About this file

Amendment 0003

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W16ROE60211044

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Revise Specification Sections 00 73 00, 31 24 00.00 18 and 01 74 19.

2) Provide response to bidder request for information.

NOTE: Bidders must acknow ledge receipt of this amendment by date specified in the bid (or as amended) by one of the follow ing methods:

In the space provided on the SF 1442, by separate letter, or by signing block 15 below .

FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE

LATE BID, LATE MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304)

See additional changes on the Continuation Sheet, hereby attached.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-May-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-16-B-0001

X 9B. DATED (SEE ITEM 11)

29-Apr-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-May-2016

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS-16-B-0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0003

Fire Island Inlet to Montauk Point Fire Island Stabilization Project

Fair Harbor to Seaview Contract 3A

Amendment No.3

To Bidders The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED and REISSUED:

-None

2. The following DRAWINGS have been ADDED:

- None

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

-None

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

-None

3. The following SPECIFICATION SECTIONS have REVISED but NOT REISSUED:

SECTION 00 73 00

-Add the additional sentence at the end of Paragraph 8. PHYSICAL CONDITIONS, Subparagraph C “Robert Mosses Causeway (Fire Island Inlet Bridge); a 20 ton weight limit will be in effect and any appropriate overload permits will be obtained through the New York State Department of Transportation, Regional Traffic Engineer, Traffic and Safety.”

SECTION 00 73 00

Revise Paragraph as below

1. Paragraph 2: ORDER OF WORK

Replace Paragraph 2 in its entirety as below:

The contractor shall proceed with the placement of beach fill and dune construction in a continuous manner along the shoreline from the east to the west, or as directed by the Contracting Officer.

The work in Robert Moses State Park, CLINS 0004 and 0005, must be the first increment of beachfill placement.

The contractor shall establish and work within approximately 500-1000 foot wide beach work zone/closure areas, one work zone at a time. No community will be left without pedestrian access to the beach at any time. Within each work zone/closure area, the contractor shall first remove any existing dune crossover structures. Immediately following the removal of an existing dune crossover structure, an on-grade mesh stabilization mat will be placed approximately where the existing dune crossover was removed, from the landward limit of work to 15 feet seaward of the seaward toe of the new dune design template, to be used as temporary pedestrian access.

Timber pilings for the new pedestrian crossovers will be installed prior to the placement of dune material in a community, in advance of beach fill placement and dune construction operations. Minimal excavation and regrading of existing topography will be allowed for the installation of new timber piles.

Immediately following the timber pile installation, the on-grade mesh stabilization mats will be replaced from the landward limit of work to 15 feet seaward of the seaward toe of the new dune design template, to be used as temporary pedestrian access. Mesh stabilization mats will be removed no more than 24 hours prior to new dune construction.

After beachfill and dune placement completion and acceptance of a new dune section within a work zone/closure area, the contractor shall place/replace the on-grade mesh stabilization mats, at all cross-over locations shown in the plans, from the landward limit of the new crossover to 15 feet seaward of the seaward toe of the dune, to be used as temporary pedestrian dune crossovers prior to proceeding to the next work zone/closure area. The on-grade mesh stabilization mats shall remain in place and be maintained for the community to access the beach until the initiation of the new timber dune crossover decking structure at each location. Within three (3) weeks after acceptance of a specific new dune section, the contractor shall complete the associated new timber dune crossover decking structures within that work zone/closure area, and reopen the new crossovers to the community for pedestrian use. Timber decking for all dune crossover structures within a previously established work zone shall be completed prior to decking work start in the next established work zone.

SECTION 31 24 00.00 18

-Revise Paragraph 2.2.4 in its entirety as given below:

“2.2.4 Slopes The dredge cuts in the borrow area shall not have side slopes steeper than 1 on 3. Borrow area entrance and exit slopes shall not be steeper than 1 on 3. Borrow area must have a uniform bottom elevation.”

SECTION 01 74 19

Add the following to Paragraph 1.3 Management, after sentence three:

“Contractor is required to have appropriate piping plover monitoring experience (or shorebird monitoring experience), as necessary, which requires approval by the NYSDEC and/or USFWS.”

Questions and Answers:

(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only ”and do not revise the solicitation, plans or specifications.)

RFI #1: Question:

As listed in Supplementary Conditions of Section 00 73 00 the Contractor is allowed 300 days to complete the work, but the Contractor cannot start beach fill until after September 6th, 2016 with a must complete date of not later than 31st March 2017.

a) If the Contractor were to have to be complete with the beach fill by March 15th 2017, and still allowed 300 days to perform the work then that means NTP would be issued on or before 05/19/2016 which is prior to the bid date. Can the Government clarify these dates and correct them in the Contract documents accordingly.

Answer #1:

Beach fill placement and demobilization work needs to be completed as described in paragraph Section 00 73 00, paragraph 1. Other work can be completed after 31 March 2017.

RFI #2: Question As stated in paragraph 1.3 Management of section 01 74 19 of the Project Specifications the Environmental Monitor shall be responsible for instructing workers and overseeing/documenting results of the Waste Management Plan for the project.

a) Is the Contractor required to provide this Monitor?

b) If so can the Government clarify what the qualifications would be for this position?

Answer #2:

SECTION 01 74 19 has been modified as noted above:

“Contractor is required to have appropriate piping plover monitoring experience (or shorebird monitoring experience), as necessary, which requires approval by the NYSDEC and/or USFWS.”

RFI #3: Question As stated in Paragraph 2.2.4 of Section 31 24 00.00 18 Page 7 the Borrow Area shall have slopes not steeper than a 1 on 5.

As shown on Page C-109 in the borrow area cross section the slopes are 1 on 3.

a) Can the Government verify the slope requirements and advise the Contractor accordingly?

Answer #3:

Paragraph 2.2.4 of Section 31 24 00.00 18 was revised in this amendment.

RFI #4: Question As according to the synopsis listed on the FBO website for the project it consist of placing up to 1,404,000 cubic yards of material but as according to the bid schedule issued within the Contract Documents, Line items 0002 for 1,404,000, line item 0004 for 200,000 and line item 0005 for 20,000 combined add up to be 1,624,000 cubic yards of material.

a) Is this the amount the Contractor should anticipate placing or should the Contractors pricing be indicative of placing 1,404,000 cubic yards.

Answer #4:

The synopsis in the FedBizOps is for information only. Quantities have been provided in Amendment 2 with changes made in the bid schedule.

(End of Summary of Changes)