and ties to the existing striping. Key Note #5 denotes location to tie into existing striping.

c. Key Note #5 denotes location to tie into existing striping.

d. Free standing sign is per the UFC 3-120-1, section 3-3.1, Free Standing Identification Sign Primary. Sign details added to re-issued detail C2/CP530.

e. This area is striped to denote a no parking area. 4" white stripe, 3'-0" apart, 45-degree angle. Area is approximately 20'x18'. Refer to Key Note 11.

f. Added call outs provided for the centerline for parking for C-130. Sheet CP301 re-issued.

g. Added call outs provided for the centerline for parking for UH-60. Sheet CP301 re-issued.

h. Added call outs provided for the centerline for parking for AH-1Z/UH-1Y. Sheet CP302 re-issued.

i. Handicap symbols shown in this area are for existing parking spaces and not in scope of this project.

j. Six spaces in this area are new parking spaces. Key Note #4 added and re-issue CP302.

4. Drawing CP521 provides several Pavement Marking Details. With regard to the information presented on this drawing, please clarify the following:

a. Please add a Note on the drawings to clarify whether or not all Pavement Markings for this project are to be Painted.

b. Detail C1 provides a Rotary Aircraft Landing Detail. However, we cannot find any location on Dwg CP301 and CP302 where this Detail is to be provided.

c. Detail C2 provides a series of Pavement Marking Numerals. However, we cannot find any location on Dwg CP301 and CP302 where these Numerals are to be provided.

d. Detail B4 provides a Detail for CH Markings. However, it is not clear as to how this detail is to be used on this project. Please provide a sample Layout to clarify how this detail is to be applied to this project.

e. Detail A5 provides a Detail for UH Markings. However, it is not clear as to how this detail is to be used on this project. Please provide a sample Layout to clarify how this detail is to be applied to this project.

f. There is a call-out for Detail A2 called Pavement Marking Details, but there is no detail that is provided for Detail A2.

g. Details B2 and A1 show a 6" Solid Yellow Line protruding past the Dashed White perimeter striping for the Aircraft Parking Positions. But, these details do not provide a dimension for the length of the 6" Yellow Line that protrudes past the perimeter striping. Please provide the missing information. Response: a. Pavement markings are to be painted, refer to specification 32 17 23.

b. Landing zone added on CP301, Key Note 8 where new Taxiway 'X' intersects with existing Taxiway 'H'.

c. Numerals to be used in conjunction with detail A5/CP521.

d. Re-issued sheet CP521 provides detail of CH marking locations. Final markings shall be approved by COR prior to installation.

e. Re-issued sheet CP521 provides detail of UH marking locations. Final markings shall be approved by COR prior to installation.

f. A2 PAVEMENT MARKING DETAILS title is to be deleted from sheet.

g. The 6" solid yellow line does not extend past the aircraft parking stripe. Detail B2 and A1 updated to show labeling of Taxilane Center Line extending beyond the aircraft parking. Re-issued drawings CP301 and CP302

5. Key Note #8 on Dwg E-102 and Key Note #16 on Dwg E-103 call-out Electrical and Communications work that is to be provided for a Relocated Radio Antenna/Tower. Detail C4 on Drawing S-501 provides a Foundation Detail for the Relocated Antenna/Tower, which also states that the Contractor is to "Relocate Existing Tower and Embed 2'-0" into Foundation". However, we cannot find any information on the drawings that indicates where the Existing Antenna/Tower is located, how tall it is, how it is made, what it is made of, it and the documents do not indicate what needs to be done in order to facilitate the removal of the Existing Tower. Please provide all missing information related to the Existing Antenna/Tower so that the bidders understand what is involved with the Relocation of the Existing Antenna/Tower. Response: Drawing ED-101 shows where the antenna is located. Electrically, the antenna is shown to aware the contractor that disconnection and then new cabling shall be installed. Photos of the area are included in Appendix D.

6. Article 1.2 of Specification Section 01 14 00 requires the Contractor to erect Temporary Fencing/Temporary FAA Barricades at the Perimeter of the Construction Limits during Phase One and During Phase Two. This requirement will require a sizable quantity of the Temporary Fencing/Temporary FAA Barricades. Yet, there are no details of the Temporary Fencing/Temporary FAA Barricades provided in the bid documents. With regard to this requirement, please address and clarify the following:

a. Please provide Temporary Fence Plan drawings that show the limits of Temporary Fence and Temporary FAA Barricades for Phase One and for Phase Two.

b. Please show on the Temporary Fence Plan Drawings the limits of Temporary Fence and the limits of the Temporary FAA Barricades.

c. Please provide Typical Details for the Temporary Fence.

d. Please provide Typical Details for the Temporary FAA Barricades. Response: a. For bidding purposes, use G-004 and G-005 to determine amount of temporary fencing needed for Phase 1 and Phase 2 construction. As noted, on sheets G-004/G-005, the Contractor is responsible for preparing and submitting a final construction phasing plan.

b. For bidding purposes, use G-004 and G-005 to determine amount of temporary fencing needed for Phase 1 and Phase 2 construction. As noted, on sheets G-004/G-005, the Contractor is responsible for preparing and submitting a final construction phasing plan.

c. Temporary fencing details provided on re-issued CS531.

d. Low profile barricade with red flashers. All barricades adjacent to any open taxiway or apron must be low to the ground, no more than 18-inches in height with either steady burning or flashing red lights, spaced 50-feet apart maximum. Low profile barricade detail provided on re-issued CS530.

7. Key Note #2 on Dwg CS301 makes reference to Perimeter Fence Detail D1/CS310. With regard to the new Security Fence, please address and clarify the following:

a. There is no Detail D1 that is identified on Dwg CS310. Please confirm that the new Security Fence is to follow all of the typical Chain-Link Fence details on Dwg CS310.

b. The Chain-Link Security Detail on CS310 does not provide the required height of the fence fabric, which is labelled on the detail as the Fabric Width. Please provide this missing information.

c. Dwg CS310 provides a Fence Grounding Detail. Please clarify if the new Security Fence is to be Grounded, and if so, please clarify the spacing of the Ground Rods. Response: a. Perimeter Fencing details are on sheet A5/CS310 and CS311. Key Note #2, sheet CS301 has been revised to reference A5/CS310 and CS311 for fencing details.

b. Fence height required is shown on A4/CS311; 10-feet. As revised in this amendment.

c. See Electrical drawing ES-101; Key Note 25, ES-102; Key Note 14 for fence grounding details.

8. Key Note #3 on Dwg CS301 makes reference to Detail B3 on Dwg CS311 for the new 24' wide Sliding Gate. However, there is no Detail B3 on Dwg CS311. With regard to the new Sliding Gate please clarify the following:

a. Dwg CS311 provides a Sliding Gate Detail labelled as B1. Is the new 24' Sliding Gate to comply with Detail B1 on Dwg CS311?

b. Detail B1 on Dwg CS311 shows a Motor Operated Sliding Gate. Is a Motor Operated Sliding Gate to be provided for this project?

c. Please note that the Electrical Site Plan Dwg ES-102 does not provide any power to the new 24' Sliding Gate. If the Gate is to be Motor Operated, then please provide a revised Dwg ES-102 that provides power to the new Sliding Gate.

d. Detail B1 shows a Gate that is 11 feet tall, and the Gate includes 12" of Barbed Wire at the top, and the top of the Fence Fabric would be 10 feet above the finished ground surface. Is this correct?

e. Dwg CS311 includes Detail A4 – Wildlife Fence Fabric Detail. Please confirm our interpretation that this project does not require a Wildlife Fence to be provided. Response: a. Yes, corresponding sliding gate detail is B1/CS311.

b. Sliding gate is manual. Conduit stub outs, as noted on E-103, Note #19, shall be provided for future conversion of the sliding gate to an automated sliding gate.

c. Sliding gate is manual. Conduit stub outs, as noted on E-103, Note #19, shall be provided for future conversion of the sliding gate to an automated sliding gate.

d. Gate shall be 10'-0" tall, plus 12" of barbed wire at the top and top of fence fabric 10'-0" above finish ground. Drawing SC311 has been revised to correct the discrepancy.

e. Wildlife Fencing fabric for the permanent perimeter fence is required for this project.

9. With regard to typical details on Dwg E-502, please clarify the following:

a. Detail C4 shows a typical Padmount Transformer Detail. However, the Notes (provided above the detail) describe a different type of arrangement that includes a 72" x 54" x 36" deep enclosure with 4" thick concrete walls and a 6" thick slab. Since there is a conflict between the Notes and the drawing, please clarify what is to be provided by the Contractor.

b. The Notes above Detail C4 explain that the purpose of the Detail is to delineate JCP&L and Work at the Transformer, but the notes do not stipulate which party furnishes and installs the Transformer. It is our interpretation that the Transformer is be furnished and installed by JCP&L.

Please clarify this delineation of responsibility.

c. Detail A2 is a Typical Aircraft Ground Point. Above the sectional view is what appears to be a plan view, showing an elliptical shape. Please clarify the intent of the elliptical shape. Is it an opening? Is it a cover?

d. Detail A4 is for a Typical Taxiway Guidance Sign. The Notes do not appear to be complete:

words appear to be missing. Please take a look and provide revised wording.

e. With regard to the Typical Taxiway Guidance Signs, please provide recommended manufacturers and make and model numbers that would be acceptable with the Government.

Response: a. Detail C4 delineates what the contractor and JCP&L are responsible for. The note above the detail is what is in JCP&L's design standard. The pad shall meet JCP&L's requirements, please follow that note for bidding.

b. Per JCP&L standards, they provide the transformer.

c. Detail A2 indicates a top view of the size of the opening for access to the "hook". No cover is required.

d. Detail A4 is a standard detail provided by the Government. If information is missing, then please indicate what is missing or confusing.

e. The base does not have a standard vendor. Contractor shall provide an FAA approved Type L-858 Guidance Sign.

10. Appendix C is not in the specifications, please provide. Response: Appendix C is included in this amendment.

11. A-211: With regard to the Overhead Coiling Doors for the new Storage Building, please clarify the following:

a. Article 2.2.1.1 of Section 08 33 23 specifies thermal insulation for the Overhead Doors. Yet, the Storage Building is not insulated, as per Key Note #3 on Dwg A-211. Please clarify whether or not the Overhead Doors need to be insulated.

b. Please confirm that the color of the Overhead Doors will be a standard color provided by the manufacturer, such as: white, grey, or beige. Response: a. Disregard the thermal requirements for the door. Coiling doors to be uninsulated. Specifications has been revised accordingly.

b. Per A-601, see comments on door schedule. Finish to be Dark Bronze.

12. The door finish schedule shows a hardware set 1B for the storage building. Specification Section 08 71 00 Door Hardware does not list this 1B hardware set. Please advise as to the requirements for hardware set 1B? Response: The notation has a typo in the specification and has been corrected, Hardware set 1B on drawings is correct. Hardware 18 corrected to 1B.

13. The equipment legend on I-101 indicates a (SB1) Smart Board and (TV1) Television. Is the contractor to provide these items or are they government furnished? If the contractor is to provide these items please provide a specification or basis of design? Please clarify? Response:

Please refer to the FF&E package and provide all items identified on the purchase forms.

14. Drawing I-101 lists a (CM1) Coffee Maker. Is this to be provided by the contractor? Specification section 11 31 13 Electric Kitchen Equipment does not list a Coffee Maker. If the contractor is to provide this coffee maker please provide a specification or basis of design? Please clarify?

Response: Please refer to the FF&E package and provide all items identified on the purchase forms.

15. I-601: Specification 12 21 00 Window Blinds section 2.1 Window Blinds indicates "Provide aluminum vertical louvers 6 inch in length for each color. Provide 6 inch sample of horizontal blind slats in each color specified." Section 2.2.2 Horizontal Blinds goes on to 2.1.1.2 Controls indicate "The slats shall be tilted by a transparent tilting wand, hung vertically by its own weight, etc."

Section 3.2 Window Treatment Placement Schedule indicates "All exterior windows include vertical blinds." The drawing I-601 reference a Hunter Douglas Window Blind. Please clarify if a vertical or horizontal window blind is required? Response: Per users, vertical blinds are required.

16. I-601: The specifications calls for Aluminum slats for the window blinds. Drawing I-601 implies Hunter Douglas as a MFG. We understand that Hunter Douglas only makes a fabric vertical blind and not an aluminum blind. Please provide the model number of the Hunter Douglas blind being specified or clarify the material to be used? Response: Based on our information Hunter Douglas Architectural does produce aluminum vertical blinds.

17. Drawing CP101 depicts the 'Military/Emergency Fuel Truck Pavement' as a 6" Bit. Pavement.

Please clarify that this note on CP101 should instead indicate a 6" PCC Pavement to match detail C4/CP500 and the other misc civil & joint layout drawings that indicate PCC. Response: The Military/Emergency Fuel Truck Pavement is to be 6" PCC Pavement, detail C4/CP500.

Drawing CP101 has been revised.

18. The CP series drawings indicate that the 'Fuel Truck Parking' area south of the Army Apron Pavement is a 6" Bit. Pavement; however, the CS series drawings imply that this same Fuel Truck Parking area is a concrete pavement per the shading. Please clarify if this Fuel Truck Parking area south of the Army Apron Pavement is a bituminous pavement or if it is a concrete pavement and please provide the appropriate section detail to reference. Response: The Military/Emergency Fuel Truck Pavement is to be 6" PCC Pavement, detail C4/CP500.

Drawing CP101 has been revised.

19. Key Note #3 on Dwg CU101 makes reference to the placement of Bollards at the new Fire Hydrant, but the number of Bollards are not specified. Please clarify how many Bollards are required for the New Fire Hydrant and provide a typical plan detail to indicate the arrangement.

Also, please confirm that the New Bollards are not required for existing Fire Hydrants that are to remain. Response: Bollards shall be required for new fire hydrants only. Two (2) bollards per hydrant along parking lot, space 2'-0" min from hydrant. Bollards shall not be located directly in front of hydrant outlet. Note 3 on CU101 has been revised.

20. 02 82 13.00 10 An Independent Air Monitoring Firm will be hired to perform the Air Monitoring Requirements for the Asbestos Abatement Work for existing Building #4427. The personnel employed the Air Monitoring Firm will not be employed by the Asbestos Abatement Contractor and will not be performing any of the abatement work and will not be supervising the Abatement Contractor. Therefore, please clarify that the Industrial Hygienist employed by the Independent Air Monitoring firm will not need to be a person that has "Contractor/Supervisor" Training Accreditation, as per the Qualifications described for the Abatement Contractor's Industrial Hygienist in Article 1.6.2.d on page 10 of Specification Section 02 82 13.00 10. Response: If the independent air monitoring is ONLY collecting air samples and is NOT providing any oversight, then Contractor Supervisor training is not needed.

21. A-603 Wall type 5A: What is the height of wall type 5A. Response: 4'-0" high to top of phenolic, section on A-603 has been revised.

22. I-101 Conf Rm TB3: The TB3 Conference Table: Can you please clarify the power / data requirements for the table? How many electrical and data ports on the surface are needed?

Response: Two power/data ports should be specified for this table. Furniture Order Form has been updated to reflect this requirement.

23. In Bid Schedule Item No.11/Option 6 defines that "All work (includes all plant, labor, and material) for the purchase delivery and installation of flight equipment lockers as outlined in Appendix C."

But We were not able to find Appendix C or any detail regarding flight equipment lockers in bid documents. Please advise. Response: Appendix C is included in this amendment.

24. The bid schedule Item 0011 Option 6 indicates pricing required to purchase, delivery and installation of flight equipment lockers as outlined in Appendix C. No Appendix C has been provided. Please provide Appendix C? Response: Appendix C is included with this amendment.

25. Subcontractors in the area are asking if another site visit would be considered? Some site and demolition subcontractors just hearing of the project has asked? Response: Please refer to prior amendment for additional site visit.

26. Item #0002 on bid schedule calls for all site work excluding Apron Pavement and Associated features. Please advise where on bid schedule do we include these excluded items. Response:

Please refer to the revised bid schedule.

27. Please advise which Item No. on Bid Schedule do we include the Demolition of Bldg 4427.

Response: Please refer to the revised bid schedule.

28. Block 10 of the SF1442 indicates that a hard copy of the bid is to be submitted at Federal Plaza, New York, NY. Would the Government consider utilizing an email submission with the hard copy submitted by express delivery within one or two days? Response: No, no e-mail submissions will be accepted.

29. Is the demolition of building 4427…

This is the start of the file's text. The full file is on GovTribe.